A product Increment must be released to production at the end of each Sprint. Bookmark this question A) True B) False

...

When a Development Team is having trouble delivering a working Increment because they don't understand a functional requirement, what should they do? Bookmark this question Choose one answer. A) Defer the work to a more appropriate Sprint. B) Add a specialist to the Development Team. C) Partially complete the functionality, and discuss the remaining work at the Sprint Review. D) Collaborate with the Product Owner to determine what is possible and acceptable.

...

When is a Sprint over? Bookmark this question A) When all Product Backlog items meet their definition of "Done." B) When the timebox expires. C) When the Product Owner says it is done. D) When all the tasks are completed.

...

The Product Owner makes sure the team selects enough from the Product Backlog for a Sprint to satisfy the stakeholders. Bookmark this question A) True B) False

b

A Sprint Retrospective should be held: Bookmark this question A) At the end of the last Sprint in a project or a release. B) At the beginning of each Sprint. C) At the end of each Sprint. D) Only when the Scrum Team determines it needs one.

c

How much work must a Development Team do to a Product Backlog item it selects for a Sprint? Bookmark this question A) Analysis, design, programming, testing, and documentation. B) As much as it can fit into the Sprint. C) As much as it has told the Product Owner will be done for every Product Backlog item it selects in conformance with the definition of "Done". D) The best it can do given that it is usually impossible for QA to finish all of the testing that is needed to prove shippability.

c

Sprint burndown charts are an efficient tracking tool because they show: Bookmark this question A) How much effort has gone into a Sprint. B) How many Product Backlog items remain. C) An estimate of the total work remaining for the Sprint. D) How many hours have been worked by each Development Team member.

c

The purpose of a Sprint is to produce a done Increment of product. Bookmark this question A) True B) False

t

The Development Team informs the Scrum Master that the IT manager has asked for a status report during the Sprint. The Scrum Master will: Bookmark this question A) Ask the Product Owner to send the manager the report. B) Create and deliver the report to the manager herself. C) Tell the Development Team to fit the report into the Sprint Backlog. D) Tell the Development Team to figure it out themselves. E) Talk to the IT manager and explain that progress in Scrum comes from inspecting an Increment at the Sprint Review.

a

Which three of the following are feedback loops in Scrum? Bookmark this question Choose three answers. A) Daily Scrum B) Sprint Retrospective C) Refinement Meeting D) Sprint Review E) Release Planning

abd

Which of the following are true about the Product Owner role? (Choose 3 answers) Bookmark this question Choose 3 answers. A) The Product Owner can be influenced by a committee. B) Multiple people can share the Product Owner role on a Scrum Team. C) The Product Owner is one person. D) The Product Owner role can be played by a committee or a team of people. E) The Product Owner is accountable for ordering the Product Backlog.

acd

What are three benefits of self-organization? Bookmark this question A) Increased creativity B) Increased rule compliance C) Increased accuracy of estimates D) Increased commitment E) Increased self-accountability

ade

Which of the following are true about the length of the Sprint? Bookmark this question Choose two answers. A) All Sprints must be 1 month or less. B) The length of the Sprint should be proportional to the work that is done in between Sprints. C) Sprint length is determined during Sprint Planning, and should hold the time it will take to code the planned features in the upcoming Sprint, but does not include time for any testing. D) Sprint length is determined during Sprint Planning, and should be long enough to make sure the Development Team can deliver what is to be accomplished in the upcoming Sprint. E) It is best to have Sprints of consistent length throughout a development effort.

ae

Which two things should the Development Team do during the first Sprint? Bookmark this question Choose 2 answers. A) Develop at least one piece of functionality. B) Analyse, design, and describe the complete architecture and infrastructure. C) Make up a plan for the rest of the project. D) Analyse, describe, and document the requirements for the subsequent Sprints. E) Create an Increment of potentially releasable software.

ae

Who determines when it is appropriate to update the Sprint Backlog during a Sprint? Bookmark this question A) The Scrum Team B) The Development Team C) The Project Manager D) The Product Owner

b

The Product Owner is not collaborating with the Development Team during the Sprint. What are two valuable actions for a Scrum Master to take? Bookmark this question A) Stop the Sprint, send the Product Owner to a course and restart. B) Coach the Product Owner in the values of Scrum and incremental delivery. C) Bring up the problem in the Sprint Retrospective. D) Inform the Product Owner's functional manager. E) Nominate a proxy Product Owner.

bc

Choose three responsibilities of a self-organizing Development Team. Bookmark this question Choose three answers. A) Report daily progress to stakeholders. B) Do the work planned in the Sprint Backlog. C) Increase velocity. D) Pull Product Backlog items for the Sprint. E) Reorder the Product Backlog. F) Set the time for the Daily Scrum.

bcf

What is the role of management in Scrum? Bookmark this question A) To continually monitor staffing levels of the Development Team B) To identify and remove people that aren't working hard enough C) To facilitate the Scrum Teams with insights and resources that help them improve D) To monitor the Development Team's productivity

c

Why does a Development Team need a Sprint Goal? Bookmark this question A) A Sprint Goal only gives purpose to Sprint 0. B) A Sprint Goal ensures that all of the Product Backlog items selected for the Sprint are implemented. C) The Development Team is more focused with a common yet specific goal. D) Sprint Goals are not valuable. Everything is known from the Product Backlog.

c

When many Scrum Teams are working on the same product, should all of their increments be integrated every Sprint? Bookmark this question A) No, that is far too hard and must be done in a hardening Sprint. B) No, each Scrum Team stands alone. C) Yes, but only for Scrum Teams whose work has dependencies. D) Yes, otherwise the Product Owners (and stakeholders) may not be able to accurately inspect what is done.

d

Which does a self-organizing Development Team choose? Bookmark this question A) Stakeholders for the Sprint Review B) Product Backlog ordering C) Sprint length D) How to best accomplish its work E) When to release, based on its progress

d

During the Daily Scrum, the Scrum Master's role is to: Bookmark this question A) Make sure that all 3 questions have been answered. B) Lead the discussions of the Development Team. C) Manage the meeting in a way that each team member has a chance to speak. D) Teach the Development Team to keep the Daily Scrum within the 15 minute timebox. E) All of the above.

e


Ensembles d'études connexes

Unit 107 Electrical science and technology

View Set

Pharmacology - Chapter 59 - Otic Drugs

View Set

VFC SURGERY, VFC Artificial Intelligence, VFC Blockchain, VFC Toronto Startups

View Set

Anatomy Female Reproductive System

View Set

Mod 4 1-5 Peds Growth and Development/Infants

View Set

Chapter 6: Ischemic Heart Disease

View Set

Live Virtual Machine Lab 3.2: Module 03 Install and Configure DHCP and DNS Servers

View Set

Chapter 07: Life Insurance Beneficiaries

View Set