Quiz 5: Navisworks Parts 1-3
In construction a typical working day starts from _______________ AM and finishes on _____________ PM.
8AM 5PM
What are the four different task relationship types in scheduling: _________________ _________________ _________________ _________________
FS(finish-to-start), SS(start-to-start), FF(finish-to-finish), SF(start-to-finish)
what is the most common Task relationship in construction? _______________
Finish-to-start
List 2 scheduling file formats/extensions that can be imported under TimeLiner resources tab: a)______ b)______
MPP, CSV
Which Navisworks file format is the most complete one and contains geometry with relevant data (review markup, clash tests, viewpoints)
NWD
Which of the following options is used to enable the avatar to pass through the doors, walls, and etc. in the model? -gravity -collision -crouch -fly
collision
List the other two task types under TimeLiner resource tab: a)__________ b) demolish c)__________
construct, temporary
Which of the following options is used to pass the avatar through those objects that are too low to walk under? -gravity -collision -crouch -fly
crouch
In navisworks you cannot export data in various file formats (T/F)
false
You can modify the geometry of your model in Navisworks (T/F)
false
in navisworks, the gravity option can be used while flying around a model (T/F)
false
in navisworks, the walk and fly tools can be used simultaneously (T/F)
false
Any task in the schedule with zero duration is automatically displayed as a ______________ which is a reference point that marks a major event in a project and is used to monitor the project's progress.
milestone
The 3 Navisworks Files
nwc, nwf, nwd
(Fill the blanks) a) 4D BIM = 3D BIM + ____________________ b) 5D BIM = 4D BIM + ____________________ c) 6D BIM = 5D BIM + ____________________ d) 7D BIM = 6D BIM + ____________________
scheduling, cost, sustainability, facility management
List four basic features/capabilities/tools available through navisworks? ___________ ___________ ___________ ___________
select hide objects save selections timeliner
Clash detection in navisworks refers to detecting interference between objects (T/F)
true
The Global Options are saved for all navisworks sessions (T/F)
true
for creating 4D simulations, you can attach same objects to multiple tasks (T/F)
true
navisworks improves productivity and quality by pre-visualizing the construction project (T/F)
true
navisworks provides the ability to export animation from the TimeLiner in JPEG/PNG formats (T/F)
true
the clear attachment button is used to detach the object from the task (T/F)
true
there is a gantt chart view under the TimeLiner window (T/F)
true
we must assign task type before generating 4D simulation video (T/F)
true
you can hide/unhide elements in navisworks (T/F)
true