Security Management Chapter 10
In the early stages of planning, the project planner should attempt to specify completion dates only for major employees within the project. a. FALSE b. TRUE
a. FALSE
In a __________ implementation, the entire security system is put in place in a single office, department, or division before expanding to the rest of the organization. a. pilot b. parallel c. loop d. direct
a. pilot
The parallel operations strategy works well when an isolated group can serve as a test area, which prevents any problems with the new system from dramatically interfering with the performance of the organization as a whole. a. TRUE b. FALSE
b. FALSE
The work breakdown structure (WBS) can only be prepared with a complex specialized desktop PC application. a. TRUE b. FALSE
b. FALSE
Each organization has to determine its own project management methodology for IT and information security projects. a. FALSE b. TRUE
b. TRUE
In the __________ process, measured results are compared against expected results. a. turnover b. wrap-up c. negative feedback loop d. direct changeover
c. negative feedback loop
By managing the __________, the organization can reduce unintended consequences by having a process to resolve potential conflict and disruption that uncoordinated change can introduce. a. Governance process b. conversion process c. process of change d. wrap-up process
c. process of change
Tasks or action steps that come after the task at hand are called __________. a. parents b. children c. successors d. predecessors
c. successors
Technology __________ guides how frequently technical systems are updated, and how technical updates are approved and funded. a. supervision b. oversight c. responsibility d. governance
d. governance
The goal of the project __________ is to resolve any pending project-related issues, critique the overall effort of the project, and draw conclusions about how to improve the project management process for the future. a. phased implementation b. pilot implementation c. direct changeover d. wrap-up
d. wrap-up