Which document establishes the forms, content and procedures for submitting the bid proposals?
Instructions to Bidders
Which document issued by the Architect illustrates what is to be built?
Plans
When there is a conflict between the plans and specifications, the plan will govern.
False
The Spearin Doctrine states that the contractor is not liable for performance when the design specifications have been followed.
True
Which document makes changes, modifications and corrections prior to bid opening?
Addendas
Which document describes the duties and responsibilities of each party and the business procedures for administering the contract?
General Conditions
Which document specifies the Regulations required such as soil erosion or minorities?
General Requirements
"The system shall develop a total output of 20,000 BTU." is considered as a performance specification.
True
"The wall shall be constructed of 2 × 4 studs spaced at 16 inches on center." is Design Specification.
True
Which document describes quality of work, the quality of the materials, and the construction execution procedures?
the technical specifications