MS Project Quiz

अब Quizwiz के साथ अपने होमवर्क और परीक्षाओं को एस करें!

A milestone symbol is represented as

black diamond is a symbolic task used mainly to communicate progress or to mark the end of a significant phase of the project.

Directions can be________. a. estimated or firm b. hard or fast c. managed or calculated d. determinate or indeterminate

estimated or firm

Tasks that must be completed before a task can be started are called ____.

predecessors

An estimated duration appears with a(n) ____ after the duration.

question mark

The ____ is displayed along the top edge of the Gantt chart. Select one: a. timescale b. View Bar c. menu bar d. Entry bar

timescale

In ____ view, the lines drawn between the boxes represent relationships among the tasks and how the sequence must be completed.

Network Diagram

Gaining management agreement to a concise project goal that addresses the issues of ___ is essential for both the project manager and management to stay synchronized with project expectations

Scope -Time Frame -Budget *All of the above

You can find commands such as Resource Usage, Task Usage, and Resource Sheet on the ______ tab.

View

What are task relationships?

Dependencies are the relationships among tasks which determine the order in which activities need to be performed. There are four (4) types of dependency relationships. Finish-To-Start (FS) : The successor can't begin until the predecessor finishes. Start-To-Start (SS) : The successor can't begin until the predecessor begins. Finish-To-Finish (FF) : The successor can't finish until the predecessor finishes. Start-To-Finish (SF): The successor can't finish until the predecessor begins.


संबंधित स्टडी सेट्स

Chapter 48: Personal Property and Bailments

View Set

Anatomy/Physiology Chapter 4: Types of Tissue/ Cell Junction

View Set

Ortografía Español Practica (a donde/adonde/donde/dónde)

View Set

Chapter 2, THE SUPPORT STRUCTURE OF RESPIRATION

View Set

Chapter 25: Assessment of Cardiovascular Function

View Set