Quiz Planning
If a worker works 9 hours a day for 6 days per week, what is the productivity loss per week (in percentage)? 20% 0% 10% 5%
10%
What is a common period for short interval schedules? 2 week period 4 week period 3 week period 2 or 3 week period
2 or 3 week period
What activity of the following is the last one to be completed? 1. Site mobilization 2. Foundation 3. Roof 4. Closing temporary utilities 3 1 4 2
4
If a worker works 8 hours a day for 6 days per week, what is the productivity loss per week (in percentage)? 10% 5% 2% 0%
5%
Compared to the master project schedule, short interval schedules show____. A lower level of details A higher level of details
A higher level of details
Assume that A is a predecessor of B. Which statement is correct? A occurs before B A and B occur simultaneously B occurs before A
A occurs before B
CSI format is: A standard hierarchy of activities To determine activity relation type To determine activity duration All of them
A standard hierarchy of activities
What is true about increasing the number of starting point method? Work overtime Adding more workers into the same Add another crew to work the same task in another area
Add another crew to work the same task in another area
When you expected that the activity is likely to be performed during the raining season, what will you do with the estimated duration based on RS Means? Subtract some time from the estimated duration Add some time to the estimated duration. Nothing
Add some time to the estimated duration.
A critical activity has: Zero float The same early start and early finish All of them No flexibility
All of them
A good updated schedule shows: Responsibility All of them Delays Effects of changes
All of them
What are the reasons to accelerate a project? Avoid impact of bad seasonal weather All of them Completion time bonuses To do other projects
All of them
What information to should included in short interval schedules? Drawing approvals Material testings Material delivery Number of workers All of them
All of them
What are possible causes of schedule update? Bad weather All of them Design changes Logic changes
All of them bih
Which is an appropriate match between schedule type and project stages? Baseline - Detailed design As built schedule - Feasibility Milestone schedule - Preliminary design As-planned schedule - Construction
Baseline - Detailed design
Which information is needed to estimate duration? Estimated productivity Both Work quantity
Both
What formats of a schedule file are commonly accepted by a 4D scheduling platform? Both of them .csv (comma separated values) .mpp (MS Project)
Both of Them
To request for a time extension, what you need to do is: Both of them Prove that the event directly affects critical activities. Prove that the delay is out of control of the contractor.
Both of them
Which statement is true about a compensable delay? Both of them Caused by the owner. Time extension will be granted if requested.
Both of them
WBS can be used to: Calculate duration of activity Break a complex project into manageable and quantifiable work Determine start and finish dates
Break a complex project into manageable and quantifiable work
What to do if an activity is too long? It is fine Present it as one single bar Break it into multiple activities
Break it into multiple activities
Project finish milestone is when: Certificate of Occupancy is received Whenever the contract requests Punch list is developed Major works are completed
Certificate of Occupancy is received
Activity logics is dependent on: Review time Activity names Construction methods
Construction methods
What is not true about permit activities? Consume resources Consume time Controlled by government agencies
Consume resources
Which are the reasons why the owner does not want to grant a time extension? Just want to stick with the contract. Cost increase Create difficulties to the project.
Cost Increase
When reducing project duration, we need to... Crash one or more critical activities at a time. Crash the longest activity. Crash only one critical activity at a time.
Crash one or more critical activities at a time.
Select the correct statements. Crashing always increases project cost. Crashing increases labor cost. Crashing does not impact overhead cost
Crashing increases labor cost.
Which statements are true about crashing? Crashing always increases the total project cost. Crashing is the process of reducing activity duration Working overtime does not necessarily help crash an activity All of them
Crashing is the process of reducing activity duration
Select the correct statements. Direct cost does not include equipment cost. Project overhead is the indirect cost that is not related to the project. Salary for administrative staff is not a part of the project cost. Direct cost includes labor, equipment, and materials.
Direct cost includes labor, equipment, and materials.
Building permit will allow the contractor to: Do electrical and mechanical work Deliver equipment Test equipment
Do electrical and mechanical work
Which statement is NOT true? Activity duration determination is an estimate process. Activity duration is the best guess you can have. Duration estimate is alway accurate.
Duration estimate is alway accurate.
A 4D-BIM is the integration of cost into a 3D model. False True
False
Acceleration increases indirect cost. True False
False
An activity can be presented as two bars in a bar chart schedule. False True
False
Doubling a crew size can double productivity. True False
False bih
Which is an appropriate activity for a small housing project? East footing formwork Footing formwork West footing formwork
Footing Formwork
Which is an construction activity? As-built preparation Formwork All of them Purchasing concrete
Formwork
Activity duration ____ preparation time. Does not include Correct! Includes
Includes
What is NOT true about contingency? Higher contingency should be assigned to activities with high risks. It helps to avoid extending working time of an activity. It reduces the risk of exceeding the total contract time.
It helps to avoid extending working time of an activity.
What reason for using PDM for scheduling? It has a timescale integrated It is easy to develop even for complex projects It is easy to understand It shows logics
It shows logics
Which of the following is NOT a reason to do a schedule? Keep the scheduler busy Because the contract requires it Identify problems on paper Determine completion date
Keep the scheduler busy
Which statement is TRUE? Quantity estimates are very uncertain. None of them Productivity is exactly the same as the national average, no adjustment is needed.
None of Them
Who is not a project stakeholder? Subcontractor Contractor Owner None of them Designer
None of Them
What states are not true about crowding? Can not help to reduce duration. None of them Can maintain production rate while accelerate project.
None of them
With an unavoidable (excusable) delay, a time extension can be granted only if the delay was on critical activities. None of them. It is dependent on the contract provisions. True False
None of them. It is dependent on the contract provisions.
What document typically defines the start date of a contract? Notice to Proceed Contract Drawings Proposal
Notice to Proceed
Which are common ways to specify contract duration? Number of non-working days Number of allowed calendar days Both of them
Number of allowed calendar days
RS Means can provide us with the national ___ averages. Project delay Activity quantity Productivity
Productivity
What happens if you delay one activity on the critical path? Project is accelerated Nothing happens Project is delayed
Project is delayed
What types of projects tend to use a working-day schedule? Private projects Public projects Both of them
Public Projects
Which action is recommended when the project is delayed? Try to accelerate the project and not need to inform the owner that issue. Report the delays to the client. Do nothing.
Report the delays to the client.
Who estimates the duration of activities performed by a subcontractor? General contractor The owner Subcontractor
Subcontractor
When should you use your own company data instead of RS Means? The company data is sufficient and reliable. Never. RS Means is always more accurate.
The company data is sufficient and reliable.
The primary criticism of bar charts is that: They can't be used to compare actual progress with planned They don't indicate duration They do not show clear dependencies between activities They don't show activities occurring at the same time
They do not show clear dependencies between activities
For an avoidable (non-excusable) delay, ____. Time extension is not likely to be granted. Time extension can mostly be granted.
Time extension is not likely to be granted.
A 3-week schedule can show those tasks accomplished in the previous week. False True
True
A 4D-BIM is the integration of schedule into a 3D model. False True
True
Daily crew planning schedule can show the utilization of each worker on an hour-by-hour basis. True False
True
Daily schedules can show the use of equipment for every hour during the day. True False
True
Lag time is the period that an activity must be delayed after it's predecessor finish. True False
True
Lead time is the period that an activity can start earlier before it's predecessor finish. False True
True
Liquidated damages are based on a reasonable estimate of actual damages. False True
True
Navisworks is a 4D-BIM modeling tool. True False
True
Project time has a linear relationship with indirect cost. True False
True
4D scheduling can .... Visualize the work sequence in a 3D environment. Show project payment overtime.
Visualize the work sequence in a 3D environment.
When doing time-cost tradeoff problem, when to stop the iteration process? When cost exceeds saving. when the project time reaches minimum.
When cost exceeds saving.