SIE 557 Midterm Review Questions V2

Lakukan tugas rumah & ujian kamu dengan baik sekarang menggunakan Quizwiz!

If the optimistic estimate for an activity is 12 days, and the pessimistic estimate is 18 days, what is the standard deviation for this activity? A. 1 day B. 1.3 days C. 6 days D. 3 days

A. 1 day

Which statement describes best the meaning of the term cost baseline? A. A cost baseline is an approved time-phased budget that will be used to measure and monitor cost performance on the project. B. Data to draw a cost baseline can be easily generated and updated as necessary from information related to actual project cost. C. A cost baseline is usually displayed in the form of an inverse S-curve drawn from the beginning of the project until data date.

A. A cost baseline is an approved time-phased budget that will be used to measure and monitor cost performance on the project.

A project management team decided to develop a risk management plan. What would be an appropriate occasion to create it? A. A specific planning meeting B. During a documentation review C. When data precision is ranked D. After selection of diagramming techniques

A. A specific planning meeting

Todd is working on resource scheduling in preparation for the start of a project. There is a potential problem in the works; however, as the new collective bargaining agreement with the company's union has not been concluded. Todd decides to continue working on the resource schedule in anticipation of a satisfactory settlement. Todd's approach would be an example of which method for dealing with risk? A. Accept it B. Minimize it C. Transfer it D. Share it

A. Accept it

To control the schedule, a project manager is reanalyzing the project to predict project duration. She does this by analyzing the sequence of activities with the least amount of scheduling flexibility. What technique is she using? A. Critical Path Method B. PERT Method C. Critical Chain Method. D. Activity on Arrow Method

A. Critical Path Method

The project manager wants to make sure that he is proceeding in the right order as he moves to develop a clear scope for his project. During scope definition, what should he be doing? A. Involving stakeholders and verifying that they have all provided their input to the process B. Developing his WBS and OBS C. Moving as quickly as possible to the determination of scope reporting methods D. Identifying all necessary vendors for any outsourcing that must be done

A. Involving stakeholders and verifying that they have all provided their input to the process

You are creating your WBS and find that you keep decomposing tasks into smaller and smaller units. How can you tell when you are done? A. Keep decomposing tasks until you reach an amount of work that is small enough to reliably estimate required resources and durations B. Keep decomposing tasks until you reach an amount of work that can be accomplished in one hour C. Keep decomposing work until you reach an amount of work that can be accomplished in you organization's basic work unit D. Keep decomposing work until you reach predetermined number of hierarchy levels to keep the WBS balanced

A. Keep decomposing tasks until you reach an amount of work that is small enough to reliably estimate required resources and durations

You are working on the project of painting of your house. You identify a dependency that the painting of roof should begin only after two days of completion of painting of walls. This is an example of A. Lag B. Lead C. Slack D. Float

A. Lag

Which of the following statements regarding PERT times is true? A. Optimistic time estimate is an estimate of the minimum time an activity will require. B. Optimistic time estimate is an estimate of the maximum time an activity will require. C. The probable time estimate is calculated as t = (a + 4m + b)/6. D. Pessimistic time estimate is an estimate of the minimum time an activity will require. D. Most likely time estimate is an estimate of the maximum time an activity will require.

A. Optimistic time estimate is an estimate of the minimum time an activity will require. C. The probable time estimate is calculated as t = (a + 4m + b)/6.

A professional organization for project management specialists is the: A. PMI B. AMA C. MIS D. IPM E. PMBOK

A. PMI

The notion that work fills the time available so why hustle to complete a task when it isn't due until tomorrow is? A. Parkinson's law B. Self protection C. Dropped baton D. Student syndrome D. Bottlenecks

A. Parkinson's law

Rolling wave planning is ______. A. Planning near term work in detail B. Critical chain project management C. Critical path project management D. Precedence diagramming

A. Planning near term work in detail

What is the organization that controls project managers? A. Project Management Office B. Strong matrix C. Functional D. Pure project

A. Project Management Office

You have just been made the Project Manager of the ABC project. You are trying to read the WBS and are unable to understand some of the WBS components. Which should be your first step to understand this? A. Refer to the WBS dictionary B. Refer to the scope statement C. Refer to the Project charter D. Contact the previous Project Manager

A. Refer to the WBS dictionary

The assessment of the external and internal environments is called a _______ analysis. A. SWOT B. Competitive C. Industry D. Market E. Strategic

A. SWOT

The scope baseline is used to ídentify variance on the scope during the project. It consists of what? A. Scope statement, WBS with work packages and planning packages, WBS dictionary B. Cost baseline, quality baseline and schedule baseline C. Configuration management plan and configuration identification document D. Procurement statement of work and project scope statement

A. Scope statement, WBS with work packages and planning packages, WBS dictionary

A building contractor is working on a vacation home and is looking over his schedule. He notices that the schedule calls for the foundation footers to be poured and then the rough decking to be installed. In this plan, the decking would be an example of what type of activity? A. Successor task B. Predecessor task C. Lag activity D. Crashed activity

A. Successor task

A project is handled by departments of an organization and expedited by a project coordinator. Which of the following statements is most likely to be true? A. The performing organization is a weak matrix. B. The performing organization is doing "management by projects". C. The performing organization is a strong matrix. D. The performing organization is projectized.

A. The performing organization is a weak matrix.

What is the main role of the functional manager A. To control resources B. To manage the project when the Project Manager isn't available C. To define business processes D. To manage the project manager

A. To control resources

Which of the following is not true about the WBS report? A. WBS should focus in on the activities that must be performed in the project and should not focus on the deliverables B. The project team must be involved in developing the WBS C. As a rule of thumb, each activity of the WBS should take less than 80 hours D. WBS is usually represented in a hierarchical fashion

A. WBS should focus in on the activities that must be performed in the project and should not focus on the deliverables

What is the lowest level of decomposition in the Works Breakdown Structure called? A. Work package B. Deliverable C. Subdeliverable D. Project

A. Work package

What cost estimating technique uses project characteristics in a mathematical model to estimate project costs? A. parametric modeling B. fast-track estimating C. analogous estimating D. critical chain

A. parametric modeling

What two dimensions should you use when evaluating project risks? A. probability and impact B. cost and schedule C. negative and positive D. source and responsibility

A. probability and impact

Which statement describes best why you should document assumptions? Assumptions might prove to be wrong. Knowing which assumptions were incorrect allows baseline adjustments in case of project crisis. Assumptions recorded in the assumptions log may help identify individual project risks during risk identification. Assumptions limit the project management team's options for decision making because they can not be controlled by the team. In case of schedule or budget overruns, the documentation of assumptions supports a clear assignment of responsibility.

Assumptions recorded in the assumptions log may help identify individual project risks during risk identification.

What is a trigger in project risk management? A. An expected situation causing an unidentified risk to occur B. A warning sign that a previously identified risk might be occurring or has occurred C. An unexpected situation causing an identified risk to occur D. An unexpected situation causing an unidentified risk to occur

B. A warning sign that a previously identified risk might be occurring or has occurred

Your project team is working on a brand new project with leading edge technology. As a result, it is very difficult for your team to give reasonable accurate estimates for how long their activities are going to take in order to be completed. Because of this uncertainty, it would be appropriate for you to require your team members to use what kind of logic when estimating durations? A. Normal distribution B. Beta distribution C. Deterministic estimates D. Experience

B. Beta distribution

Funds that are for identified risks that have a low probability of occurring and that decrease as the project progresses are called ______ reserves. A. Management B. Budget C. Contingency D. Padded E. Just in case

B. Budget

A project manager tracks the work of team members using a network logic diagram. Which effect will the presence of an actual finish date have on the calculation of float for the finished activity? A. Finished activities have only float left when they have been completed on schedule. B. Calculating free float and total float is generally not reasonable for finished activities. C. When an activity has been finished, total float gets often converted to become free float. D. When an activity has been finished, float gets often converted to become slack

B. Calculating free float and total float is generally not reasonable for finished activities.

Which of the following becomes increasingly important in a virtual team environment? A. Requirements engineering B. Communication planning C. Formal procurements closure D. Network diagramming

B. Communication planning

A hospital expansion is being planned for a community. As part of the scope of this project, it will be necessary to close down the access routes into the emergency room for major remolding; however, because this is the only hospital for trauma cases within 50 miles, it is not possible to completely shut down the emergency room. The project team will have to find a means to remodel the emergency room while allowing for continuous operations of the unit. This is an example of what? A. Negotiation points with the owner B. Constraints C. Initial assumptions D. Milestone development

B. Constraints

The essential difference between cost and price is? A. Price includes cost-of-living adjustment and cost does not B. Cost is the expenses incurred by the project; price is what the customer is charged for the work/product C. Price divided by cost equals the benefit cost ratio (BCR) for the project D. Cost is what the customer is charged for the project work/product; price is based on the retail value of the project work/product

B. Cost is the expenses incurred by the project; price is what the customer is charged for the work/product

A project manager is informed that a limited number of resources are going to be available for his project. He creates a project schedule by adding buffers to the project to protect the target finish date. What type of schedule network analysis is he using? A. What-if Analysis B. Critical chain method C. Critical path method D. Resource leveling

B. Critical chain method

A project manager spent some days to create a multi-page document, which he called project charter. The document should have been issued by the project sponsor. The sponsor found the document outsized and asked for a condensed document. Which of the following is usually not an element of the project charter? A. The authority level of the project manager B. Detailed control account and work package descriptions C. The business need that the project was undertaken to address D. High-level risks

B. Detailed control account and work package descriptions

Which of the following is a benefit of an analogous project estimate? A. It will be closer to what the work will actually require. B. It gives the project team an understanding of management's expectations C. It is based on a detailed understanding of what the work requires D. It helps the project manager determine if the project will meet the schedule

B. It gives the project team an understanding of management's expectations

Which should be included in a requirements management plan? A. The document should trace requirements to project scope / WBS deliverables. B. It should describe how requirements activities will be planned, tracked, and reported. C. It should trace high-level requirements to more detailed requirements. D. It should trace requirements to business needs, opportunities, goals, and objectives.

B. It should describe how requirements activities will be planned, tracked, and reported.

To balance risks, the PM should also consider? A. Problems B. Opportunities C. Resources D. Schedules

B. Opportunities

A project manager is using weighted average duration estimates to perform schedule network analysis. Which type of mathematical analysis is being used? A. Critical path method B. PERT C. Monte Carlo D. Resource Leveling

B. PERT

A temporary endeavor undertaken to create a new product or service is called a: A. New product development. B. Project C. Program D. Enterprise

B. Project

What kind of certification does the Project Management Institute provide? A. Certified Project Manager (CPM) B. Project Management Professional (PMP) C. Project Management Expert (PME) D. Project Management Mentor (PMM)

B. Project Management Professional (PMP)

You are working as a project manager in a company. You have the highest degree of authority, you are working full-time for your project and you manage the budget of the project. What is the organization structure in your company? A. Strong matrix B. Projectized C. Functional D. Balanced Matrix

B. Projectized

A project manager is preparing two documents for risk management. One contains sources of overall project risk and also summary information on individual risks. The second describes individual risks identified. What name should the project manager give to the first document? A. Risk Register B. Risk Report C. Risk management plan D. Requirements traceability matrix

B. Risk Report

In a matrix organization, which of the following is true? A. The project manager is responsible for employee skills improvement. B. The functional manager is responsible for employee skills improvement. C. The project manager is responsible for the employee's annual appraisal. D. The employee is responsible for his or her own skills improvement.

B. The functional manager is responsible for employee skills improvement.

A finish to finish relationship is defined as which of the following? A. Both activities have to finish at the same time B. The predecessor has to finish before the successor can finish C. Both activities are on a critical path D The predecessor has a defined lead while the successor has a defined lag

B. The predecessor has to finish before the successor can finish

Purchasing insurance is BEST considered an example of risk: A. Mitigation B. Transfer C. Acceptance D. Avoidance

B. Transfer

Which of the following would be least important on the risk register? A. Risk owner B. Who identified the risk C. Risk triggers D. Secondary risks

B. Who identified the risk

Cost baseline is usually represented using which curve or line? A. a Slanted line B. an S-curve C. a Z curve D. a PQ curve

B. an S-curve

What is the first step in planning a project schedule? A. developing a budget B. developing an activity list C. assigning resources to the project D. determining activity sequencing

B. developing an activity list

All of the following are elements in the definition of a project except A. A project is time-limited B. A project is unique C. A project is composed of unrelated activities D. A project is undertaken for a purpose

C. A project is composed of unrelated activities

Which is not a point used for three-point estimation? A. Optimistic estimate B. Most likely estimate C. Budget estimate D. Pessimistic estimate

C. Budget estimate

The WBS, estimates for each work package, and the network diagram are completed. Which of the following would be the NEXT thing for the project manager to do? A. Sequence the activities B. Verify that they have the correct scope C. Create a preliminary schedule D. Complete risk management

C. Create a preliminary schedule

______ is a method of planning and managing projects that emphasizes the resources required to execute project tasks. It is based on methods and algorithms derived from Theory of Constraints. A. Critical Path Method B. PERT Method C. Critical Chain Method. D. Activity on Arrow Method

C. Critical Chain Method.

If a risk has a 90 percent chance of occurring, and the consequences will be $10,000, what does $9,000 represent? A. Risk value B. Present value C. Expected monetary value D. Contingency budget

C. Expected monetary value

With your team you are using judgment from subject matter experts early during initiation to discuss perceived project risks. There is a number of experts from different disciplines available. You want to create a conversational setting to allow them to discuss their different views on the project and its risks. Which of the following techniques can ensure best that the different perceptions and opinions are contributing to the expert discussion? A. Peer review B. SWOT analysis C. Focus group D. Monetary value calculation

C. Focus group

Suppose a project plan had three distinct paths through a network. The first path consisted of activities A (3 days), B (4 days), and C (2 days). The second path consisted of activities D (4 days), E (5 days), and F (5 days). The third path consisted of activities G (2 days), H (3 days) and I (10 days). Which is the critical path? A. ABC B. DEF C. GHI D. ADG

C. GHI

Which of the following is a benefit of an analogous project estimate? A. It will be closer to what the work will actually require B. It is based on a detailed understanding of what the work requires C. It gives the project team an understanding of managements' expectations D. It helps the project manager determine if the project will meet the schedule

C. It gives the project team an understanding of managements' expectations

Which of the following is not true about analogous estimating A. Estimate based on past projects B. It is not very accurate C. It uses bottom-up approach D. It is a form of an expert judgement

C. It uses bottom-up approach

Which of the following is not part of the triple constraint in project management? A. Meeting scope goals B. Meeting time goals C. Meeting communication goals D. Meeting cost goals

C. Meeting communication goals

A group of related projects that are managed in a coordinated way that usually include an element of ongoing activity is called a: A. Major project. B. Project office. C. Program. D. Group of projects.

C. Program.

When would a milestone chart be used instead of a bar (Gantt) chart? A. Project planning B. Reporting to team members C. Reporting to management D. Risk analysis

C. Reporting to management

In a software company a large number of simultaneously performed projects utilize the same groups of human and other resources. What is the term commonly used for this situation? A. Concurrent engineering B. Resource over-allocation C. Resource pooling D. Program management

C. Resource pooling

The project manager has just met with her team to brainstorm some of the problems that could occur on the upcoming project. Today's session was intended to generate possible issues that could arise and get everyone to start thinking in terms of what they should be looking for once the project kicks off. This meeting would be an example of what element in the risk management process? A. Risk mitigation B. Control and documentation C. Risk identification D. Analysis of probability and consequences

C. Risk identification

Which of the following is true statement about risks? A.If a risk is identified in a risk response plan, then that means that risk has already happened. B.A risk that was not planned but has happened is called a trigger. C. Risk identification happens in all the phases of the project.

C. Risk identification happens in all the phases of the project.

What is the typical role of senior management on a project? A. Support the project B. Pay for it C. Support the project and resolve resource and other conflicts D. Resolve resource and other conflicts

C. Support the project and resolve resource and other conflicts

Which of the following statements is false concerning the financial analysis of projects? A. The higher the net present value the better B. A shorter payback period is better than a longer one C. The required rate of return is the discount rate that results in an NPV of zero for the project D. ROI is the result of subtracting the project costs from the benefits and then divided by the costs.

C. The required rate of return is the discount rate that results in an NPV of zero for the project

A ______ is a deliverable-oriented grouping of the work involved in a project that defines the total scope of the project. A. contract B. Gantt chart C. WBS D. Network diagram

C. WBS

A document called ____________ is created by decomposing the project scope into smaller, more manageable elements. A. Scope Statement B. Network Logic Diagram C. Work Breakdown Structure D. Requested Change

C. Work Breakdown Structure

A _____ is a time-phased budget that project managers use to measure and monitor cost performance. A. cost estimate B. life-cycle budget C. cost baseline D. cash flow analysis

C. cost baseline

In which of the five PMI project management process groups is the most time and money usually spent? A. initiating B. planning C. executing D. monitoring & controlling E. closing

C. executing

Which relationship model is most commonly used in the Precedence diagrams? A. start-to-start B. start-to-finish C. finish-to-start D. finish-to-finish

C. finish-to-start

A RACI chart is a type of _______ . A. project organizational chart B. resource histogram C. responsibility assignment matrix D. project dashboard

C. responsibility assignment matrix

A ______ is a document that contains results of various risk management assessments, often displayed in a table or spreadsheet format. A. risk event B. trigger C. risk register D. risk management plan

C. risk register

Project portfolio management addresses ______ goals of an organization, whereas project management addresses _____ goals. A. external, internal B. internal, external C. strategic, tactical D. tactical, strategic

C. strategic, tactical

Together with your project management team in a project to build a state-of-the-art power station, you want to perform active risk acceptance in your project. What should you do? Create contingency reserves in resources, money and time. Develop a plan to minimize impact in case that an identified risk occurs. Develop a plan to minimize the probability of occurrence for identified risks. Make additional resources available to speed up the project.

Create contingency reserves in resources, money and time.

Suppose you evaluated the best-case, most likely, and worst-case duration estimates for an activity and determined that they were 3 days, 4 days, and 8 days, respectively. Using PERT (three-point estimates) estimation techniques, what would be the expected duration for the activity? A. 4 days B. 8 days C. 5 days D. 4.5 days

D. 4.5 days

Which of the following best describes a project stakeholder A. A team member B. The project manager C. Someone who works in an area affected by the project D. All of the above are stakeholders

D. All of the above are stakeholders

Which of the following is a common multi-criteria selection model? A. Checklist B. Net Present Value C. Weighted criteria model D. Both A and C are correct E. All of these are common multicriteria selection models

D. Both A and C are correct

Which of these is not an example of a project? A. Planning for your friends wedding B. Building a bridge across the Amazon river C. Buying clothes from the market on a special sale D. Cleaning the office building each day

D. Cleaning the office building each day

The authority to approve or deny change request lies with A. Project Manager B. Customer C. Project Sponsor D. Configuration Control Board

D. Configuration Control Board

What should not be covered by a risk management plan? A. Roles and responsibilities for handling project risks B. Timing of project risk management activities C. The methodological approach used for risk management D. Individual risks and potential responses to them

D. Individual risks and potential responses to them

The PMI project management process groups are: A. Initiating, planning, expediting, and control. B. Plan, organize, develop, and control. C. Plan, do, observe, commit. D. Initiating, planning, executing, monitoring & controlling, and closing.

D. Initiating, planning, executing, monitoring & controlling, and closing.

Activity slack (also known as float) can be calculated through which of the following means? A. Early Finish (EF) - late finish (LF) B. Early finish (EF) - early start (ES) C. Late finish (LF) - late start (LS) D. Late start (LS) - early start (ES)

D. Late start (LS) - early start (ES)

You have been asked to make an estimate for a project. The project involves manufacturing 1000 toys. You expect that as the team manufactures some toys, the time to make them will reduce. Which estimation technique are you trying to use? A. Analogous Estimation B. Regression Analysis C. Bottom up Estimating D. Learning Curve

D. Learning Curve

You have been criticized that certain specifications in your scope statement do not pass the test for SMART objectives. What are SMART objectives? A. Objectives specified in far more detail than necessary for an execution of a successful project. B. Easily achievable objectives which help you reducing the pressure on yourself and the team. C. Objectives that should be achieved in order to attain formal recognition by both the customer and the project sponsor. D. Objectives that are described using specific, measurable, assignable, realistic and time-related specifications.

D. Objectives that are described using specific, measurable, assignable, realistic and time-related specifications.

A rough order of magnitude estimate is made during which project management process group? A. Project planning B. Project closing C. Project executing D. Project initiating

D. Project initiating

All of the following are characteristics of a project EXCEPT: A. Temporary B. Definite beginning and end C. Interrelated activities D. Repeats itself every month

D. Repeats itself every month

Which of the following is true statement about risks? A. If a risk is identified in a risk response plan, then that means that risk has already happened. B. Once a risk has happened, you refer to the risk management plan to determine what action needs to be taken. C. A risk that was not planned but has happened is called a trigger. D. Risk identification happens in all the phases of the project.

D. Risk identification happens in all the phases of the project.

A company has to make a choice between two projects, because the available resources in money and kind are not sufficient to run both at the same time. Each project would take 9 months and would cost $250,000. The first project is a process optimization which would result in a cost reduction of $120,000 per year. This benefit would be achieved immediately after the end of the project. The second project would be the development of a new product which could produce the following net profits after the end of the project: 1. year: $ 15,000 2. year: $ 125,000 3. year: $ 220,000 Assumed is a discount rate of 5% per year. Looking at the present values of the benefits of these projects in the first 3 years, what is true for their monetary attractiveness? A. Both projects are equally attractive B. One cannot say based on the numbers C. The second project is more attractive D. The first project is more attractive

D. The first project is more attractive

Which of the following is the most critical component of the quadruple constraint? A. Time, then cost, then quality B. Quality, then budget, then time C. Scope D. They are all equal importance unless otherwise stated

D. They are all equal importance unless otherwise stated

All of the following are characteristics of a project EXCEPT: A. project success criteria B. product requirements C. deliverables D. roles and responsibilities

D. roles and responsibilities

Which of the following is not part of a SWOT analysis? A. strengths B. weaknesses C. opportunities D. tactics

D. tactics

Resource leveling can provide A. Lower peak demand B. Reduced resource need over the life of the project C. Reduced fluctuations in resource demand D. Both A and B are correct E. A, B, and C are all correct

E. A, B, and C are all correct

Splitting an activity creates the following situation: A. More people working on the same activity B. There are possible startup and shutdown costs C. A resource may be moved from one activity to another and then back D. Both B and C are correct E. A, B, and C are all correct

E. A, B, and C are all correct

All of the following would be considered examples of significant project risks except? A. Financial risks B. Technical risks C. Subcontractor risks D. Legal risks E. All are examples of significant potential project risks

E. All are examples of significant potential project risks

The project manager spends a great deal of her time communicating with project stakeholders. Which of the following represent an example of a stakeholder group for her project? A. Top management B. Customers C. Project team members D. Functional group heads E. All are project stakeholders

E. All are project stakeholders

Which of the following statements regarding networks is false? A. The critical path is the shortest of all paths through the network. B. The critical path is that set of activities that has positive slack. C. Some networks have no critical path. D. All activities on the critical path have their LS equal EF. E. All of the above are false.

E. All of the above are false.

The chances of a risk event occurring as a project proceeds through its life cycle tends to A. Slowly rise B. Drop sharply and then level out C. Rise sharply and then level out D. Remain about the same E. Slowly drop

E. Slowly drop

A project budget report is showing our project as spending $35,000 against a budgeted amount of $40,000. Which of the following is true? A. We are spending less than we should for the project B. We are doing a good job managing the project C. We should check to see if all the bills have been paid D. Both A and B are correct E. We can't be sure how the project is going

E. We can't be sure how the project is going

Which tools and techniques are used in the processes Create WBS and Define activities? Nominal group technique Human resource assignment Brainstorming Expert judgement and decomposition

Expert judgement and decomposition

The Project Management Office (PMO) of your company is performing a project management audit in your company and find that most of the various plans in the project are neither consistent nor up-to-date. Which of the following statements is true? Projects should never be executed without a valid, updated and working project management plan. The consistency of the various plans is secondary because it is only the results that matter. The alternatives to systematic planning are reactive management, crisis management, conflict management, and fire fighting. Poor planning and insufficient updating of project management plans are rather uncommon as reasons for cost and time overruns.

The alternatives to systematic planning are reactive management, crisis management, conflict management, and fire fighting.

A project manager has been asked to support an internal project request by developing a business case. What kind of information is the person expected to provide in the document? The detailed information from a business standpoint to determine whether bidding for the customer project will be successful. The detailed information from a project management standpoint to determine whether the project will be successful. The detailed information from a technical standpoint to determine whether the project will be successful. The necessary information from a business standpoint to determine whether the project is worth the investment.

The necessary information from a business standpoint to determine whether the project is worth the investment.


Set pelajaran terkait

Chapter 14: Musculoskeletal System

View Set

Google for Education Chrome Browser w/ added Q's

View Set

PrepU - Chapter 47: Management of Patients With Intestinal and Rectal Disorders

View Set

Management of Patients with Cerebrovascular Disorders

View Set

chapter 2: psychological and spiritual well-being

View Set

Wongs Ch 6. Childhood Communicable and Infectious Disease

View Set

BioChemistry: Learning Curve Chapter 4

View Set