What button is pressed to save the displayed address and exit address mode?
*
The sounder bell connects to which terminals?
+3 , -4
2 wire smoke detectors should be tied to this terminals
-1
What 2 keys should be pressed for 3 seconds when setting a keypad address?
1 & 3
Where should the home premises be connected to on a RJ31x?
1 & 8
What zone should 2-Wire smoke detectors be on?
1 Z+/-
What size plastic grommets must a control panel have?
1/2 inch
What kind of outlet should the power supply be plugged into?
110 VAC unswitched
What is the master Code after defaulting the panel?
1234
Additional standby battery required for fire alarm installs?
12V 17.2ah
Battery charge voltage ?
13.8 VDC, max charge current 650mA
How many button zones can a vista 20p have installed?
16
How many PRM devices can be supported in an XH install?
2 max PRM devices per install
What value resistor is required for a 2 wire smoke detector?
2,000 ohm resistor
Which terminals are tip on an alarm panel?
21 & 23
Connect phone line Direct connect cable wires these terminals
21-24
Which terminals are ring on an alarm panel?
22 & 24
What is the standby battery duration required for fire installs?
24 hour
Which terminal is used for earth ground on an alarm panel?
25
What is the max number of keypads supported in a takeover?
3
What is the PIM light sequence when starting up?
3 blinks every 5 seconds
How many transmitter zones does a vista 15p support?
34
If installed, how many amp fuse should be used?
3A
What size battery fuse should be used?
3amp
Where should incoming telco be connected on a RJ31x?
4 & 5
What is the minimum battery capacity required for emergency burglary standby?
4 hours
Pim panel lead must be connected to what teminals?
4,5,6 and 7
How many transmitter zones does a vista 20p support?
48
How many wired zones can be installed on a vista 15p?
6
Non compatible Honeywell keypads will need to be replaced with which model keypads?
6160
What is the max number of zones an XH takeover can cover?
64
What resistor value should a 4 wire smoke detector use?
750 to 10,000 ohm resistor
How many wired zones can be installed on a vista 20p?
8
How many zones does the Honeywell 20P support?
8
How many wired zones can a single PRM support?
8 wired zones
How many OHM resistor is need for the external alarm sounder?
820
How long does a PIM stay in pairing mode?
90 seconds
How do you determine the total standby load on the battery?
Add 100mA to the total of AUX power output and remote keypad current
What must be done if a customer has partitions in a takeover?
Advise the customer we do not support partitions and either cancel the call or eliminate the partition.
What is a prerequisite for wires in a control panel?
All wire must be jacketed cable
What variety of smoke detectors do PRM devices support?
Both 2 and 4 wire smoke detectors
Which 4 wire smoke detector can NOT be taken over?
Brinks 2112ATL/TL
What function does the #6 do on a honeywell keypad?
Bypass
What function does the #9 do on a honeywell keypad?
Chime
What function does the #8 do on a honeywell keypad?
Code
EOLR zones should be used on this type of installation
Commercial
What are 2 approved wire connections for control panels?
Dolphin B Connectors or Wire nuts
Double balanced zone should never be installed here
Fire exits
Which two security panel models can be taken over?
Honeywell Vista 15/20P firmware version 3.0 or newer
In a panel swap installation, which model of panel is installed?
Honeywell Vista 20P
Which 3 keypads are compatible with XFINITY Home System Takeover?
Honeywell6148, Honeywell6150, Honeywell6160
Where should a PIM not be installed?
Inside the panel
What function does the #7 do on a honeywell keypad
Instant
What is the purpose of a sounder?
Makes noise in an Alarm event
What function does the #4 do on a honeywell keypad?
Max
Which NFPA code requires the condition of panel wiring to be neat and workman-like.
NFPA 70
Equipment should be installed to this standard.
NFPA 72 chapter 2
What function does the #1 do on a honeywell keypad?
Off
What is the part number for the PRM power transformer?
RE012-16
What is the part number for the PRM battery?
RE043
What function does the * do on a honeywell keypad?
Ready
What colors are the PIM panel lead colors?
Red, Black,Green, and Yellow/White
What is the National Electrical Code for a take over installation?
Sections 396 and 800 Part II
Wired contacts on a detached garage, workshop, or the like may be taken over and included on our system IF it meets this NEC code.
Sections 396, and 800 Part II
What function does the #3 do on a honeywell keypad?
Stay
If an existing system is powered down upon arrival, which 4 requirements must be met?
System must not use any RF keypads, Powering-up the system must only require the battery to be connected and transformer plugged-in, No signs of over heating with transformer, System indicators must show green" or "ready" upon powering-up
What function does the #5 do on a honeywell keypad?
Test
What supply's current to the alarm sounder?
The Battery
What label must be attached and visible on a honeywell keypad?
UL Notice
How many smoke detectors can a PRM support?
Up to 16 depending on current draw
When must fire alarm verification be disabled?
When using smoke detectors with the PRM
What type of keypad is required for a PRM install?
Zigbee
When Installing supplemental power what will be required?
a transformer and battery
This must be installed if the total power draw of the security system exceeds 600mA.
additional supplemental power
What is the typical battery life for sealed lead acid battery?
around 3 years typically
What function does the #2 do on a honeywell keypad?
away
Double balanced zone should be only used in what zones
burglary zones
What must be replaced with service date of installation written on it in a takeover?"
control panel battery
What should be connected to ECP terminals 4-7 in an alarm panel?
keypads and other addressable devices
What type of connections are not supported for system upgrades on control panels?
scotch locs
What terminal should the red wire from the PIM go to?
terminal 4
What terminal should the black wire from the PIM go to?
terminal 5
What terminal should the green wire from the PIM go to?
terminal 6
What terminal should the yellow/white wire from the PIM go to?
terminal 7
What should be done with an old control panel battery?
terminals taped and left with customer
What is the maximum distance between the power supply and control during a PRM install when #22 gauge wire is used?
up to 20 ft
What is the maximum distance between the power supply and control during a PRM install when #20 gauge wire is used?
up to 30ft
What is the maximum distance between the power supply and control during a PRM install when #18 gauge wire is used?
up to 50 ft
What firmware version is required for Honeywell Vista panels for a takeover?
v3.0 or newer
Zone doubling and double balanced zone can only be done on this panel
vista 20p
What zone should 4-Wire smoke detectors should go to?
zone 2