Program Evaluation and Review Technique (PERT)

अब Quizwiz के साथ अपने होमवर्क और परीक्षाओं को एस करें!

Standard Deviation

the square root of the sum of the variances of the individual activities.

Mean project duration

a straightforward sum of critical path activity means

When is PERT used

projects where there is insufficient historical knowledge for estimating project activity duration's

Standard Deviation

provides an indication of the uncertainty associated with the mean estimate of activity duration.

PERT Recognizes what

the probabilistic nature of activity duration's as opposed to the deterministic assumptions that CPM incorporates.


संबंधित स्टडी सेट्स

CH. 4 SOCIAL ENGINEERING, PHYSICAL, AND PASSWORD ATTACKS

View Set

C. The Government of the Philippines in Transition

View Set

2020 Chapter 11 - Compensating Executives

View Set

Marketing Channels Chapter 17: Marketing Channels for Services

View Set

9.6 - Registration of Securities Under the Uniform Securities Act

View Set

Module 14: The Endocrine System: Thyroid Gland Hormones and Function

View Set

Chapter 16: Postoperative Nursing Management

View Set