A contractor's project being analyzed by PERT has an estimated time for the critical path of 120 days. The sum of all activity variances is 81; the sum of variances along the critical path is 64. What is the probability that the project will take 130 or more days to complete?
0.1057
An activity on a PERT network has these time estimates: optimistic = 2, most likely = 5, and pessimistic = 10. What is its expected activity time?
5.33
The difference between AON and AOA networks is that:
A. nodes consume no resources or time in AOA networks. B. nodes designate activities in AON, while arrows designate activities in AOA. C. both are acceptable in practice; however, Microsoft Project uses AON. D. AOA networks sometimes require dummy activities. E. ALL OF THE ABOVE ARE CORRECT
Which of the following statements regarding CPM is true?
All activities on the critical path have their LS equal to the maximum EF of all immediate predecessors.
Which of the following is an example of competing on quick response?
A firm's products are introduced into the market faster than its competitors' products.
The ________ distribution is used by PERT analysis to calculate expected activity times and variances.
Beta
Which of the following represents the FIRST step to crash a project?
Compute the crash cost per week for each activity in the network.
Which of the following statements regarding CPM networks is true?
If a specific project has multiple critical paths, all of them will have the same duration.
Which of the following activities are NOT part of project scheduling?
Make sure all necessary activities are finished in proper sequence and on time.
Which of the following statements regarding critical paths is true?
On a specific project, there can be multiple critical paths, all with exactly the same duration.
The main difference between PERT and CPM is that:
PERT employs three time estimates for each activity.
Which of the following is NOT a characteristic of services?
Standardized product
Which of the following is an advantage of PERT and CPM?
Straightforward concept and not mathematically complex.
A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B and of C. B is an immediate predecessor of C. The activity durations are Aequals=4, Bequals=3, Cequals=8.
The critical path is A-B-C, duration 15.
Which of the following statements concerning CPM activities is false?
The late finish of an activity is the earliest late start of all preceding activities.
Which of the following statements regarding PERT times is true?
The optimistic time estimate is an estimate of the minimum time an activity will require.
pessimistic time
The time an activity will take assuming very unfavorable conditions is:
Which of the following statements is an assumption PERT makes regarding the probability of finishing the project on time?
Total project completion times follow a normal probability distribution.
Which of the following statements best characterizes delivery reliability?
a company that always delivers at the promised time
Dummy activities
are used when two activities have identical starting and ending events.
Which of the following activities at a commercial bank is NOT an operations activity?
auditing
The ability of an organization to produce goods or services that have some uniqueness in their characteristics is:
competing on differentiation.
Which of the following international operations strategies involves a high degree of centralization?
global
Which operations function at a manufacturing facility strives for the efficient use of machines, space, and personnel?
industrial engineering
The critical path of a network is the
longest time path through the network.
Which of the following is NOT one of the factors that fosters specialization and worldwide supply chains?
marketing
The most realistic estimate of the time required to complete an activity is referred to as what?
most likely time
Which of the following international operations strategies uses decentralized authority with substantial autonomy at each business?
multidomestic
Which of the following is used for computations in CPM?
normal time
What is the practice of transferring a firm's activities that have traditionally been internal to external suppliers?
outsourcing
Among the following, critical path and slack time analysis MOST help
pinpoint activities that need to be closely watched
Gantt charts are
planning charts used to schedule resources and allocate time.
Which of these is NOT an advantage of outsourcing?
potential creation of future competition
The creation of goods and services is referred to as:
production.
Which of the following is NOT considered to be one of the three primary functions that all organizations perform?
research and development
Which of the following activities at an airline is NOT an operations activity?
sales
PERT analysis computes the variance of the total project completion time as
the sum of the variances of all activities on the critical path.
Which of the following is an example of a "hidden" production function?
transplanting a liver
The three phases involved in the management of large projects are
planning, scheduling, and controlling.