ARSP2 EXAM 3

Lakukan tugas rumah & ujian kamu dengan baik sekarang menggunakan Quizwiz!

Critical Path Method

A common type of construction schedule, also called the__________, which depicts a continuous chain of activities showing both activity durations and the relationship of the activities.

Workers engaged in excavations at least one half meter deep or deep enough to cause danger, shafts, earthworks, underground works or tunnels

According to DO No. 13, Section 12, which of the following is not specialized instruction and training?

40 hours

According to DO No. 13, Section 13, how many hours does it take to finish the basic construction safety and health training course prescribed by the BWC?

If the water is used in common drinking areas, it should be stored in closed containers from which the water is dispensed through taps or cocks. Such containers should be cleaned and disinfected at regular intervals not exceeding 30 days.

According to DO No. 13, Section 16, which of the following is incorrect in the working facilities provided by the employer by the employer to its construction works?

Chairperson

According to Department Order No. 13 Series of 1998, he shall convene the Construction Safety and Health Committee at regular intervals so as to effectively and efficiently monitor the implementation of the Construction Safety and Health Program.

Henry Grantt

An American engineer and project management consultant, published the grantt chart around 1910.

Construction Planning

Below are the different phases of the project except one.

Detailed Schedules

Breaks major work activities down into small tasks so the schedule can be analysed in greater detail.

All of the above

During the construction, the general constructor must ensure that the following conditions are met or complied with:

DO 13 Series of 1998

GUIDELINES GOVERNING OCCUPATIONAL SAFETY AND HEALTH IN THE CONSTRUCTION INDUSTRY

6

Identify the float in the diagram shown.

24 hours

In case of any dangerous occurrence or major accident resulting in death or permanent total disability, the concerned employer shall initially notify the DOLE Regional Office within how many hours from occurrence?

Work breakdown structure

It helps to develop your activity list which organize and identify the work of the project by breaking each division into separate work packages.

Critical Path

It includes those activities that have zero days of float.

Daily field reports

It is intended to simplify the capture of some fundamental information needed to track job progress and confirm that various project requirements are being met.

Logs

It is used to track a number of regular activities occurring on the job site

Emergency health provider

Means any person or organization who is credited or recognized by the DOH and who can provide the same or equivalent emergency health services as an emergency hospital, including emergency treatment of workers on site, emergency transport and care during transport of injured workers to the nearest hospital, with adequate personnel, supplies and facilities for the complete immediate treatment of injuries or illnesses.

Occupational Safety and Health Standards

OSHS means what?

Visual records

Progress photos help document construction methods, highlight and capture problem areas, and supplement written reports.

Rule 1080

Provision of personal protective equipment (PPE) shall be in accordance of what rule in OSHS?

Heavy Equipment

Refers to any machine with engine or electric motor as prime mover used either for lifting, excavating, leveling, drilling, compacting, transporting & breaking works into construction site, such as but not limited to crane, bulldozer, backhoe, grader, road compactor, prime mover and trailer, with minimum operating weight and horsepower of rating 1000 KG and 10 HP, respectively

Tool box meeting

Refers to daily meeting among workers and their respective supervisors for the purpose of instruction, discussion and proper briefing on the planed work, the assessment of past work, the possibility or actual occurrence of accidents and other related matters.

Safety Personnel

Section 7 in DOLE talks about?

Activity-on-arrow, activity-on-node

There are two techniques used to develop a network diagram. The firs is called ____________ and the second is called the __________.

Administrative activities

These activities are mostly associated with contract administration tasks such as permitting, submittals, inspections, and testing.

Procurement activities

These activities are primarily associated with obtaining materials and equipment for the project. They can be some of the crucial activities in the schedule and, if not properly considered, can cause major delays on the project.

Production activities

These activities identify task that are associated with the physical building of the project.

Production, Procurement, Administration

These are types of activities that must be planned and included in the schedule.

Diaries

This tracking tool can take the form of a simple spiral notebook or something more elaborate, such as a day planner or electronic organizer. It is used to track all of the day's events in a summarized fashion and in the individual's own words.

Float

What is the amount of leeway available to start or complete an individual schedule activity before it affects the planned project completion?

Schedule Calculations

What part of scheduling stage determines exactly how much float or slack you have in the noncritical activity times?

Forward Pass

What scheduling techniques is used to calculate an activity's early start and early finish?

Section 09

What section does "Construction Safety Signages" belong?

Summary Schedules

_____________ group activities under broader headings such as mobilization, site work, foundation, and rough framing.

Web cameras

________________ record images or live video streams from remote digital cameras and are usually accessible for viewing on a project website.


Set pelajaran terkait

CH 19 Blood vessels MAP questions

View Set

IS 438: Practice Exam 1 - True/False

View Set

Simulate Exam Part 1 (Law), Simulate Exam Part 2 (Law)

View Set

Geometry - Using Deductive Reasoning

View Set