Quiz 5: Navisworks Parts 1-3

अब Quizwiz के साथ अपने होमवर्क और परीक्षाओं को एस करें!

In construction a typical working day starts from _______________ AM and finishes on _____________ PM.

8AM 5PM

What are the four different task relationship types in scheduling: _________________ _________________ _________________ _________________

FS(finish-to-start), SS(start-to-start), FF(finish-to-finish), SF(start-to-finish)

what is the most common Task relationship in construction? _______________

Finish-to-start

List 2 scheduling file formats/extensions that can be imported under TimeLiner resources tab: a)______ b)______

MPP, CSV

Which Navisworks file format is the most complete one and contains geometry with relevant data (review markup, clash tests, viewpoints)

NWD

Which of the following options is used to enable the avatar to pass through the doors, walls, and etc. in the model? -gravity -collision -crouch -fly

collision

List the other two task types under TimeLiner resource tab: a)__________ b) demolish c)__________

construct, temporary

Which of the following options is used to pass the avatar through those objects that are too low to walk under? -gravity -collision -crouch -fly

crouch

In navisworks you cannot export data in various file formats (T/F)

false

You can modify the geometry of your model in Navisworks (T/F)

false

in navisworks, the gravity option can be used while flying around a model (T/F)

false

in navisworks, the walk and fly tools can be used simultaneously (T/F)

false

Any task in the schedule with zero duration is automatically displayed as a ______________ which is a reference point that marks a major event in a project and is used to monitor the project's progress.

milestone

The 3 Navisworks Files

nwc, nwf, nwd

(Fill the blanks) a) 4D BIM = 3D BIM + ____________________ b) 5D BIM = 4D BIM + ____________________ c) 6D BIM = 5D BIM + ____________________ d) 7D BIM = 6D BIM + ____________________

scheduling, cost, sustainability, facility management

List four basic features/capabilities/tools available through navisworks? ___________ ___________ ___________ ___________

select hide objects save selections timeliner

Clash detection in navisworks refers to detecting interference between objects (T/F)

true

The Global Options are saved for all navisworks sessions (T/F)

true

for creating 4D simulations, you can attach same objects to multiple tasks (T/F)

true

navisworks improves productivity and quality by pre-visualizing the construction project (T/F)

true

navisworks provides the ability to export animation from the TimeLiner in JPEG/PNG formats (T/F)

true

the clear attachment button is used to detach the object from the task (T/F)

true

there is a gantt chart view under the TimeLiner window (T/F)

true

we must assign task type before generating 4D simulation video (T/F)

true

you can hide/unhide elements in navisworks (T/F)

true


संबंधित स्टडी सेट्स

Chapter VII: Structuring Organization for Today's Challenges

View Set

Math Graphing Linear Equations and Graphing Linear Inequalities

View Set

Chapter 6 Performance Management

View Set

(TOPIC E) WHOLE SCHOOL, WHOLE COMMUNITY, WHOLE CHILD (WSCC)

View Set