Chapter 06: Developing a Project Plan (1X2 & true/false)
Arrows on an activity-on-node (AON) project network represent
Project flow and dependency
The likelihood the original critical path(s) will change once the project is initiated is referred to as
Sensitivity
An activity cannot begin until ALL preceding connected activities have been completed.
True
It is acceptable for arrows to cross one another in a network diagram.
True
Using free slack does not delay any following activities and requires no coordination with managers of other activities.
True
Information to develop a project network is collected from the
Work breakdown structure
On a project network, the activity times are derived from the
Work packages
The critical path is the shortest path through a network and indicates activities that cannot be delayed without delaying the project.
False
If, for some reason, the project must be expedited to meet an earlier date, which of the following actions would the project manager take first
Heck to see which activities are on the critical path
An activity that has more than one dependency arrow flowing into it is termed a(n)
Merge activity
When translated into a project network, a work package will become
One or more activities
Activities which can take place at the same time are termed
Parallel activity
________ activities must be completed immediately before a particular activity
Predecessor
The backward pass in project network calculations determines all of the following EXCEPT
Earliest time an activity can finish
An activity can include only one work package.
False
If the project has a duration of 13 days, the project should be completed 13 days from the day it starts.
False