The ? drawing will show items such as fabricated structures for steel towers. a.architectural b.mechanical c.specification d.structural
D. Structural
Freehand drawings are made to exact scale and are then transferred to the blueprints. Select one: True False
False
In the field, if minor adjustments have to be made to the blueprint, an entirely new blueprint must be drawn. Select one: True False
False
The word "blueprint" applies only to those prints that are blue with white object lines. Select one: True False
False
Different types of drawings are used because one type of blueprint cannot have all the information. Select one: True False
True
In total, blueprints are a specific set of instructions and are usually drawn to scale. Select one: True False
True
A detailed drawing that shows how a cable pull manhole should be installed is a(n) ? drawing. a.architectural b.mechanical c.specification d.structura
a.architectural
The drawing that would show the floor plans for a substation relay shed is the ? drawing. a.architectural b.construction c.mechanical d.structura
a.architectural
Blueprints are normally printed in size C, which would measure ? . a.16" × 21" b.21" × 30" c.30" × 21" d.30" × 48"
b.21" × 30"
The ? direct and coordinate the efforts of everyone involved in the project. a.architects b.blueprints c.pre-job meetings d.work orders
b.blueprints
The original blueprint for a project is kept at the ? office and is placed in a permanent file. a.customer's b.engineer's c.general contractor's d.inspector's
b.engineer's
A ? sheet is normally used to qualify the information presented in a certain portion of the blueprint. a.detail b.specification c.staking d.work order
b.specification
A construction strip map printed at 10.5 in. × ? would be size F. a.21" b.30" c.36" d.48"
c.36"
The ? tree area shown on a clearing drawing means that any tree, when it falls, will reach the line. a.caution b.crossing c.danger d.hazard
c.danger
Blueprints are kept as part of a permanent file because they furnish the basis for future alterations and ? of the system. a.decommissioning b.expansion c.maintenance d.transfer
c.maintenance
If a control box was delivered in a "knocked down" condition, one would look at the ? drawing to see how it is assembled. a.as-built b.construction c.mechanical d.specification
c.mechanical
Blueprints are used as part of a ? record once the job is finished. a.construction b.completion c.permanent d.photographic
c.permanent
If an existing road needs to be improved in order to get to a transmission tower site, the road would be shown on a ? drawing. a.clearing b.construction strip c.plan and profile d.vicinity map
c.plan and profile
The drawing that would show property ownership is the ? drawing. a.construction b.land contract c.plan and profile d.vicinity map
c.plan and profile
A crew charged with hauling material for a new transmission line would use a construction ? map to find the site location. a.area b.road c.strip d.vicinity
c.strip
Blueprints and specification sheets are designed to furnish specific dimensions, assembly arrangements, construction details, and ? . a.lists of local suppliers b.lists of qualified contractors c.local building codes d.pictures of parts
d.pictures of parts
Blueprints are a ? of every aspect of the job. a.collection b.listing c.summary d.view
d.view
A certified professional ? approves blueprints and specification sheets so that authorized and uniform information is furnished. a.contractor b.draftsman c.engineer d.inspector
C. Engineer