MGT 450 Ch 9 Reducing Project Duration
fast tracking a project
Doing critical path activities in parallel that were originally planned in series Moves activities in parallel to become at least partially concurrent Disadvantage -Often results in rework -Usually increases risk -Requires more attention to communication
time reduction decision
Go for optimum cost-time? - it depends -Risk must be considered -Logic of the cost-time procedure suggests managers should reduce the project duration to the lowest total cost point and duration -How far to reduce the project time from normal toward optimum depends on sensitivity of the project network
owner take more responsibility
Identify tasks customers can do themselves Homeowners frequently use this to reduce costs on home improvement projects Costs are lowered but original scope is the same
crash time
Is the SHORTEST estimated length of time in which the activity can be completed. The greatest time reduction possible under realistic conditions
slope (of cost duration graph)
Knowing the slope of activities allows managers to compare which critical activities to shorten The less steep the slope of an activity, the less it costs to shorten one time period A steeper slope means it will cost more to shorten one time unit
crash point
Maximum time an activity can be compressed
reduce project scope option (for accelerating completion)
Most common response to meeting unattainable deadlines Reduction in functionality of the project Can lead to big savings in time and money, it may come at a cost of reducing the value Key to reducing scope without reducing value is to reassess the true specifications of the project
determining activities to shorten
Most difficult task in constructing a cost duration graph is finding the total direct costs for specific project durations over a relevant range Central task is to decide which activities to shorten how far to carry the shortening process -Managers need to look for critical activities that can be shortened with the smallest increase in cost per unit of time Rationale for selecting critical activities depends on identifying the activity's normal and crash times and corresponding costs
sensitivity
Network is sensitive if it has several critical or near critical paths Network is insensitive is it has a dominant critical path
constructing (project cost duration graph)
Three major steps are required: 1.Find total direct costs for selected project 2.Find total indirect costs for selected project durations 3.Sum direct and indirect costs for these selected durations
crashing
Time / cost trade off Objective: determine the shortest project completion time based on crashing the activities that result in the smallest increase in total project cost Adding more resources to critical path while maintaining scope -Move resources from noncritical task -Add more resources -People -Equipment -Work overtime Disadvantage: Additional cost
Using (the Project Cost-Duration Graph)
Valuable in comparing any proposed alternative or change with the optimum cost and time Creation of such a graph keeps the importance of indirect costs in the forefront of decision making Calculating in the pre-project planning phase without an imposed duration is the first choice because normal time is more meaningful Creating the graph in the project planning phase with an imposed duration is less desirable because normal time is made to fit the imposed date and is probably not low cost
outsource project activities (or even entire project)
When estimates exceed budget, makes sense to not only re-examine the scope but also search for cheaper ways to complete the project Instead of relying on internal resources, it would be more effective to outsource segments or even entire projects, opening up work to external price competition
brooks law
adding more people to a late project makes the project later
unforeseen delays (rational for reducing duration)
adverse weather, design flaws, and equipment breakdown cases substantial delays midway in the project getting back on schedule requires compressing time on some of the remaining critical activities
establish a core project team
assigning professionals full time avoids hidden costs of multitasking devote undivided attention to a specific project singular focus creates a shared goral that can bind a diverse set of professionals into a highly cohesive team capable of accelerating completion
incentive contracts (rationale for reducing duration)
bonuses for early completion reduction of time rewarding both project contractor and owner
project constraints
cost constraint time constraint scope constraint quality constraint
pressure to reassign resources (rationale for reducing duration)
cost of compressing the project can be compared with the opportunity costs of not releasing key equipment or people
use critical chain management
designed to accelerate project completion Difficult to apply CCPM midstream in a project Requires considerable training and a shift in habits and perspectives
schedule overtime
easiest way to add more labor avoid additional costs of coordination and communication fewer distractions outside normal working hours disadvantages: -hourly worker usually paid time and a half, double for weekends and holidays -sustained by salaried employees may incur intangible costs such as divorce, burnout, and turnover
time to market (rationale for reducing duration)
intense global competition and rapid technological advances have made speed a competitive advantage companies have to spot new opportunities, launch project teams, and bring new products or services to marketplace in a flash survival depends on rapid innovation and adaptability
add resources
most common to assign additional staff and equipment to activities doubling workforce will not necessarily reduce completion time by half additional workers increase communications requirements additional delay of training and catch up
overhead costs (rationale for reducing duration)
sometimes high overhead costs are recognized before the project begins prudent to examine the direct costs of shortening the critical path vs the overhead cost savings usually there are opportunities to shorten a few critical activities at less than the daily overhead rate
imposed deadlines (and contract commitments -rationale for reducing duration)
statements become project objectives without any consideration of the problems or costs of meeting such a date Duration time is set while project is in its concept phase before or without any detailed scheduling of all the activities in the project Leads to a higher cost project than one that is planned using low cost and detailed planning Quality is sometimes compromised
outsource project work
subcontract an activity -subcontractor may have access to superior technology to expertise that will accelerate the completion
crash
term for shortening the duration of an activity or a project beyond when it normally can be done
rationale (for reducing project duration)
time to market pressures unforeseen delays incentive contracts imposed deadlines and contract commitments overhead costs pressure to reassign resources to other projects
do it twice - fast and correctly
when in a hurry, building a "quick and dirty" short term solution then go back and do it the right way
improve project team efficiency
Team may be able to improve productivity by implementing more efficient ways to do their work Can be achieved by improving the planning and organization of the project or eliminating barriers to productivity such as excessive bureaucratic interference and red tape
brainstorm
Team members can offer tangible ways for reducing project costs Just ask if there is a cheaper, better way
crash cost
The estimated cost to complete the activity in the crash time
assumptions underlying graph
1. Cost-time relationship is linear 2. Normal time assumes low-cost efficient methods to complete the activity 3. Crash time represents a limit- the greatest time reduction possible under realistic conditions 4. Slope represent cost per unit of time 5. All accelerations must occur within the normal and crash times
steps to crash a project
1. Determine crash cost per time unit and maximum crash time for each task 2. Draw the network 3. Determine all paths through the network 4. Determine the lengths of all paths 5. Try to reduce the length of the CP by 1 -Find activity on CP with lowest crash cost -Crash the activity by 1 time unit, if possible 6. Reduce the length of all paths with this activity 7. Are there activities that can still be crashed? If yes go to step 3
resources NOT constrained (options for accelerating project completion)
1. add resources 2. outsource project work 3. schedule overtime 4. establish a core project team 5. do it twice - fast and correctly
Resources ARE constrained (options for accelerating project completion)
1. improve project team efficiency 2. fast tracking 3. use critical chain management 4. reduce project scope 5. compromise quality
project cost duration graph
A graph that plots project cost against time; it includes direct, indirect, and total cost for a project over a relevant range of time. used to compare additional cost alternatives for benefits
direct costs
Are costs that assigned directly to a work package and activity Examples: labor, materials, equipment, sometimes subcontractors Represent normal costs (low-cost, efficient methods for a normal time) Because direct costs are assumed to be developed for normal methods and time, and reduction in activity time should add to the costs of the activity Sum of the costs of all the work packages or activities represents the total direct costs for the project
linearity assumption
Assumes the cost for crashing each day is constant Reasonable but quick comparisons can be made using the linear assumption
indirect costs
Continue for the life of the project Are costs that cannot be associated with any particular work package or activity if indirect costs are a significant percentage of the total project costs, reductions in project time can represent vert real savings Examples: overhead costs such as supervision, administration, consultants, and interest
factors beyond cost (to be considered w/ choice of activities to crash)
Cost-time crashing method relies on choosing the cheapest method for reducing duration factors: First, the inherent risks involved in crashing particular activities Some are riskier to crash than others Second, the timing of activities needs to be considered -Crashing an early activity may be prudent if there is concern that subsequent activities are likely to be delayed, and absorb the time gained Third, crashing frequently results in overallocation of resources -Resources required to accelerate a cheaper activity may suddenly not be available -Resource availability, not cost, may dictate which activities are crashed Fourth, the impact of crashing would have on the morale and motivation of the project team needs to be assesses
cost is the issue (not time)
Especially true for fixed bid project where profit margin is derived from the difference between the bid and actual cost of the project Each dollar saved is a dollar in your pocket Commonly used options for cutting costs are: -reduce project scope -have owner take more responsibility -outsource project activities (or even entire project) -brainstorm
normal cost
Estimated cost to complete the project in normal time
normal time
Estimated length of time required to perform the activity under normal conditions (low-cost, efficient methods), according to the project plan
compromise quality
Rarely acceptable or used May reduce time of an activity on the critical path
fast tracking
Rearrange the logic of the project network so that critical activities are done in parallel (concurrently) rather than sequentially Most common way for restructuring activities is to change a finish to start relationship to a start to start relationship Has risk - Late design changes can produce wasted effort & rework
reduce project scope (if cost is the issue not time, cut cost)
Scaling back scope can gain time Delivering less than what was originally planned produces savings Time is not the issue, you do not need to focus on critical activities
