CAPM Practice Questions

Lakukan tugas rumah & ujian kamu dengan baik sekarang menggunakan Quizwiz!

Question 32: Which tool or technique is commonly used in the Collect Requirements process to generate as many ideas as possible in a short period? A) Brainstorming B) Focus groups C) Surveys D) Benchmarking

A) Brainstorming Explanation: Brainstorming is a tool used in the Collect Requirements process to facilitate the generation of a broad range of ideas and requirements from stakeholders and team members quickly.

Question 12: Which document describes the necessary information to determine whether a project is worth the required investment? A) Business case B) Project charter C) Project management plan D) Scope statement

A) Business case Explanation: The business case provides the necessary information to determine whether a project is worth the investment. It typically includes an analysis of the benefits, costs, risks, and opportunities associated with the project.

Question 19: Which process involves defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive project management plan? A) Develop Project Management Plan B) Direct and Manage Project Work C) Monitor and Control Project Work D) Close Project or Phase

A) Develop Project Management Plan Explanation: The Develop Project Management Plan process involves defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive project management plan that directs project execution and control.

Question 24: In which process group are the project's objectives established and the feasibility of achieving them assessed? A) Initiating B) Planning C) Executing D) Monitoring and Controlling

A) Initiating Explanation: In the Initiating process group, the project's objectives are established, and the feasibility of achieving these objectives is assessed to ensure a clear understanding and alignment with stakeholders' needs and expectations.

Question 2: Which document defines how a project is executed, monitored, controlled, and closed? A) Project management plan B) Project charter C) Project scope statement D) Project status report

A) Project management plan Explanation: The project management plan is a comprehensive document that defines how the project is executed, monitored, controlled, and closed. It integrates and consolidates all subsidiary plans and baselines.

Question 28: What does the critical path method (CPM) help a project manager determine? A) The shortest path to complete the project B) The most cost-effective path to complete the project C) The least risky path to complete the project D) The path with the most resources required to complete the project

A) The shortest path to complete the project Explanation: The critical path method (CPM) is used to identify the longest sequence of dependent tasks in a project and determine the shortest possible duration to complete the project.

Question 29: What is the primary purpose of creating a project scope statement? A) To document the project objectives, deliverables, and work required B) To outline the project's budget and resource requirements C) To establish the project's communication plan D) To define the project's quality metrics

A) To document the project objectives, deliverables, and work required Explanation: The project scope statement is essential for documenting the project's objectives, deliverables, and the detailed work required to create those deliverables, providing a basis for future project decisions and scope control.

Question 15: What is the primary purpose of the Validate Scope process? A) To formalize acceptance of the completed project deliverables B) To define the detailed project scope C) Monitor the status of the project and product scope D) To update the project scope baseline

A) To formalize acceptance of the completed project deliverables Explanation: The Validate Scope process involves formalizing acceptance of the completed project deliverables, ensuring they meet the agreed-upon requirements and are formally approved by stakeholders.

Question 30: What is the primary purpose of the Monitor and Control Project Work process? A) To track, review and regulate the progress and performance of the project B) To initiate the project and define its objectives C) To develop the project team and assign tasks D) To close the project and confirm that all work is completed satisfactorily

A) To track, review and regulate the progress and performance of the project Explanation: The Monitor and Control Project Work process is essential for tracking the project's progress, reviewing its performance against the plan, and making necessary adjustments to keep the project on track toward its objectives.

Question 4: What is a work breakdown structure (WBS)? A) A list of activities required to complete the project B) A hierarchical decomposition of the total scope of work C) A graphical representation of the project timeline D) A chart showing the project organization

B) A hierarchical decomposition of the total scope of work Explanation: The WBS is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create required deliverables.

Question 8: What is a risk register? A) A document outlining the project's approach to risk management B) A log of all risks identified along with their responses and status C) A report detailing the potential impacts of project risks D) A chart that ranks the probability and impact of risks

B) A log of all risks identified along with their responses and status Explanation: The risk register is a project document where all identified risks, along with their characteristics, responses, and status, are recorded and monitored throughout the project lifecycle.

Question 11: What is the process of obtaining team members, goods, and services to complete project work? A) Plan Resource Management B) Acquire Resources C) Develop Project Team D) Conduct Procurements

B) Acquire Resources Explanation: The Acquire Resources process involves obtaining the team members, equipment, materials, and supplies needed to complete project work.

Question 13: In which type of organizational structure do team members report to several bosses? A) Functional B) Matrix C) Projectized D) Composite

B) Matrix Explanation: In a matrix organizational structure, team members report to both functional and project managers, resulting in multiple reporting lines.

Question 5: Which type of organizational structure features a blend of functional and projectized characteristics? A) Functional B) Matrix C) Projectized D) Composite

B) Matrix Explanation: In a matrix organizational structure, team members report to both functional managers and project managers, blending characteristics of functional and projectized structures.

Question 3: In which process group is the project scope defined? A) Initiating B) Planning C) Executing D) Monitoring and Controlling

B) Planning Explanation: The project scope is defined in the Planning process group, where detailed planning including scope definition takes place to outline the project boundaries.

Question 18: What is the process of numerically analyzing the effect of identified risks on overall project objectives? A) Qualitative Risk Analysis B) Quantitative Risk Analysis C) Risk Management Planning D) Risk Response Planning

B) Quantitative risk analysis Explanation: Quantitative risk analysis involves numerically analyzing the probability and impact of identified risks to assess their effect on project objectives and to determine the overall risk exposure.

Question 17: Which type of power is derived from a project manager's personal attributes, such as charisma, skills, and experience? A) Legitimate power B) Referent power C) Expert power D) Coercive power

B) Referent power Explanation: Referent power is derived from the personal attributes and charisma of the project manager, which can influence and inspire team members.

Question 20: What is the primary output of the Identify Stakeholders process? A) Stakeholder management plan B) Stakeholder register C) Communication management plan D) Change log

B) Stakeholder register Explanation: The primary output of the Identify Stakeholders process is the stakeholder register, which contains all identified stakeholders, their information, assessment data, and classification on how they may be engaged throughout the project.

Question 31: What is the primary purpose of the Plan Communications Management process? A) To ensure timely and appropriate collection of project information B) To develop an appropriate approach for project communications C) To distribute project information in accordance with the plan D) To update stakeholders on project progress

B) To develop an appropriate approach for project communications Explanation: The Plan Communications Management process aims to develop an appropriate plan for project communications, determining the information and communications needs of the stakeholders.

Question 1: What is the primary purpose of the project charter? A) To outline the project budget B) To formally authorize the project C) To document the project scope D) To assign project team members

B) To formally authorize the project Explanation: The project charter is a document that formally authorizes a project, providing the project manager with the authority to apply organizational resources to project activities.

Question 21: What is the primary purpose of the Performance Integrated Change Control process? A) To approve or reject changes to the project charter B) To manage changes to the project scope, schedule, and cost baselines C) To ensure that all changes are recorded in the project management plan D) To update the project's work breakdown structure

B) To manage changes to the project scope, schedule and cost baselines Explanation: The Perform Integrated Change Control process is crucial for reviewing all change requests, approving changes, and managing change to the project deliverables, organizational process assets, project documents, and the project management plan, particularly focusing on scope, schedule, and cost baselines.

Question 6: What is the main purpose of a stakeholder register? A) To document the interests of stakeholders B) To record all identified stakeholders and their information C) To describe the strategies for stakeholder engagement D) To outline the communication plan for stakeholders

B) To record all identified stakeholders and their information Explanation: The stakeholder register is a project document that includes the identification, assessment, and classification of a project's stakeholders. It contains information such as stakeholders' interests, involvement, and potential impact on project success.

Question 10: Which conflict resolution technique involves finding a temporary solution that satisfies all parties? A) Forcing B) Withdrawal C) Compromise D) Collaboration

C) Compromise Explanation: Compromise involves finding a temporary solution that partially satisfies all parties involved. It's often used when a quick resolution is needed, and the parties are equally powerful.

Question 16: What type of dependency is established based on the relationship between project activities and external events or conditions? A) Mandatory dependency B) Discretionary dependency C) External dependency D) Internal dependency

C) External dependency Explanation: External dependencies involve a relationship between project activities and external events or conditions not within the team's control, such as regulatory approvals or supplier deliveries.

Question 14: Which tool or technique is used in the Develop Project Team process to improve team interaction and increase team cohesiveness? A) Interpersonal and team skills B) Training C) Team-building activities D) Ground rules

C) Team-building activities Explanation: Team-building activities are used in the Develop Project Team process to improve team interaction, enhance communication, and increase cohesiveness among team members.

Question 26: What is the primary function of a decision tree in project management? A) To schedule project tasks B) To allocate project resources C) To analyze the consequences of decisions along with their associated risks and rewards D) To track project costs

C) To analyze the consequences of decisions along with their associated risks and rewards Explanation: A decision tree is used in project management to analyze the potential outcomes of different decisions, allowing for a visual representation of the consequences, risks, and rewards associated with each decision path.

Question 22: What is a histogram used for in project management? A) To show the relationship between two variables B) To display the project's schedule and milestones C) To illustrate the frequency distribution of a set of data points D) To represent the hierarchy of project tasks

C) To illustrate the frequency distribution of a set of data points Explanation: In project management, a histogram is used to illustrate the frequency distribution of variables or data points, such as the number if occurrences of a defect within a specific period.

Question 25: What is the primary goal of quality assurance activities? A) To inspect the final product to ensure it meets quality standards B) To identify quality problems after the product is developed C) To integrate quality standards into the project design and development processes D) To manage the quality of project communications

C) To integrate quality standards into the project design and development processes Explanation: The primary goal of quality assurance is to integrate quality standards into the project processes, ensuring that the project will produce outputs that meet the necessary quality requirements.

Question 27: Which conflict resolution technique involves collaborating with the conflicting parties to meet their interests and find a win-win solution? A) Smoothing B) Forcing C) Compromising D) Collaborating

D) Collaborating Explanation: The collaborating technique aims to work with the conflicting parties to understand their interests and needs fully, finding a solution that satisfies everyone involved, often resulting in a win-win situation.

Question 7: Which process involves monitoring the status of the project and product scope and managing changes to the scope baseline? A) Plan Scope Management B) Validate Scope C) Define Scope D) Control Scope

D) Control Scope Explanation: The Control Scope process involves monitoring the status of the project and product scope and managing changes to the scope baseline, ensuring the project remains within its defined boundaries.

Question 9: In project management, what is the term for an uncertain event of condition that, if it occurs, has a positive or negative effect on project objectives? A) Issue B) Constraint C) Assumption D) Risk

D) Risk Explanation: A risk is an uncertain event or condition that, if it occurs, has a positive (opportunity) or negative (threat) effect on at least one project objectives (such as as scope, schedule, cost, or quality).

Question 23: Which type of estimate provides a range that reflects the estimate's accuracy, such as "-10% to +25%"? A) Definitive estimate B) Parametric estimate C) Three- point estimate D) Rough order of magnitude (ROM) estimate

D) Rough order of magnitude (ROM) estimate Explanation: The Rough Order of Magnitude (ROM) estimate provides a range, such as "-10% to +25%", indicating a broad estimate that reflects the current level of project detail or accuracy of the estimate.


Set pelajaran terkait

International Style of Architecture

View Set

Comptia 220-801 12.4.12 Practice Test Questions

View Set

Section 2.6) Tax and Retirement Planning

View Set

Pro First Aid Advanced CPR/AED/First Aid w/ Multiple Choices

View Set

Conservation Biology Exam 1 (Tiebout)

View Set

Chemistry and Urinalysis/Body Fluids

View Set

Flower Culture Flash Cards - Produce Patch

View Set