MS Project Quiz
A milestone symbol is represented as
black diamond is a symbolic task used mainly to communicate progress or to mark the end of a significant phase of the project.
Directions can be________. a. estimated or firm b. hard or fast c. managed or calculated d. determinate or indeterminate
estimated or firm
Tasks that must be completed before a task can be started are called ____.
predecessors
An estimated duration appears with a(n) ____ after the duration.
question mark
The ____ is displayed along the top edge of the Gantt chart. Select one: a. timescale b. View Bar c. menu bar d. Entry bar
timescale
In ____ view, the lines drawn between the boxes represent relationships among the tasks and how the sequence must be completed.
Network Diagram
Gaining management agreement to a concise project goal that addresses the issues of ___ is essential for both the project manager and management to stay synchronized with project expectations
Scope -Time Frame -Budget *All of the above
You can find commands such as Resource Usage, Task Usage, and Resource Sheet on the ______ tab.
View
What are task relationships?
Dependencies are the relationships among tasks which determine the order in which activities need to be performed. There are four (4) types of dependency relationships. Finish-To-Start (FS) : The successor can't begin until the predecessor finishes. Start-To-Start (SS) : The successor can't begin until the predecessor begins. Finish-To-Finish (FF) : The successor can't finish until the predecessor finishes. Start-To-Finish (SF): The successor can't finish until the predecessor begins.