The max depth of a barrier such as a curb or housekeeping pad in front of accessible equipment is _____

10"

What is the minimum branch circuit size for a Level II EVSE with a 32-ampere current rating?

40 A 32 A * 1.25 = 40 A minimum OCPD

Fleet vehicle battery capacity has reached upward of ? for heavy duty vehicles.

550 kWh

The CHAdeMO V1.0 Standard has charging power up to ? at ? , up to ? .

62.5 kW / 500 VDC / 125 A

Information gathered during a site visit should include...

A. Details about the existing electrical visit.B. Details on the desired EVSE location.C. Notes on how the customer intends to use the EVSE installation.D. All of the above **

Incentives available for EVSE installation include which of the following?

A. Rate breaks or other incentives from serving utility.B. state or federal tax creditsC. tax incentives from the city of municipality.D. All of the above**

Charging methods for battery electric buses include which of the following? a.Above/below bus charging wireless charging b.Plug-in charging c.Wireless power transfer d.All of the above

All of the above

Requirements for branch circuits and AFCI/GFCI protection of branch circuits are found in ? .

Article 210

DC charging equipment provides DC directly to ? in an EV.

Battery management systems

Forklifts, yard tractors, and drayage trucks are all examples of ? .

Cargo-handling equipment

What factors limited the popularity of EVs as internal combustion engine vehicles came to the market in the early 1900s?

Charge Times Range Speed

Which of the following illustrates why electric vehicles were so popular in the early days of automobiles? a.They were clean to operate. b.They were mechanically complicated. c.They were quiet. d.Both a. and c.

D

EVs can be equipped with a(n) (?) motor. a.induction b.internal combustion c.permanent magnet d.either a. or c.

D.

True or false: The EV's power acceptance rate should not be considered when making EVSE purchasing decisions.

False

Which of the following is not an alternative to fossil fuels? a.Compressed air b.Electricity c.Fuel cell d.Gasoline

Gasoline

Which of the following was an early electric vehicle charger? a.City of Seattle's Electro-Park electrified parking space b.Ford Dyna-Charge c.General Electric arc rectifier d.Tesla Model 001 Charger

General Electric arc rectifier

What category of EV has been available to consumers the longest? a.BEV b.HEV c.PHEV d.All of the above

HEV

Wireless EV charging utilizes the principles of ? .

INDUCTION

What is the SAE standard for wireless charging?

J2954 recommended practice

An AC charger with a single-phase 120-volt connection and 14-16 amperes of continuous current output is classified as a ? charger.

Level 1

An AC charger with a single-phase 208-volt or 240-volt connection and a continuous current output of up to 80 amperes is classified as a ? charger.

Level 2

Which of the following describes an EV drivetrain architecture in which power can be transmitted to the drive from two sources at the same time? a.Full electric drive b.Parallel hybrid drive c.Series hybrid drive d.3-phase series drive

Parallel hybrid drive

Quiz #2

Quiz # 2`\

Quiz 7

Quiz 7

What was the first mass-produced hybrid electric vehicle?

Toyota Prius

True or False: The maximum amount of current a conductor can carry under the conditions of use without exceeding its temperature rating is found using the calculation methods based in Article 310.

True

The State of Charge of the EV battery is ? .

a determining factor in calculating the time necessary to fully charge an EV

Utilities or municipalities may have requirements that ? basic code considerations.

billing rates and plans

? is the process that ensures mechanical, electrical, and other building systems are installed, tested, and perform interactively in accordance with design documents.

commissioning

Issues with data servers, EVSE locator networks, and billing networks are typically the result of a(n) ? problem.

communication

NEC Chapter 8 covers ? systems and ? subject to Chapters 1-7 unless specifically referenced.

communications / is not

NEC 110.14(C) requires conductor ampacity to be ? .

coordinated with equipment termination ratings

The most commonly reported repair to electric vehicle supply equipment (EVSE) manufacturers is damage to the ? . Select one:

cord set

EVSE equipment shall have means to ? the charging cable if strain is placed upon it that could rupture the cable or connector, leading to exposure of live parts.

deenergize

EV networks utilize memberships that are ? .

fee-based or pay-as-you-go

Utilities or municipalities may have requirements that ? basic code considerations.

permissible

Part of the initial setup of fleet EVSE is making sure that the customer is comfortable with ? .

programming RFID cards and the reporting software

Documentation transfers important information about an installation from the contractor to the owner.

True

NEC Chapters 1-4 apply to ? .

all installations except as modified by Chapters 5, 6, and 7

Public EVSE installations need to be protected from ? vehicles and maintenance equipment.

impacts with

The ? load for listed occupancies is based on Table 220.12.

lighting

Commercial and fleet EVSE installations often require ? communications and ? functions.

networked / revenue collection

NECA 413-2012 contains ? requirements for EVSE installation, covering everything from planning an installation to ADA considerations and commissioning process.

performance-based

EVSE-specific testing tools ensure ? and ground-fault response.

proper communications protocol function

The National Electrical Code (NEC) ?

provides minimum installation requirements

The final step in the troubleshooting and repair guidelines flowchart is to ? .

release EVSE as fully operational

When a business installs charging equipment, the public may sense that the business supports...

sustainability

The first electric vehicle can be traced back to ? .

1832

What is the maximum voltage drop recommended for branch circuits and feeders/electrical systems in the National Electrical Code (NEC)?

3% branch / 5% feeder/system Note: Informational Note to NEC 210.19 - 3% for branch circuits / 5% for the overall system.

A partial zero emissions vehicle (PZEV) is defined as which of the following? a.A gas-engine vehicle that has zero evaporative emissions from its fuel system b.A plug-in electric vehicle c.A vehicle with a hybrid gas-electric drive train d.An electric vehicle that only has provisions for wireless charging

A

EV networks generate revenue with which of the following?

All of the above

Installations covered by the NEC include which of the following? Select one: a.Industrial substations b.Installations on public and private premises c.Recreational vehicles, floating buildings, and mobile homes d.All of the above

All of the above

The tables in Article 310 identify ? . Select one: a.allowable ampacity of conductors based on conductor size and material b.ampacity adjustment and correction factors c.wire types and application d.all of the above

D

True or False: ADA parking space guidelines can be used when determining the number of EV charging spaces that should be made accessible.

False

True or False: EVSE provides DC power to the electric vehicle charging port.

False

Which of the following is connected to the charge controller of a wireless EV charger via hardwiring? Select one: a.Power capture resonator b.Power control unit c.Power multiplier coil d.Power source coil

Power source coil

Recognized types of EVCE activation technology include which of the following?

RFIB tags Swipe Cards

Which of the following calculations are covered in Article 220?

Residential, commercial, industrial service, and feeder

Which of the following acronyms represents the level of charge present in an EV battery? a.ANSI b.EVA c.NFPA d.SOC

SOC

Overcurrent protection for EVSE is covered in ? .

Section 625.41

Chapter 9 of the NEC contains which of the following? Select one: a.Auxiliary information that is not enforceable b.Engineering tables that are only intended to be used by electrical designers c.Load calculation examples d.Tables that are applicable and enforceable when referenced elsewhere in the Code

Tables that are applicable and enforceable when referenced elsewhere in the Code

Calculate the following correct copper conductor size so that the branch circuit has a maximum voltage drop of 2%. The load on the circuit is 32 amperes, the distance from the load to the panelboard is 400 feet, and the circuit is 208 volts, single-phase.

1 AWG 2% × 208 V = 4.16 V 2 KIL / VD = A 2 × 12.9 × 32 A × 400' / 4.16 V = 79,384.6 cmil = 1 AWG

A Level II EVSE with a rating of 32 amperes at 208 volts is installed. What is the minimum size copper equipment grounding conductor required to serve the installation?

10 AWG Note: Section 250.122 - the EVSE will be served by a 40A OCPD; therefore, the minimum size equipment ground will be 10 AWG.

Two Level II EVSE circuits are installed in the same PVC conduit. Each EVSE is served by a 40-ampere circuit at 240 volts with an EGC run along with the circuits. What size copper EGC is required for this installation?

10 AWG T250.122 - 40 A Circuit = 10 AWG CU equipment ground

Installation of EVSE at an existing building is worth as many as ____ LEED points.

15

Operable parts of accessible equipment should be located ___ above finish grade per ADA guidelines.

15"-48"

Nine Level II EVSEs are installed on a 3-phase, 4-wire 120/208-volt system. Each EVSE is 208/240 volts, single-phase and rated at 24 amperes. What is the minimum ampacity of the copper feeder conductors required to serve the installation?

156 A Note: 24 A × 1.25 = 30 A required for each EVSE 3 units on each phase = 30 A × 3 = 90 A Line current needed to find feeder size: 90 A × 1.732 = 156 A per line needed 156 A = 2/0 Copper

Calculate the voltage drop on a single-phase circuit with 32 amperes of load, a distance of 320 feet from the load to the panelboard, and served by 8 AWG copper THHN conductors.

16 V 2KIL / A = VD (2) × 12.9 × 32A × 320' / 16,510 cmil = 16 V

A 32,000 square foot office building has 120 20-ampere, 120-volt duplex receptacle outlets. What is the branch circuit receptacle load?

28,000 VA Note: 220.14(K) - use largest of either 1 VA per square foot or 180 VA per outlet .180 VA × 120 = 21,600 VA 32,000 ft2 × 1 VA = 32,000 VA

The ? section of the troubleshooting and repair guidelines flowchart outlines issues specific to testing and procedures and may also be used as a sequence of events.

2nd

Level 2 EVSEs with a rating of 6.6 kilowatts can supply ? of charge current when operating at 220 VAC.

30 A I = P/E

An office building has 22 kilovolt-amperes of lighting that is at continuous operation. It also has 35 20-ampere, 120-volt duplex receptacles. Both loads are fed from a 300-ampere panelboard operating at 120/240 volts, single phase. How much more continuous load can be added to the service?

30,560 VA 22 kVA × 1.25) + (35 × 180 VA) = 33,800 VA 300 A × 240 V = 72,000 VA 72,000 - 33,800 VA = 38,200 VA 38,200 VA × 0.8 = 30,560 VA is the capacity left on the continuous load The correct answer is: 30,560 VA

An existing 400-ampere, 120/208-volt, 3-phase, 4-wire service has 30 kilovolt-amperes of non-continuous load and 58 kilovolt-amperes of continuous load. How much more continuous load can be added to the service? (Note: Use 1.732 for the square root of 3.)

33,281.92 VA Note: 30 kVA + (58 kVA × 1.25) = 102.5 kVA 400 A × 208 V × 1.732 = 144,102.4 VA Remaining VA available prior to continuous load correction = 41,602.4 VA 41,602 VA × 0.8 = 33,281.92 VA

What is the general lighting load of a store with an area of 12,000 square feet?

36,000 VA Note: 12,000 ft2× 3 VA per ft2 = 36,000 VA per Table 220.12 Continuous factors are not needed as actual lighting load is all that is requested. Correction factors will apply when sizing the branch circuit OCPD and conductors, which is beyond the question scope.

Leadership in energy and Environmental Design (LEED) has ____ certification levels.

4

According the ADA guidelines, what percentage of general parking spaces should be accessible?

4%

What is the minimum copper THHN feeder size for 12 EVSEs rated at 24 amperes on a 3-phase, 4-wire, 120/208-volt system, assuming four EVSE per phase? (Note: Use 1.732 for the square root of 3.)

4/0 AWG 24 A × 1.25 = 30 A There will be four per phase. 30 A × 4 = 120 A per phase Line current is 120 A × 1.732 = 208 A feeder = 4/0 Copper

Three single-phase Level II EVSE are distributed equally on a 3-phase, 4-wire system and each EVSE draws 24 amperes. What is the line current on each phase? (Note: Use 1.732 for the square root of 3.)

41.56 A 24 A × 1.732 = 41.56 A per phase

Additional EVSEs are to be added to an existing 120/208-volt, 3-phase, 4-wire, 600-ampere service with 220 amperes of non-continuous load and 172 amperes of continuous load. The EVSEs each draw 32 amperes. How many new EVSEs can be added to the service? (Note: Use 1.732 for the square root of 3.)

6 look at the quiz

When an EV and its EVSE is used as a power supply for an optional standby system, requirements found in ? are applied.

702

What is the minimum size XHHW-2 copper conductor permitted to supply a Level II EVSE that has a 30-ampere current rating, assuming 75° terminations?

8 AWG 30 A * 1.25 = 37.5 A = 8 AWG

The SAE standard for wireless charging has specifications that include which of the following? Select one: a.Magnetic triangulation for vehicle alignment over the power source coil b.Means to allow for payment without physical interaction c.Up to 11 kW charging capacity d.All of the above

All of the above

The Society of Auto Engineers (SAE) creates standards for which of the following? Select one: a.Maximum current and voltage specifications for EVSE b.Plug configuration c.Safety features d.All of the above

All of the above

Jurisdictional codes and requirements should ____ be checked when determining the location and other features of the EVSE.

Always

Regenerative braking is best described as

An Energy recovery system

When an EV and EVSE is used to facilitate power supply as an interactive power production source, which article must be applied?

Article 705

Which of the following describes an advantage that hybrid electric vehicles have over traditional gas-powered vehicles? a.Hybrid vehicles are more expensive than gas-powered vehicles. b.Hybrid vehicles have superior efficiency compared to gas-powered vehicles. c.Both a. and b. d.None of the above

B

Electric vehicle supply equipment (EVSE) provides which of the following safety features? Select one: a.A continuously energized output b.GFCI protection c.Hardware fault detection d.Both b. and c.

Both B and C

Which of the following is the Japanese DC quick charging standard? Select one: a.CHAdeMO b.JARI c.SAE d.TEPCO

CHAdeMO

What types of commercial/industrial vehicles are currently available in an electrified version?

Cargo and material-hanling equipment Delivery vans and buses Semi-trailer trucks

Which of the following is not a variable that determines the charging time of an EV? Select one: a.Connector configuration b.Max power capacity of the EVSE's converter c.Size of the electrical feeder/service supplying the EVSE d.All of the above

Connector configuration

Which of the following are benefits of commissioning the installation of electric vehicle supply equipment (EVSE)? a.Increased communication between the customer and installer b.Reduced call back rate c.The customer has peace of mind and is educated in the process d.All of the above

D

Which of the following outlines the steps, in order, for repairing an EVSe unit? a.Disassemble EVSE, lockout EVSE, inspect all components for damage, repair or replace b.Inspect all components for damage, lockout EVSE, repair and replace, disassemble EVSE c.Inspect all components for damage, repair or replace, disassemble EVSE, lockout EVSE d.Lockout EVSE, disassemble EVSE, inspect all components for damage, repair and replace

D

Which of the following drive the market for EVs? a. Cheaper gasoline prices b. Decreased cost of electric vehicles c. Increased interest in alternatives to gas-powered vehicles d. Both b. and c.

D.

Trailblazing signs are for ...

Direct drivers to the location of the EV charging equipment

The EV industry is comprised of ? . a.auto manufacturers b.consumer advocacy groups c.EV charging equipment manufacturers d.research and standards organizations e.all of the above

E

EVSE output cable is permitted to be made from Type ? cable and is generally permitted to have a maximum length of ? .

EVJT / 25'

Determining the appropriate location for EVSE requires the person planning the installation to consider..

How the customer plans on using the installation.

Which of the following is not a category of electric vehicles? a.BEV b.HEV c.ICE d.PHEV

ICE

What improvements in technology have increased interest in EVs?

Improved range, power and lighter batteries

Which of the following is not true of EV charging networks? Select one: a.Charging networks offer both paid memberships and free memberships with pay-as-you-go charging. b.There are over a dozen networks across the U.S. and Canada. c.They allow businesses a way to draw consumers to charging equipment and generate revenue via transaction processing. d.None of the above

None of the above

Which of the following describes a plug-in electric vehicle that runs on batteries until nearly depleted, then switches over to an ICE generator to extend the battery range? a.BEV b.PHEV c.All electric vehicles have this capability. d.No electric vehicle currently on the market has this capabilit

PHEV

Bollards, curbs, and wheel stops can protect charging equipment from...

Physical damage from vehicles

What best describes early EVs?

Quiet, easy to start, and mechanically simple

Quiz 3

Quiz 3

Quiz 4

Quiz 4

Quiz 5

Quiz 5

Quiz 6

Quiz 6

Quiz 8

Quiz 8

Charging is defined as which of the following? a.Refilling brake fluid in an EV b.Removing the batteries from an EV and placing them inside charging equipment c.Replacing batteries in an EV d.Supplying power (kW) to an EV battery

Supplying power (kW) to an EV battery

True of False: Wireless charging is more expensive than coupled EVSE.

True

True or False A battery electric vehicle requires external charging but does not rely on an internal combustion generator for extended range.

True

True or False Cord management is a major concern for manufacturers of EVSE as charge cables can cause a tripping hazard and are often subject to theft.

True

True or False The NECA 413-2012 Standard is the only ANSI-approved standard for EVSE installation and maintenance.

True

True or False: The first EV chargers were external and supplied DC current directly to the vehicle's batteries.

True

True or False: The state of charge is the available capacity of the battery, expressed as a percentage.

True

True or False: DC fast chargers pose accessibility challenges because their cables and connectors are larger and heavier than standard Level 1 and Level 2 EVSE.

True

True or False: Site lighting can help protect charging equipment from being subjected to vandalism.

True

Conductor insulation does not have an effect on voltage drop.

True Note: While insulation type will not directly affect the conductor voltage drop, the insulation must be rated for the operating temperature of the conductor. Per NEC 2017 Chapter 9, Table 8, conductor properties are based at 75°C. Any temperature aside from that will require compensation of the DC resistance per Note 2.

True or False When calculating the voltage drop on a conductor of a given length, the following values must be considered: conductor material, conductor length, and conductor operating temperature.

True Note: While insulation type will not directly affect the conductor voltage drop, the insulation must be rated for the operating temperature of the conductor. Per NEC 2017 Chapter 9, Table 8, conductor properties are based at 75°C. Any temperature aside from that will require compensation of the DC resistance per Note 2.

The proper hand-off of documentation should include electrical details, contract documents, operation and maintenance manuals as well as ? . a.applications and approvals for incentive programs b.inspection reports c.rebate and tax forms d.all of the above

all of the above

The purpose of the J1772 connector pins is to provide ? . Select one: a.a charging interface that is safe for consumers to use b.a means to signal the EVSE to stop charging based on the pin contact state c.signals to the EVSE that the connector is properly seated on the vehicle d.all of the above

all of the above

Which of the following is true about the J1772 standard control pilot terminal pin's function? Select one: a.It changes the state of the EVSE according to the voltage present. b.It defines the state of the EVSE. c.It uses a +12V to -12V AC square wave signal. d.All of the above

all of the above

What are the advantages of wireless charging? Select one: a.Compatibility standards are still under development b.It has no exposed electrical contact points c.Wireless charging has better aesthetic quality d.Both b. and c.

both B and C

A key component of commissioning fleet EVSE is to ensure that the ? understands how to manage the software.

customer

A successful meeting with a prospective customer requires the contractor or contractor's representative to _____

demonstrate that they are qualified and have the needed expertise to handle the project, listen to the customer and ask questions, and look professional.

Article 110 covers ? requirements for wiring and equipment.

general

Installing electric vehicle charging equipment may ____ public perception of a business

improve

EVSE must be equipped with a(n) ? that prevents the charging connector from being accidentally energized before it is connected to the vehicle.

interlock

Conducting an onsite visit when assessing a location for an electric vehicle supply equipment installation is important because

it allows the electrical contractor to understand the prospective customers needs for an EVSE installation AND it provides an opportunity for electrical contractor to gather facts and present themselves as a knowledgeable professional.

EVSE shall have a(n) ? system for shock protection for personnel.

listed

For information regarding specific tools required for servicing EVSE installed in public locations that use tamper-resistant hardware, one should refer to ? .

manufacturer's instructions

The acronym RFID stands for ? .

radio frequency identification

Later in the development of EV charging equipment, the actual charging means was accomplished by a(n) ? that converts AC to DC to be used in charging the vehicle's battery.

rectifier

Temperature ratings of equipment, overcurrent devices, and conductors must be ? and ? to not exceed the lowest rated element of the circuit.

selected / coordinated

One of the tests performed by an EVSE test set is to ? .

test EVSE ground fault response

Which of the following steps in the troubleshooting and repair guidelines flowchart requires PPE for electric hazard?

test unit using an EVSE simulator

According to Article 625, EVSE is equipment that has the specific purpose of transferring energy from ? to the electric vehicle.

the premises wiring system

ADA guidelines are useful when planning an EVSE installation because____

there are no federal standards for EVSE accessibility.

True or False: Proper location of EVSE may include consideration of ADA guidelines depending on location.

true

The first step in the troubleshooting and repair guidelines flowchart is to ? .

visually inspect EVSE

Definitions that are specific to a particular article are located in which of the following sections? Select one: a.xxx.1 b.xxx.2 c.xxx.10 d.xxx.12

xxx.2


Related study sets

Criminal Procedure 5th amendment

View Set

Nursing: A Concept-Based Approach to Learning, 2e (Pearson) Module 40 Professional Behaviors

View Set

More, Psych Ch 16, Psychology Chapter 15, Psychology

View Set

chapter 2: fluids, electrolytes, and acid-bases

View Set

Introduction to Management Information Systems (BADM 2301) Final Review

View Set

General Chemistry Chapter 1 Bowie State University

View Set

Adult Health 2 Peri-operative Care

View Set