DPWH PE
What is the durometer hardness for Elastomeric Bearing Pads which is 100% virgin chloroprene (neoprene) pads
60
One eligibility requirement for Contractors is to be a Filipino Citizen or at least __ Filipino owned partnership or corporation
60%
What is minimum dimension of square flags for STOP and GO
600mm
What is the minimum depth of roadside channel from the bottom of pavement
600mm
What is the width of the Stop Line in Rural Roads
600mm Rural Roads
What is the design speed for flat terrain of Tourism Roads
60kph
What is the minimum desirable length of Turnouts, unloading and loading bays, on National Roads
60meters
What is the length of the road widening from center of the road left and right side for Municipal Roads
6m
In horizontal alignment of roads and highways, what is the maximum algebraic difference of cross-over
7%
What is the length of road widening from center of the road left and right side for Provincial Roads
7.5m
What is the standard distance range for Road Warning Signs in advance of the construction site in rural areas
75-225m
In rural area, what is the minimum bridge pedestrian width
750mm
For buildings, the minimum concrete protection for reinforcement shall be __ clear for concrete deposited to the ground
75mm
What is the minimum days of stripping of Forms and Shores for suspended slabs in school buildings
8 days
When Borehole Drilling using Super Mud, what is the pH range of Pre-treat water with soda ash
8.0 - 10.0
What is the maximum jacking force for Pre-Stressed Girders
85%
When the spread footing located on a slope, the minimum distance from the lower edge of the footing to the sloping ground surface should be __
900mm
Once the project reaches an accomplishment of __ of the total contract amount, the procuring entity may create an inspectorate team to make preliminary inspection and submit a punch-list to the contractor in preparation for the final turnover of the project
95%
During interim progress billing, contracts with amount of more than 100 million can file a progress billing up to __ contracts that are below 100 million can only file up to __ of the contract amount
95%, 90%
Which of the following is NOT a type of bridge superstructure: Girder, Abutment, Deck Slab, Sidewalk
Abutment
After a typhoon, a dam measuring 250m suffered a 40m breach equivalent to P4.8 million. You found out that it is impossible to close the gap before the onset of rainy months, which may result in total collapse of the dam. If you are the Contractor's Project Engineering, what will you suggest to the DPWH PE
Armor the breached section with gabion-mattress and spur dike, to utilize gap as diversion channel
Who is the approving official if the Work Suspension Order is 85 calendar days
Assistant Secretary for Operations
These are rectangular piles which can take huge axial loads and high moments, ideal for boulder ground and alluvial soil but adaptable to most types of ground
Barrette Piles
It is measured from the back of backwall to back of backwall of the bridge
Bridge Length
It reflects Accomplishment-duration relationship in the project
Catch up schedule
What is issued to the Contractor by the DPWH to cover any increase/decrease in quantities of original work items in the contract
Change Order
It is design to control and direct traffic movement, usually turning
Channelizing Island
Which of the following is NOT a type of steel deck used on bridges namely steel jack arches, open panel and stiffened steel
Close Panel
Which of the following is NOT a type of Caisson Foundation: Pneumatic, Open, Close, Box
Closed Caisson
It is a temporary wall installed to exclude water to allow construction work within the area protected by the cofferdam
Cofferdam
It refers to a set of detailed rules to cover the processes and practices that should be utilized in a specific construction site in conformity with OSHC
Construction Safety and Health
This is where the computation of contract price escalation of a project that is awarded thru simplified bidding should be based and reckoned
Contract Approval
What kind of report are used to summarize the work progress for the immediate preceding month or quarter, usually contains a narrative section describing status of project, S-curve diagram, summary of contract time and change orders
Contract performance reports
What method is usually adopted when there is no visible evidence of termite infestation during soil poisoning
Cordoning
It provides access for equipment to the location of the foundation of the bridge
Craneway
What do you call the process of compressing the duration of a project in a PERT CPM/PDM
Crashing
Contract Time Extension may be granted only when the affected activities fall within the __ of the PERT/CPM or PDM network
Critical Path
What term is used to indicate the maximum length of a designated upgrade on which a loaded truck can operate without an unreasonable reduction in speed
Critical length of Grade
Dike height = free board + __
DFL
This is the guidelines on the Accreditation of Contractors' and Consultants' Project Engineers
DO No. 10 of 2019
This is where the computation of contract price escalation of a project that is awarded thru public bidding should be based and reckoned
Date of Bidding
What do you call additional support on steel sheet piles to support embankment of the abutment of a bridge embedded in the ground designed to increase load safety factor against overturning
Deadman
What do you call the scouring of bed material due to increased stream sediment transport capacity that results from an increase in the energy gradient
Degredation
A proposed flood control project has a mini-hydroelectric power component. However, the area is already being serviced by the National Grid Corporation of the Philippines (NGCP). Which of the following will be the best action to take for the DPWH Engineer
Delete mini-hydro power component
What do you call the discharge used to size the capacity of the bridge
Design Flood
What do you call the one that provides lateral support to the girder
Diaphragm
What method is usually adopted when there is visible evidence of termite infestation during soil poisoning
Drenching
This is equal to the tip elevation minus the "cut-off elevation" or bottom elevation of the Pile Cap
Driven Length
What should be conducted after the final inspection of a reported 100% accomplished project, before a certificate of final inspection is to be issued
Exit Conference
MELF means Maximum __ Flood Level
Experienced
Statement: Pouring permit for PCCP is the same from pouring permit on bridge structures
False
Statement: Splicing of PVC Sheet piles for revetment shall be allowed
False
Statement: When a contract is not mutually terminated, the contractor is still allowed to submit bids
False
What kind of report are used to document any corrective changes which occur in the field that would require departure from the plans and specifications and then provide the necessary information to understand the problem, decide of how tor resolve it and issue instructions to the field and serve as a source of document for variation order approvals
Field correction reports
This represents the payment of the remaining balance of the contract including the total retention after the completion of the project
Final Billing
Total amount of liquidated damages shall be deducted to the __
Final billing
Gradient/grades of roads, highways and bridges should be as __ as possible for economic reasons
Flat
For span lengths of 6-12meters, what bridge type shall be used as per Department Order No. 30 Series of 2011
Flat Slab
In identifying project location intended for asphalt pavement, which of the following criteria is not appropriate to recommend: Drainage facilities is well-maintained, Location is not in a typhoon belt area, Existing base course is stable, Floor-prone road section
Flood prone road section
What do you call the clearance between the Design Flood Level (DFL) or the Maximum Experience Flood Level (MEFL) and the (soffit) if the lowest member of the bridge superstructure
Free board
There are monthly or quarterly statements of time and cost for the project. The report documents all changes that have accrued since the beginning of the project regarding time and cost
General project status report
It's main job is to transfer loads to the column of the bridge upon which it rests
Girder
If the actual soil bearing capacity of School Building did not meet the required 96 kPa of soil bearing capacity, the implementing office may opt to perform/use the following except one: Micro-piles, Mat foundation, Bored Piles, H-Piles
H-Piles
What is used to emphasize to the approaching driver a marked change in the direction of travel and the presence of an obstruction
Hazard Marker Type HM
What do you call the depth of water above the culvert inlet bottom
Headwater
The main objective of the __ Dynamic Test is to determine pile Bearing Capacity
High Strain
Which of the following is not a function of a groin: Decrease the flow velocity, Regulates the flow direction, Decreases scouring effect, Increases flow velocity
Increase flow velocity
On simple curves, widening of curves should be applied on the __ edge only
Inside
What is the standard color of all DPWH steel bridges? International __
International Orange
You are to recommend measures to minimize inundation on the landslide of an overflowing river. Which of the following is not acceptable: Reduce the flood inflow to area by constructing spillways and retarding basins, Regulate the land use in the area, Install drainage facilities like pumping stations, Introduce dredging works
Introduce dredging works
The implementation of this Contractor's Project Engineer Accreditation shall take effect on __
January 4, 2021
Vertical Clearance for Bridges over Navigable Waterways is sum of the Highest Water Level (HWL) and Height of Vessel (HV) and the K factor. What is the constant value of the K-factor
K = 1.0m
Construction joints in floors shall be located within the __ of spans of slabs, beams, and girders. Joints in the girders shall be offset a minimum distance of two times the width of intersecting beam
L/3
What do you call the overlap between the first and second activity in PERT CPM/PDM
Lead Time
The BAC shall determine to its satisfaction whether the Bidder that is evaluated as having submitted the __ complies with and is responsive to all the requirements and conditions
Lowest Calculated Bid
It is the physical island at the center of a divided roadway separating traffic flows
Median Island
The ACI code gave a provision on structural integrity to perimeter beams is to splice continuous top bars at __ and splice continuous bottom bars at or near supports
Midspan
Lateral forces on building frames can be analyzed by approximate analytical methods, except one: Portal method, Factor method, Cantilever Method, Moment-Distribution Method
Moment-Distribution Method
Which of the following contractor category is not required for ISO 9000 Certification
None of the Above
If the actual condition of the soil in school building is susceptible to liquefaction, ground improvement technique may be performed except one: Permeation Grouting, Jet Grouting, Compaction Grouting, None of the Above
None of the above
What do you call the bridge with superstructure perpendicular to its substructure
Normal
It is the promotion and maintenance of highest degree of physical, mental and social well-being of workers in all occupation
Occupation Safety and Health
What is the periodic payment for contractor's progress billing
Once/month
What is the formula used in computing price escalation
Parametric
Groundsills are structures constructed __ to the flow of the river
Perpendicular
Compute the amount of Liquidated Damages (LD) given the following data: Remaining Scope of Work Amount is Php 1,000,000 and the contractor completed the remaining scope of work in 15 calendar days' time
Php 15,000
What do you call the component of a bridge that supports the bridge spans and is located to minimize the constriction of traffic or flow of water underneath the bridge
Pier
This is a kind of cut-off channel being constructed to carry 10% of a river discharge, and which subsequently develops capacity of up to 40%
Pilot Channel
What kind of reports are used to document events that occur at a plant or operation, such as concrete batch plant or bituminous plant
Plant inspector's report
For span lengths of 21-30meters, what bridge type shall be use as per Department Order No. 30 Series of 2011
Pre-Stressed Concrete Girder (PSCG)
What should be conducted if there is evidence of discrepancies on the actual elevation from those shown in the Plans
Pre-construction survey
What do you call the project scheduling technique used for DPWH Projects
Precedence Diagram Method
Who is the approving official for Work Suspension Order when the suspension period is up to 60 CD
Regional Director
To guide the blind, sidewalks should as much as possible follow straight forward routes with __ angle turns
Right Angle Turns
It is the graphical representation of the cumulative monthly cash flow of a project over its time duration
S Curve
What do you call the depth refers to the total depth of water from surface to a purge bed level
Scoured
Defective works in a project should be brought to the attention of the contractor by the Resident Engineer thru
Site Instructions
What do you call the bridge with superstructure not perpendicular to its substructure
Skewed
What do you call the distance between two intermediate supports of bridges
Span Length
Which of the following is not a type of flood control
Spear Dike
This is very suitable for shallow foundation and for areas wherein the hard strata lie 3m below the NGL for firm materials and 5m below the NGL for soft materials
Spread Foundation
If a project is abandoned by the contractor due to peace and order problems, what recommendation should immediately be submitted
Termination of Contract
Which does not fall under the condition when a change order can be issued
There are additional works which were not included as items of work in the original contract
It is the difference between the targeted accomplishment and the actual accomplishment at the end of a certain period, it is expressed in percentage and indicates the performance of project implementation
Time Slippage
Statement: For single span bridges, the bridge length is equal to the span length
True
Statement: No pipes shall be allowed to pass thru beams of school buildings vertically
True
Statement: No pipes shall be embedded in columns of the school buildings
True
What is the suggested type of Pre-Stressed Girder to be used when the span length is about 18m
Type III
What is the suggested type of Pre-Stressed Girder to be used when the span length is about 35m
Type VI
Who is the approving official for Work Suspension Order when the suspension period is 100 CD
Undersecretary for Operation
This is a method of determining steam discharge by measuring the cross-sectional area of the stream and its velocity with a current meter
Velocity Area
Which of the following is not a classification of a terrain
Volcanic
What do you call the portion of earth or base course materials left unleveled by a road grader during longitudinal grading operation
Window
Revetment are structures constructed __ to the flow of the river
parallel
What is the cross slope of the higher shoulder for roads and highways when the superelevation is 5%
-2%
What is the cross slope of the higher shoulder for roads and highways when the super elevation is 4%
-3%
Vertical alignment of roads shall require that for every degree of curvature over six degrees, the ruling grade shall be reduced by __
0.10%
What is the minimum preferred slope on pipe culverts
0.20%
For effective drainage, the slope of edge of pavement shall be less that or equal to __ between +-1.5% grade
0.3%
For service load design of bridges, what is the flexural stress in the extreme fiber stress in compression
0.4 f'c
Every building will be designed for lateral seismic forces. As a minimum, the design base shear (V = ZICW/Rw) will be applied to the structure and be distributed to the various levels of the structure. The factor Z (seismicity of the site) as used in the Philippines is __
0.4 for Zone 4
For Raised Median Island, Planting of Trees should not be permitted on High Speed Multilane Divided Highway and the surface level of soil fill shall be lower than the top of island - 50mm for island height less than or equal to __ and 10mm for island height greater than __
0.45m
No vertical curve is required when algebraic difference between grades is less than __
0.5%
If the shoulder is less than 2.0m, what is the setback distance of the Kilometer Post from the edge of the shoulder
0.50m
For roads and highways, what is minimum recommended width of curve widening
0.60m
Pipe culverts shall be laid at such grades that there will be a cushion of at least __ of fill over the top of the pipe
0.60m
Generally, what is the minimum freeboard allowance above the MEFL and DFL of revetments
0.6m
All doors for people with disability (PWD) shall have a minimum clear width of __ meter
0.90m
What is the minimum width of a curb cut-out
0.90m min
As per BP 344 requirement, what is the walking speed design on the crossings
0.90m/sec
What is the minimum diameter size of pipe culverts
0.910m
For buildings, what is the maximum of number of borehole for 200 m2 of the structure
1
The spacing of the bars at the column strips for school building shall not be more than __ slab thickness
1 1/2
What is the minimum Financial Capacity, Net Worth/Equity of a Class A Category AAAA Contractor in Pesos
1 billion pesos
As a minimum requirement for Bridge projects, __ bored pile(s) shall be tested representing each pile size
1 bored pile
For multi-span bridges, Pile Bearing Capacity Test shall be conducted __ at each abutment and 1 at every other pier
1 test
Defects Liability Period
1 year
What is the range of Spur Dike's top width
1-2m
What is the standard maximum height for traffic bollards
1.0m
All sidewalks/walkways for people with disability (PWD) shall have a minimum clear width of __ meter
1.20m
What is the minimum head pressure required to drill when Borehole Drilling Using Super Mud
1.20m
What is the minimum sidewalk width as per Accessibility Law BP 344 along national highways
1.20m
What is the standard dimension for Project Billboard
1.22m x 2.44m
For concave sections, what is the distance between spur dike times the length of spur (LS)
1.4 to 1.8 x LS
What is the minimum and maximum height of signages on walls and doors as per Accessibility Law BP 344
1.40m min, 1.60m max
What is the roadway cross slope for PCCP
1.50%
For school building, footing shall rest at least __ below natural grade line
1.50m
What is the minimum width of the refuge island and its total length
1.5m wide, 30m length
All embedded pipes for utilities etc. that pass thru beams shall not exceed 100mm in diameter or __ beam depth whichever is less, and no pipes shall be allowed to pass thru beams vertically
1/3
As per RA 11058, the General Contractor must provide one (1) Construction Safety and Health Officer for every __ units of Heavy Equipment assigned to the project site to oversee the effective compliance with the COSH program
10 units
What is the minimum STE individual years of experience for Class A Category AA Contractor
10 years
What is the minimum individual years of construction experience for Sustaining Technical Employee (STE) for all Classes and Categories of a Contractor
10 years
ICU Stage happens when the negative slippage of the project accomplishment is
10%
If, after fifty percent (50%) completion, the Works are satisfactorily done and on schedule, the amount of retention money will be limited to __ of the contract amount
10%
In no case however, shall the total sum of liquidated damages exceed __ of the contract price, in which event the contract shall be automatically be taken over by the procuring entity concerned or can be awarded to same qualified contractor through negotiated contract
10%
The procuring entity shall retain from each progress payment __ of such payment, referred to as the "retention money"
10%
Variation order should not exceed __ of the original contract price
10%
What is the maximum allowable grade for Barangay roads
10%
What is the negative slippage for "ICU stage"
10%
When Concreting of Bored Piles, overpouring in the quantity of __ of the theoretical volume is considered "in-order"
10-20%
What is the maximum amount for "selected" District Engineer to approved Program of Works, ABC, and plans like as-built and as-staked
100 million pesos
Topographic/hydrographic survey of river channel and flood plains upstream and downstream of the bridge site a distance five times the width of the river channel or atleast
100-200
No other billboards shall be allowed to be installed __ before and after all DPWH projects and in-between the project limits of within the road-right-of-way
100m
What is the maximum length of spur dike
100m
During re-blocking construction of PCCP, the breaking and restoration of pavement in 2-lane carriageway shall be limited to 1-lane and Not More than __ in Length at any time in Non-Urban Areas
100m max
Concrete Barriers need to be continuous or secured together, generally using steel pins and eyelets, with a maximum __ gap to ensure they perform satisfactorily
100mm
For roadway obstructions markings, what is the minimum width of the black and white stripes on the object markings
100mm
For school buildings, all embedded pipes for utilities etc. that pass thru beams shall not exceed __ in diameter or 1/3 beam depth whichever is less
100mm
The pavement thickness of Turnout, Unloading and Loading Bays, shall in no case be less than __ for asphalt and 230mm for concrete with supporting base layers
100mm
What is the maximum spacing center to center of adjacent rings of circumferential reinforcement in a cage of a standard two-meter RCPC
100mm
For Pre-Cast Concrete Curb and Gutter, minimum curb inlet interval (D) is __ in flooded areas and __ in other areas
10m flood areas, 20m others
The cut-off date of physical accomplishments to be reflected in Progress Billings shall be reckoned on the __ day of each month instead of the 25th day of the month
10th
Monthly accomplishment for any DPWH project shall constitute the works completed and accepted from the __ day of the preceding month up to the __ day of the current month
11th and 10th
How many High Tensile Strand used in Pre-Stressed Concrete Girders
12
What is the diameter of the High Tensile Strand used in Pre-Stressed Concrete Girders
12.7mm
From the time of project was bid to the issuance of notice to proceed, __ calendar days is required for a project to be entitled to contract priced adjustment
120 CD
In urban area, what is the minimum bridge pedestrian width
1200mm
When the AADT is greater than __ vehicles, paving of shoulder is necessary
1250 vehicles
If the length and width of the drainage area is equal to 50m and 100m respectively; what should be the length of the channel
136.80m
What is the minimum days of stripping of Forms and Shores for beams in school buildings
14 days
What is the maximum allowable single project cost for Small B Category C Contractor
15 million pesos
Warranty period for permanent structures as per RA 9184
15 years
Advance payment to the Contractor in an amount not to exceed __ of the total Original Contract Amount
15%
Terminal Stage happens when the negative slippage of the project accomplishment is
15%
What is the negative slippage for "Terminal Stage"
15%
What is the maximum allowable contract cost for Medium A Category B contractor
150 million pesos
For pre-painted metal sheets, what is the minimum end laps that shall be provided
150mm
What is the minimum bandwidth of the reflective tapes for traffic cones
150mm
What is the minimum diameter of Bridge drains
150mm
What is the length of the road widening from center of the road left and right side for National Roads
15m
What is the maximum length of bridge abutment
15m
What is the minimum Road-Right-of-Way (RROW) for Municipal Roads
15m
What is the maximum length of turnouts, unloading and loading bays, on National Roads
185meters
For cross sections, provide at every full station and at intermediate breaks on a scale of __
1:100
What is the vertical alignment scale for the road plan preparation
1:100
What is the horizontal alignment scale for the road plan preparation
1:1000
What is the maximum gradient for Curb Cut-Outs
1:12
What is the maximum gradient for sidewalk as per BP 344
1:20 or 5%
The RROW boundary marker posts shall be installed along the RROW limit line one each side of the road at ___ kilometer interval
1km
What is the minimum raised height required for signage/symbols labeling public rooms and places
1mm
In accordance with the requirements of Geotechnical Investigation, what is the minimum number of boring shall be provided for piers or abutments over 30m wide
2
Contractor shall shoulder all the expenses for the alteration and/or reconstruction of the structure and a fine of __ of the original total contract price, if they violated the minimum Vertical Clearance for Bridges over Navigable Waterways
2%
What is the minimum width of PCCP on farm to market roads per lane
2..5m
If the actual soil bearing capacity of the natural ground is less than 96 kPa at depth of 1.5m, what is the maximum depth of the isolated footing
2.0 meters
Pedestrian crossing markings at road intersections without channelized islands shall be placed outside the intersection area at least __ set back from the edge of road
2.0m
The minimum headroom between the pedestrian walking surface and bottom of girder of the structure like railway, flyover and bridge above shall be __
2.0m
What is the maximum free height of the PVC sheet pile for revetments to limit potential deflection
2.0m
What is the setback distance from the RROW Limit for Welcome Arches and Overhead Boundary Markers
2.0m
What is the maximum distance outside the shoulder for Kilometer Post from the edge of the road pavement
2.5m
For convex sections, what is the distance between spur dike times the length of spur (LS)
2.8 to 3.6 x LS
For combination of bored/steel sheet pile for bank protection, what is the minimum N-value capable developing the required ultimate bearing capacity
20
During bidding, the Bidder may sub-contract a material or significant portion of the goods which must not exceed __ of the contract price
20%
In an emergency, the Head of the Procuring Entity may authorize a Variation Order beyond 10% but not more than __ of the original contract price following the guidelines determined by Government Procurement Policy Board (GDDP)
20%
The contractor will be allowed to file for the release of first partial billing if he had satisfactorily completed at least __ of the contract
20%
On highly urbanized area, RROW marker shall be concrete block embedded on the surface along the edge of concrete sidewalk on each side of the road at __ interval
200m
What is the minimum pavement thickness for Farm to Market Roads
200mm
What is the minimum thickness of PCCP on farm to market roads
200mm
What is the minimum Road-Right-of-Way (RROW) for National Roads
20m
For school buildings, all slab reinforcements shall be __ clear minimum from bottom and top of slab
20mm
What is the minimum days of stripping of Forms and Shores for walls and columns in school buildings
21 days
What is the maximum allowed span length for Reinforced Concrete Deck Girder
24m
A change order may be issued when the aggregate cost is limited to __ of original contract cost
25%
When using Reclaimed Asphalt Pavement (RAP) as partial replacement to coarse aggregate in Hot-Mix Asphalt (HMA), what is the maximum % for Item 310 Grading D and Grading B
25% Grading D, 40% Grading B
What is the minimum bandwidth of the reflective tapes for traffic bollards
250mm
What is the minimum end laps for Corrugated Metal Roofing
250mm
During Road Re-blocking works, holes of __ diameter and spaced at 300mm shall be drilled at 1/2 of the existing concrete pavement thickness to permit the load transfer transverse construction joints
260mm
What is the Navigational Clearance of a Bridge over Navigable Waterways with the given data: HWL = 15.0m and HV = 10.0m
26m
What is the spacing of dowel bars for 300mm thick PCCP
274mm
What is the minimum PCCP slab thickness on National Roads
280mm
After the issuance of the "punch list" during the pre-final inspection, __ months-time durations imposed to complete the project without penalties
3
What is the minimum girder required for a one-lane bridge
3 girders
What is the minimum individual years of construction experience for Sustaining Technical Employees (STE)
3 years
What is the validity/renewal period of the Project Engineer Accreditation
3 years
What is the roadway cross slope for gravel surfacing of sidewalk
3.00%
What is the minimum width of PCCP on National Highways per lane
3.35m
What is the minimum width of turnouts, loading and unloading bay, to accommodate all types of vehicle
3.60m
Timeframe for the processing of Variation Orders from the preparation up to the approval by the procuring entity concerned shall not exceed __ calendar days
30 CD
What is the minimum Financial Capacity, Net worth/Equity of a Class A Category A Contractor in Pesos
30 million pesos
Processing of advance payment shall require that minimum of __ of the scope of work should be workable of free from obstructions
30%
What is the standard distance range for Road Warning Signs in advance of the construction site for urban areas
30-100m
What is the length of tangent between reverse curves for both Tourism and Farm to Market Roads
30.0m
What is the maximum amount for Regional Directors to approved Program of Work, ABC and plans like as-built and as-staked
300 million pesos
For roadway obstructions, such as bridge piers, what is the width of the black and white strips on the object markings
300mm
Minimum overall thickness should be __ for all types of revetment, except for reinforced concrete type.
300mm
What is the spacing of dowel bars at 280mm thick PCCP
300mm
What is design speed for flat terrain of Farm to Market Roads
30kph
What is design speed for mountainous terrain of Farm to Market Roads
30kph
Cross hole Sonic Logging Test (CSL) is recommended for bored piles with embedded length of more than __
30m
The reversion length of tangent between reversed curves should be 50m and in no case, should be less than __
30m
What is the maximum design span range for Box Girders
30m
What is the minimum Radius of Curve for a design speed of 30kph
30m
What is the minimum Radius of Horizontal Curve for Farm to Market Roads
30m
What is the minimum length of the radius of horizontal curve for PCCP on farm to market roads
30m
What is the flood flow velocity criteria for designing slope protection works
3m/sec
The refuge island shall be provided in roadways having clear carriageway width of at least __ lanes
4 lanes minimum
What is the minimum width of Zebra (Longitudinal Bars) for Pedestrian crossing markings
4.0m
For creeks in urban and rural areas and not subjected to overbank flows, a minimum easement to be provided measured from the edge of the existing bank or the improved bank should be __
4.5m
For school building, camber all beams and girders at least 6mm for every __ of span, except cantilevers for which the camber shall be as noted in plans but no case less than 20mm for every __ span
4.5m, 3.0m
What is the minimum vertical clearance above road carriageway for Vehicles
4.88m
What is the minimum vertical clearance of the Overhead Utilities and Power Lines from the sidewalk surface to the calculated lowest point of cable sag
4.88m
As per BP 344, Handrails attached to walls should have a clearance no less than 50mm from the wall and handrails on ledges should have a clearance not less than
40mm
What is the width of the Stop Line in Urban Roads
450mm Urban Roads
Barrier boards shall NOT be used for delineation purposes or installed parallel to vehicular traffic unless there is an offset of at least __ from the travelled path
4m
All permanent bridges along national roads shall be provided with the Informative signs to be posted on conspicuous place within __ before the abutment at both approaches
5 meters
Traffic cones shall be spaced __ apart on tapers and around small work sites
5 to 10 meters apart
As per RA 9184, Rule XIX Section 62, what is the warranty period for semi-permanent structures or Building Types 1, 2 and 3
5 years
All sidewalks/walkways for people with disability (PWD) shall have a maximum gradient of __
5%
Early Warning Stage happens when the negative slippage of the project accomplishment is __
5%
For buildings, at least __ of the total number of bored piles shall be tested
5%
It is acceptable for "A-built plans" as a reason for Final variation order if the cumulative increase in value of work does not exceed __ of the adjusted original contract price
5%
Withholding VAT for progress billings of the contractor shall be
5%
What is the minimum vertical clearance above road carriageway for flyovers, bridges and railways
5.03m
For road projects with length of 10 kilometers or more, additional billboard shall also be installed at every __ interval
5.0km
What is the minimum vertical clearance above road carriageway for pedestrian footbridges
5.33m
What is the minimum vertical clearance of the welcome Arch/Overhead Boundary Marker from the roadways surface
5.33m
What is the minimum vertical clearance of the Overhead Utilities and Power Lines from the roadway surface to the calculated lowest point of cable sag
5.50m
Rivers, esteros and navigating canals, not subject to overbank flows should have a minimum easement measured from the edge of the existing bank or the improved bank of __
5.5m
What is the maximum amount for "ALL" District Engineers to approved Program of Works, ABC, and plans like as-built and as-staked
50 million pesos
What is the designed life span of permanent bridges before it is being replaced
50 years
What is the flood frequency used in hydraulic analysis for bridge design
50 years
Pile Integrity Test shall be conducted on at least __ of the total number of bored piles at each abutment and pier of bridges or at the entire foundation area of buildings
50%
Minimum distance between two consecutive pedestrian refuge islands along the highways shall not be less than __ meters
500m min
During re-blocking construction of PCCP, the breaking and restoration of pavement in 2-lane carriageway shall be limited to 1-lane and Not More than __ in Length at any time in Urban Areas
50m
What is the minimum Radius of Horizontal Curve for Tourism Roads
50m
As per IRR BP 344, Handrails attached to walls should have a clearance no less than __ from the wall
50mm
For buildings, the minimum concrete protection for reinforcement shall be __ clear for concrete deposited against a formwork
50mm
What is the minimum design thickness for asphalt overlay projects
50mm
If the height if the revetment is more than __, berm (banquette) must be provided to separate the revetment into segments, for stability and maintenance/patrolling services
5m
What is the length of the road widening from center of the road left and right side for Barangay Roads
5m
What is the maximum spacing of bridge drains
5m
What is the minimum girder required for a more than 2-lane bridge
6 girders
National Route Numbering (NRS) should remain over the medium term and reviews shall be undertaken on a periodic __ cycle
6 years
What is the maximum allowable grade for national roads
6%
The minimum Bridge Carriageway width for 5.0m width - Farm to Market Roads
6.10m
What is the minimum PCCP width of Tourism Roads
6.10m
What is the minimum travelled way for City roads
6.1m
What is the minimum travelled way for provincial roads
6.1m
The minimum Bridge Carriageway width for 6.1m width - Farm to Market Roads
6.70m
The minimum Bridge Carriageway width for Tourism Roads
6.70m
What is the minimum PCCP width on National Roads
6.70m