BUS5 140 Chapter 7
A tortilla chip workstation produces 1,000 chips in 20 seconds. What is its bottleneck time? _____
.02 seconds per chip
A factory produces 1000 units a month. If design capacity is 3000 and efficiency is 50%, what are utilization and effective capacity? ______
33.3%; 2000
Process A has fixed costs of $1000 and variable costs of $5 per unit. Process B has fixed costs of $500 and variable costs of $15 per unit. What is the crossover point between process A and process B? _____
50 units
Effective capacity is the: _____
Capacity a firm expects to achieve given the current operating constraints.
In the mass service and service factory quadrants of the service process matrix, the operations manager could focus on all of the following except: _____
Customization
Utilization will always be lower than efficiency because:
Effective capacity is less than design capacity.
Activity times should not be included in a service blueprint.
False
An example of the postponement strategy for improving service productivity is having the customer wait until you have sufficient time to serve the customer.
False
Efficiency is actual output as a percent of design capacity.
False
Harley-Davidson, because it has so many possible combinations of products, utilizes the process strategy of mass customization.
False
The bottleneck time is always at least as long as the throughput time.
False
The typical full-service restaurant uses a product-focused process.
False
To find the throughout time with simultaneous processes, compete the time overall the paths and choose the shortest path through the system.
False
A product-focused process is commonly used to produce:
High-volume, low-variety products.
Process X has fixed costs of $10,000 and variable costs of $2.40 per unit. Process Y has fixed costs of $9,000 and variable costs of $2.25 per unit. Which of the following statements is TRUE? _____
Process Y is cheaper than process X at all volumes.
Goods made to order are typical of ________ and ________ approaches while goods made to forecast are typical of ________ and ________ approaches. _____
Process, mass customization; repetitive, product
Frito-Lay is to ________ focus as Harley Davidson is to ________ focus. _____
Product, repetitive
Design capacity is the theoretical maximum output of a system in a given period under ideal conditions.
True
In process-focused facilities, utilization of facilities is low.
True
Service blueprinting is a process analysis technique that focuses on the customer and the provider's interaction with the customer.
True