Project Management Chapter 6
Which of the following represents an activity on an activity-on-node (AON) project network?
A node
If a project has more than one activity that can begin when the project is to start, a common start node should be used to indicate a clear project beginning on the network. Without a common start node, each path is a
Dangler path
Which of the following will correctly calculate the total slack in an activity?
Either LS-ES or LF-EF
A merge activity is one that merges with other activities into a succeeding activity.
False
If the project has a duration of 13 days, the project should be completed 13 days from the day it starts.
False
Negative slack can be estimated.
False
The WBS identifies dependencies, the sequencing of activities, and the timing of activities
False
The backward pass determines project duration.
False
The critical path is the shortest path through a network and indicates activities that cannot be delayed without delaying the project
False
The forward pass through a project network determines the critical path
False
When completing a forward pass, you carry the early finish to the next activity where it becomes its early start unless the next succeeding activity is a merge activity. In this case, you select the smallest early finish number of all its immediate predecessor activities.
False
Within an Activity-on-node network, the arrows depict activities to be accomplished.
False
The requirement for a freshly poured foundation to cure before beginning construction is an example of which of the following type of lag?
Finish to Start
The assumption that all immediate preceding activities must be 100% complete is too restrictive in some situations. When an activity is broken down into smaller segments in order to start the succeeding activity sooner, this is called...
Laddering
The critical path in a project network is the...
Longest path through the network
An activity that has more than one dependency arrow flowing into it is termed a(n)...
Merge activity
When translated into a project network, a work package will become...
One or more activities
Activities which can take place at the same time are termed...
Parallel activity
A seqeunce of connected, dependent activities is termed a(n)...
Path
A project network provides the basis for ______________.
Scheduling labor and equipment
The likelihood the original critical path(s) will change once the project is initiated is referred to as...
Sensitivity
System documentation cannot end until three days after testing has started. This is an example of which kind of lag?
Start to Finish
__________ activities are to be completed immediately following a particular activity.
Successor
Which of the following is true about hammock activities?
They are used to identify the use of fixed resources or costs over a segment of a project.
The amount of delay within a task that will not delay the overall project is known as a
Total slack
The amount of time an activity can be delayed and yet not delay the project is termed...
Total slack
Tom is responsible for ordering hardware for a custom home his company is building. The contractor installing the hardware is scheduled to start in 5 working days, but the hardware is on backorder and will not arrive for another 9 working days. Fortunately, Tom has 10 days of slack; however, he shares this slack with the hardware installer. He will have to let the contactor know that the hardware will be ready 4 days later than expected and that the slack for the installer has been reduced by 4 days. Tom and the installer share 10 days of A. Free Slack. B. Shared Slack. C. Total Slack. D. Critical Slack. E. Functional Slack.
Total slack
An activity cannot begin until ALL preceding connected activities have been completed
True
Burst activities have more than one activity immediately following them (more than one dependency arrow flowing from them).
True
Different activities along the same path can have different total slack
True
Even though a project costs time and money to develop, it is worth the effort.
True
Experience suggests that when there are multiple starts, a common start node should be used to indicate a clear project beginning on the network. Similarly, a single project end node can be used to indicate a clear ending
True
Lags can be used to constrain the start and finish of an activity.
True
Only activities that occur at the end of a chain of activities can have free slack.
True
Using free slack does not delay any following activities and requires no coordination with managers of other activities.
True
On a project network, the activity times are derived from the...
Work packages
When creating a project network, your primary input will be the
Work packages
One piece of information that the arrows within the Activity-on-node network can convey is
how activities are related
Information to develop a project network is collected from the
work breakdown structure
A _______ activity is one that has more than one activity immediately following it.
Burst
Which of the following correctly calculates the late start for an activity?
LF-DUR