If a company loses $5 for every $100 in revenue for a certain product, what is the profit margin for that product?
-5%
Tom DiMarco's 4 reasons for project cost estimate inaccuracies.
1 - Estimates often are done too quickly before clear system requirements have been produced. 2 - The person doing the estimating often has a lack of estimating experience. 3 - People have a tendency to underestimate. An experienced person may estimate based on how he/she would do the task, but the task may be performed by an inexperienced worker. 4 - Management desires accuracy. They are not looking for ballpark figures and often that is what they are given.
3 Project Management Processes
1 - Estimating the cost 2 - Determining the budget 3 - Controlling costs
Earned value management involves calculating which three values for each activity or summary activity from a project's WBS?
1 - Planned Value 2 - Actual Cost 3 - Earned Value
Five levels of project portfolio management from simplest to most complex
1 - Put all your projects in one database 2 - Prioritize the projects in your database 3 - Divide your projects into two or three budgets based on type of investment, such as utilities or required systems to keep things running, incremental upgrades, and strategic investments. 4 - Automate the repository 5 - Apply modern portfolio theory, including risk-return tools that map project risk on a curve.
3 basic types of estimates
1 - Rough order of magnitude (ROM) 2 - Budgetary estimate 3 - Definitive estimate
Rough order of magnitude (ROM) estimate
A cost estimate prepared very early in the life of a project to provide a rough idea of what a project will cost.
Definitive estimate
A cost estimate that provides an accurate estimate of project costs.
Budgetary estimate
A cost estimate used to allocate money into an organization's budget.
Bottom-up estimate
A cost-estimating technique based on estimating individual work items and summing them to get a project total.
Parametric modeling
A cost-estimating technique that uses project characteristics (parameters) in a mathematical model to estimate project costs.
Analogous estimate
A cost-estimating technique that uses the actual cost of a previous, similar project as the basis for estimating the cost of the current project; also called top-down estimate.
Cost management plan
A document that describes how cost variances will be managed on the project.
Source Lines of Code (SLOC)
A human-written line of code that is not a blank line or comment.
Cash flow analysis
A method for determining the estimated annual costs and benefits for a project.
COCOMO II
A newer, computerized cost-estimating tool based on Barry Boehm's original model that allows one to estimate the cost, effort, and schedule when planning a new software development activity.
Constructive Cost Model (COCOMO)
A parametric model developed by Barry Boehm for estimating software development costs.
Earned value management (EVM)
A project performance measurement technique that integrates scope, time, and cost data.
Learning curve theory
A theory that states that when many items are produced repetitively, the unit cost of those items normally decreases in a regular pattern as more units are produced.
Cost baseline
A time-phased budget that project managers use to measure and monitor cost performance.
Cost budgeting
Allocating the overall cost estimate to individual work items to establish a baseline for measuring performance.
Estimate at completion (EAC)
An estimate of what it will cost to complete the project based on performance to date.
Cost performance index (CPI) formula
CPI = EV / AC
Cost variance formula
CV = EV - AC
Life cycle costing
Considers the total cost of ownership, or development plus support costs, for a project.
Cost control
Controlling changes to the project budget.
_______ is a resource sacrificed or foregone to achieve a specific objective or something given up in exchange.
Cost
Why do many projects never finish?
Cost management problems cause many problems to never finish.
Computerized tools
Cost-estimating tools that use computer software, such as spreadsheets and project management software.
Intangible costs or benefits
Costs or benefits that are difficult to measure in monetary terms.
Tangible costs or benefits
Costs or benefits that can be easily measured in dollars
Indirect costs
Costs that are not directly related to the products or services of the project, but are indirectly related to performing the project.
Direct costs
Costs that can be directly related to producing the products and services of the project.
________ are used for making many purchasing decisions for which accurate estimates are required and for estimating final project costs.
Definitive estimates
Cost estimating
Developing an approximation or estimate of the costs of the resources needed to complete the project.
Management reserves
Dollars included in a cost estimate to allow for future situations that are unpredictable (sometimes called unknown unknowns).
Contingency reserves
Dollars included in a cost estimate to allow for future situations that may be partially planned for (sometimes called known unknowns) and are included in the project cost baseline.
Reserves
Dollars included in a cost estimate to mitigate cost risk by allowing for future situations that are difficult to predict.
Estimate at completion (EAC) formula
EAC = BAC / CPI
Earned value formula
EV = PV to date * RP
_____ is a project performance measurement technique that integrates scope, time, and cost data.
Earned value analysis
Why is it important to define clearly the year on which the company bases its dollar amounts?
If a company bases all costs on a previous years estimates it would need to account for inflation and other factors when projecting costs and benefits in future-year dollars.
Why is cash flow important?
If top management selects too many projects that have high cash flow needs in the same year, the company will not be able to support all of its projects and maintain profitability.
________ for projects often include items like goodwill, prestige, and general statements of improved productivity that an organization cannot easily translate into dollar amounts.
Intangible costs
If a project is halfway completed and its schedule performance index is 110 percent and its cost performance index is 95 percent, how is it progressing?
It is ahead of schedule and over budget.
______ reserves allow for future situations that are unpredictable.
Management
Sunk cost
Money that has been spent in the past.
Estimated time to complete formula
Original time estimate / SPI
______ involves allocating the project cost estimate to individual work items over time.
Project cost budgeting
Profits
Revenues minus expenses.
Schedule performance index (SPI) formula
SPI = EV / PV
Schedule variance formula
SV = EV - PV
Function points
Technology-independent assessments of the functions involved in developing a system.
Overrun
The additional percentage or dollar amount by which actual costs exceed estimates.
If the actual cost for a WBS item is over $1500 and its earned value was $2000, what is its cost variance, and is it under or over budget?
The cost variance is $500, which is under budget
Cost variance (CV)
The earned value minus the actual cost.
Schedule variance (SV)
The earned value minus the planned value.
Baseline
The original project plan plus approved changes.
Budget at completion (BAC)
The original total budget for a project.
Earned value (EV)
The percentage of work actually completed multiplied by the planned cost; formerly called the budgeted cost of work performed (BCWP).
Planned value (PV)
The portion of the approved total cost estimate planned to be spent on an activity during a given period; formerly called the budgeted cost of work scheduled (BCWS).
Project cost management
The processes required to ensure that the project is completed within the approved budget.
Profit margin
The ratio between revenues and profits.
Rate of performance (RP)
The ratio of actual work completed to the percentage of work planned to have been completed at any given time during the life of the project or activity.
Cost performance index (CPI)
The ratio of earned value to actual cost; can be used to estimate the projected cost to complete the project.
Schedule performance index (SPI)
The ratio of earned value to planned value; can be used to estimate the projected time to complete a project.
Actual cost (AC)
The total of direct and indirect costs incurred in accomplishing work on an activity during a given period; formerly called the actual cost of work performed (ACWP).
When do organizations have a history of not spending enough money and what does it impact?
They have a history of not spending enough money in the early phases of projects and it impacts the total cost of ownership.
Outputs of estimating costs
activity cost estimates basis of estimates project document updates
Which of the following is not a key output of project cost management? a - activity cost estimates b - a cost management plan c - updates to the project management plan d - a cost performance baseline
b - a cost management plan
The drawback with ________ is that they are usually time-intensive and therefore expensive to develop.
bottom-up estimates
A(n) ________ is a time-phased budget that project managers use to measure and monitor cost performance.
cost baseline
Which of the following processes of project cost management involves allocating the overall cost estimate to individual work items to establish a baseline for measuring performance?
cost budgeting
The main outputs of the ________ process are work performance measurements, budget forecasts, organizational process asset updates, change requests, project management plan updates, and project document updates.
cost control
Which of the following processes of project cost management involves developing an approximation of the costs of the resources needed to complete a project?
cost estimating
Which of the following is the ratio of earned value to actual cost and can be used to estimate the projected cost of completing the project?
cost of performance index (CPI)
The ________ is the additional percentage or dollar amount by which actual costs exceed estimates.
cost overrun
Outputs of determining the budget
cost performance baseline project funding requirements project document updates
Which of the following is the earned value minus the actual cost?
cost variance (CV)
The ________ is an estimate of the value of the physical work actually completed.
earned value (EV)
A company might complete a project to develop and implement a new customer service system in one or two years, but the new system could be in place for ten years. Project managers should create estimates of the costs and benefits of the project for ten years. This is an example of ________.
life cycle costing
You are preparing a cost estimate for a building based on its location, purpose, number of square feet, and other characteristics. What cost estimating technique are you using?
parametric
A ________ might provide an estimate of $50 per line of code for a software development project based on the programming language the project is using, the level of expertise of the programmers, the size and complexity of the data involved, and so on.
parametric model
Suppose a project included a summary activity of purchasing and installing a new Web server. Suppose further that, according to the plan, it would take one week and cost a total of $10,000 for the labor hours, hardware, and software involved. The ________ for that activity that week is, therefore, $10,000.
planned value (PV)
To increase ________, a company can increase revenues, decrease expenses, or try to do both.
profits
What are most executives concerned with more than other issues?
profits
Which type of estimate is done very early in a project or even before a project is officially started?
rough order of magnitude (ROM) estimate
Which of the following is the ratio of earned value to planned value and can be used to estimate the projected time to complete the project?
schedule performance index (SPI)
Which of the following is the earned value minus the planned value?
schedule variance (SV)
Avoid ________ when deciding what project to invest in or continue.
sunk costs
What is the main goal of project cost management?
to complete a project within an approved budget.
Which type of estimate uses the actual cost of a previous, similar project as the basis for estimating the cost of the current project?
top-down estimate
Outputs of controlling costs
work performance measurements budget forecasts organizational process asset updates change requests project management plan updates project document updates