Supply Chain Chapter 7S

Lakukan tugas rumah & ujian kamu dengan baik sekarang menggunakan Quizwiz!

5) Which of the following statements regarding fixed costs is TRUE? A) Fixed costs rise by a constant amount for every added unit of volume. B) While fixed costs are ordinarily constant with respect to volume, they can "step" upward if volume increases result in additional fixed costs. C) Fixed costs are those costs associated with direct labor and materials. D) Fixed costs equal variable costs at the break-even point. E) Fixed cost is the difference between selling price and variable cost.

B

7) Basic break-even analysis typically assumes that: A) revenues increase in direct proportion to the volume of production, while costs increase at a decreasing rate as production volume increases. B) variable costs and revenues increase in direct proportion to the volume of production. C) both costs and revenues are made up of fixed and variable portions. D) costs increase in direct proportion to the volume of production, while revenues increase at a decreasing rate as production volume increases because of the need to give quantity discounts. E) All of the above are assumptions in the basic break-even model.

B

10) Utilization will always be lower than efficiency because: A) effective capacity is less than design capacity. B) effective capacity is greater than design capacity. C) effective capacity equals design capacity. D) expected output is less than actual output. E) expected output is less than rated capacity.

A

11) TOC was popularized by: A) Goldratt and Cox. B) Ford. C) Taguchi. D) Deming. E) Motorola and GE.

A

9) Which of the following represents an aggressive approach to demand management in the service sector when demand and capacity are not particularly well matched? A) lower resort hotel room prices on Wednesdays B) appointments C) reservations D) first-come, first-served rule E) none of the above

A

14) Which of the following represents a common way to manage capacity in the service sector? A) appointments B) reservations C) changes in staffing levels D) first-come, first-served service rule E) "early bird" specials in restaurants

C

12) TOC strives to reduce the effect of constraints by: A) offloading work from constrained workstations. B) increasing constrained workstation capability. C) changing workstation order to reduce throughput time. D) A and B E) A, B, and C

D

6) Which of the following costs would be incurred even if no units were produced? A) raw material costs B) direct labor costs C) transportation costs D) building rental costs E) purchasing costs

D

1) Possible decision alternatives found in capacity EMV problems are future demands or market favorability. True or false

False

1) The bottleneck time is always at least as long as the throughput time. True or false

False

1) Utilization is the number of units a facility can hold, receive, store, or produce in a period of time. True or false

False

2) Break-even analysis identifies the volume at which fixed costs and revenue are equal. True or false

False

2) The net present value of $10,000 to be received in exactly three years is considerably greater than $10,000. True or false

False

3) Break-even analysis is a powerful analytical tool, but is useful only when the organization produces a single product. True or false

False

1) Changes in capacity may lead, lag, or straddle the demand. True or false

True

10) The basic break-even model can be modified to handle more than one product. This extension of the basic model requires: A) price and sales volume for each product. B) price and variable cost for each product, and the percent of sales that each product represents. C) that the firm have very low fixed costs. D) that the ratio of variable cost to price be the same for all products. E) sales volume for each product.

B

5) Consider a production line with five stations. Station 1 can produce a unit in 9 minutes. Station 2 can produce a unit in 10 minutes. Station 3 has two identical machines, each of which can process a unit in 12 minutes (each unit only needs to be processed on one of the two machines. Station 4 can produce a unit in 5 minutes. Station 5 can produce a unit in 8 minutes. Which station is the bottleneck station? A) Station 1 B) Station 2 C) Station 3 D) Station 4 E) Station 5

B

8) A work system has five stations that have process times of 5, 9, 4, 9, and 8. What is the bottleneck time? A) 4 B) 9 C) 18 D) 35 E) 7

B

8) Effective capacity is the: A) maximum output of a system in a given period. B) capacity a firm expects to achieve given the current operating constraints. C) average output that can be achieved under ideal conditions. D) minimum usable capacity of a particular facility. E) sum of all of the organization's inputs.

B

15) Adding a complementary product to what is currently being produced is a demand management strategy used when: A) demand exceeds capacity. B) capacity exceeds demand for a product that has stable demand. C) the existing product has seasonal or cyclical demand. D) price increases have failed to bring about demand management. E) efficiency exceeds 100 percent.

C

4) Lag and straddle strategies for increasing capacity have what main advantage over a leading strategy? A) They are cheaper. B) They are more accurate. C) They delay capital expenditure. D) They increase demand. E) All of the above are advantages.

C

4) Net present value will be greater: A) as a fixed set of cash receipts occurs later rather than earlier. B) if the future value of a cash flow is smaller. C) for one end-of-year receipt of $1200 than for twelve monthly receipts of $100 each. D) for a 4% discount rate than for a 6% discount rate. E) All of the above are true.

D

7) A work system has five stations that have process times of 5, 9, 4, 9, and 8. What is the throughput time of the system? A) 4 B) 9 C) 18 D) 35 E) 7

D

7) What is sometimes referred to as rated capacity? A) efficiency B) utilization C) effective capacity D) expected output E) design capacity

D

9) Break-even analysis can be used by a firm that produces more than one product, but: A) the results are estimates, not exact values. B) the firm must allocate some fixed cost to each of the products. C) each product has its own break-even point. D) the break-even point depends upon the proportion of sales generated by each of the products. E) None of these statements is true.

D

10) Which of the following is not one of the four principles of bottleneck management? A) Release work orders to the system at the bottleneck's capacity pace. B) Lost time at the bottleneck is lost system capacity. C) Increasing capacity at non-bottleneck stations is a mirage. D) Increased bottleneck capacity is increased system capacity. E) Bottlenecks should be moved to the end of the system process.

E

13) The theory of constraints has its origins in: A) linear programming theory. B) the theory of economies of scale. C) material requirements planning. D) the theory of finite capacity planning. E) Goldratt and Cox's book, The Goal: A Process of Ongoing Improvement.

E

14) Which of the following techniques is NOT a technique for dealing with a bottleneck? A) Schedule throughput to match the capacity of the bottleneck. B) Increase the capacity of the constraint. C) Have cross-trained employees available to keep the constraint at full operation. D) Develop alternate routings. E) All are techniques for dealing with bottlenecks.

E

2) Of the four approaches to capacity expansion, the approach that "straddles" demand: A) uses incremental expansion. B) uses one-step expansion. C) at some times leads demand, and at other times lags. D) works best when demand is not growing but is stable. E) Choices A and C are both correct.

E

3) Net present value: A) is gross domestic product less depreciation. B) is sales volume less sales and excise taxes. C) is profit after taxes. D) ignores the time value of money. E) is the discounted value of a series of future cash receipts.

E

5) What is a common method used to increase capacity with a lag strategy? A) overtime B) subcontracting C) new facilities D) new machinery E) A and B

E

1) Fixed costs are those costs that continue even if no units are produced. True or False

True

1) One limitation of the net present value approach to investments is that investments with identical net present values may have very different cash flows. True or false

True

2) Design capacity is the theoretical maximum output of a system in a given period under ideal conditions. true or false

True

3) The theory of constraints is a body of knowledge that deals with anything that limits an organization's ability to achieve its goals. True or false

True

4) Expected output is sometimes referred to as rated capacity. True or False

True

5) Price changes are useful for matching the level of demand to the capacity of a facility. True or false

True

6) A useful tactic for increasing capacity is to redesign a product in order to facilitate more throughput. True or false

True

15) In "drum, buffer, rope," what provides the schedule, i.e. the pace of production? A) drum B) buffer C) rope D) all three of the above in combination E) none of the above

A

16) An organization whose capacity is on that portion of the average unit cost curve that falls as output rises: A) has a facility that is below optimum operating level and should build a larger facility. B) has a facility that is above optimum operating level and should reduce facility size. C) is suffering from diseconomies of scale. D) has utilization higher than efficiency. E) has expected output higher than rated capacity.

A

9) An assembly line has 10 stations with times of 1, 2, 3, 4, ..., 10, respectively. What is the bottleneck time? A) 18.18% of the throughput time B) 100% of the throughput time C) 550% of the throughput time D) 50% of the throughput time E) 1.82% of the throughput time

A

4) Break-even is the number of units at which: A) total revenue equals price times quantity. B) total revenue equals total variable cost. C) total revenue equals total fixed cost. D) total profit equals total cost. E) total revenue equals total cost.

E

2) To find the throughput time with simultaneous processes, compute the time over all paths and choose the shortest path through the system. True or false

False

3) Capacity decisions are based on technological concerns, not demand forecasts. true or false

False

4) Substantial research has proved that the only successful method of dealing with bottlenecks is to increase the bottleneck's capacity. True or false

False

3) Which of the following is FALSE regarding capacity expansion? A) "Average" capacity sometimes leads demand, sometimes lags it. B) If "lagging" capacity is chosen, excess demand can be met with overtime or subcontracting. C) Total cost comparisons are a rather direct method of comparing capacity alternatives. D) Capacity may only be added in large chunks. E) In manufacturing, excess capacity can be used to do more setups, shorten production runs, and drive down inventory costs.

D


Set pelajaran terkait

Dividends/Stock Splits/Reverse Stock Splits

View Set

Immunology - Chapter 9 - Hypersensitivity Reactions

View Set

Nursing Fundamentals Practice Final Exam

View Set

BUS3-198 Strategic Management Midterm Review (Quizzes #1-7)

View Set