PM

¡Supera tus tareas y exámenes ahora con Quizwiz!

Decision tree analysis

1/3 models for project selection and prioritization are presented. Used to select projects based on estimated value

NPV, IRR, ROI, Payback period

1/3 models for project selection and prioritization are presented. Used to select projects based on estimated value

Scorecard analysis

1/3 models for project selection and prioritization are presented. Used to to select and prioritize values based on qualitative criteria.

4/40

40 hrs/4 hrs min

8/80

80 hrs max, 8 hrs min

True

A benefit of project management is that it creates a structure and process that enables a project to be kept under control.

reserve analysis

A comparison of the contingency reserves of schedule, resources, and budget at a particular time during the progress of a project with the original schedule, resources, and budget to determine if there are enough reserves in schedule, resources, or budget best defines

nominal group technique

A decision-making tool used to understand and use the opinion of each and every project member best describes

UML

A graphical language for visualizing, specifying, constructing, and documenting object-oriented software best defines

burndown chart

A graphical representation of the work left to do versus the total scheduled time of an activity or an entire project best describes

Pareto chart

A simple bar graph where the y-axis represents frequency of occurrence best describes

contingency planning

A systematic approach to identify what can go wrong in a project and be prepared with plans, strategies, and approaches to mitigate and manage risks best defines

requirement traceability matrix

A table captured to map all the requirements of all stakeholders in order to track them until the project is complete best defines

fishbone diagram

A tool that allows teams to identify and graphically detail all possible causes related to a problem and discover root causes of the problem at hand best describes

65%

According to a study cited in the textbook, inadequate management practices are associated with project failure. What is the percentage?

Project Documents of Knowledge area 4: Cost Management

Activity cost estimates Basis of estimates Project funding requirements

Project Documents of Knowledge area 3: Time Management

Activity list and attributes Duration estimates Milestone list Project schedule

False

At the CMMI Level 5, software processes are defined by individuals in an organization.

Functional requirements

Capture and specify the behavior of the product, system, or service that is being developed in a project. Brief summary and a rationale that help project stakeholders and outsourced contractors understand why the requirement is needed and track the requirement through the progress of the project

PMBOOK

Collection of processes and knowledge areas generally accepted as best practices within the project management discipline?

Project Management Plan of Knowledge area 7: Communications Management

Communications management pla

Project Documents of Knowledge area 9: Procurement Management

Contracts Proposals Procurement documents Vendor lists Source selection criteria Teaming agreements</TBL>

Project Management Plan of Knowledge area 4: Cost Management

Cost management plan Cost performance baseline

DOCUMENTS DURING PROJECT PLANNING

Customer requirements, Specifications, Functional requirements, Technical requirements, Project plans and planning documents

WBS Level 2

Deliverables

False

Delivery is one of the PMBOK process groups.

Technical requirements

Detailed description of technology that is suitable for the actual design, development, and production processes of a project.

planning process group and time management knowledge area.

Developing schedules, milestones, and critical paths is associated with the

Proper planning can guarantee project success?

False

Project Documents of Knowledge area 7: Communications Management

Forecasts Stakeholder analysis Stakeholder management strategy Stakeholder register

Project plans and planning documents

Formal, approved documents used to guide both project execution and project control.

Project Management Plan of Knowledge area 6: HR Management

Human resources plan Staffing Management Plan

Cost-plus incentive fee contracts

Incentive on seller to reduce cost. Risk on buyer

Project charter

Includes Project purpose or justification, objectives, success criteria, description, risks at a high level Key milestones, Budget information

Stakeholder

Individuals or organizations who are affected by a project best defines

Target cost

Level of cost that a contractor has negotiated with a client. The contract is based on this cost. Both profits and the ceiling price are calculated from this cost.

risk responses

Options and actions that mitigate risks and reduce project threats best defines

Project Documents of Knowledge area 1:Integration Management

Performance reports Project organizational structure Statement of work Project charter Project closure reports Project change requests Project design documents

Project Management Plan of Knowledge area 9: Procurement Management

Procurement management plan

WBS Level 1

Project

Project Management Plan of Knowledge area 1:Integration Management

Project management plan Change management plan Configuration management plan

Project Documents of Knowledge area 5: Quality Management

Quality control measurements Quality control checklists Quality metrics

Project Management Plan of Knowledge area 5: Quality Management

Quality management plan Process improvement plan

Project Documents of Knowledge area 2: Scope Management

Requirement document Requirements traceability matrix Stakeholder requirements Scope document

Customer requirementS

Requirements that satisfy the needs of the customers and the end users

Project Documents of Knowledge area 6: HR Management

Responsibility assignment matrix or Responsibility, Accountability, Consultative, and Informative (RACI) matrix Resource breakdown structure Resource calendars Resource requirements Roles and responsibilities Team performance assessment

Cost-plus fixed fee contracts

Risk on buyer

Project Management Plan of Knowledge area 3: Time Management

Schedule baseline Schedule management plan

Project Management Plan of Knowledge area 2: Scope Management

Scope baseline (scope statement, WBS, and WBS dictionary) Scope management plan Requirements management plan

analyze

Six Sigma DMAIC phase focuses on why and how defects and errors occur?

work packages

Small project activities possibly with very short durations with definable results best defin

Specifications

Specify the requirement in a complete, precise, verifiable manner.

WBS Level 3

Summary tasks - Sub deliverables

True

The discipline of project management is about providing tools and techniques to enable a project team to organize its work and meet the project success factors.

project scope

The general work that needs to be accomplished to deliver a product, a system, a structure, or a service with the specified features and functions best defines

project schedule

The list of all activities of a project with intended start and end dates linked by dependencies and constraints of a project best defines

Stakeholder register

The most important after charter.

complexity.

The number of products or operations that are performed at the same time and the resulting degree of difficulty best defines

True

The overall success factor of a project is the realized value of the project that can be measured by the project stakeholders.

False

The purpose of the QFD technical requirements step is to evaluate how well customer requirements have been met compared to the competition.

Target Profit

The target profit is the negotiated profit in a contract assuming the target cost is met.

Predictable

The traditional SDLC's popularity is because it is

Guaranteed maximum-shared savings contract

This is a great contract for the client as it protects the client against overcharges by the contractor with a ceiling on the contractor price.

Target Price

This is target cost plus target profit and/or target fee found in a negotiated contract.

Target Fee

This target fee is the negotiated fee in a contract assuming the target cost is met.

product scope

Which of the following consists of the features and functions that characterize a product, a service, a system, or a structure?

WBS Level 4

Work packages - Smallest task with short durations

Can risk be positive?

Yes

The selection and prioritization process of organizational projects

alighs with the goals and strategy of the organization.

The most important benefit of a project charter

authorizes a project and ensures that necessary resources and management commitments are provided to achieve success

project scope is a

baseline for performance measurement

Six Sigma asserts that

continuous efforts to reduce process variation are important to overall performance and customer satisfaction in a project.

QFD's graphical format documents

customer requirements, technical requirements, interrelationships.

The TMAP procedure includes

define the project goals, list the knowns, unknowns, and constraints, and sequence and link all team comments, responses and questions.

Project initiation

focuses on project selection and creation of project charters for selected projects.

Steps for nominal group technique for risk management

gathering the core team for a risk workshop using a flip chart or whiteboard to collect information from the team begin by asking each person to identify potential areas of risk

A project

has a beginning and a definite end, expends resources, has constraints and requirements that may include scope, budget, schedule, and resources, performance factors, and creation of value to stakeholders.

Requirement

is a capability that must be met by a system, product, or service to satisfy stakeholders.

Project charter

is a document that formally recognizes a project, includes a problem statement, project objectives, benefits, process owners, and a project sponsor or a champion

Work breakdown structure

is a list of tasks broken down to small manageable activities.

FMEA

is a process in product development and is used in managing operations by analysis of potential failure modes within a system.

Joint Application Design/Development (JAD)

is a process used in prototyping to collect requirements while developing new information systems.

A prototype

is a sample or a model built usually to test a concept, a process, a system, or a product.

SWOT analysis

is a strategic method for identifying whether to use a component or a feature in a project

Joint Requirements Planning (JRP

is a structured group meeting of stakeholders to gather requirements by actively involving the stakeholders to replace individual interviews.

A check sheet

is a table or form that is used to allow a team to systematically record and compile data from historical sources or observations as they happen in real time.

Document analysis

is a technique used in creating requirements from "as-is" process documents.

Use case

is a technique used in software projects to document the potential requirements of a new system or software by conveying how the system should interact with the end user or another system to achieve a specific business goal graphically.

The Kano model

is a tool to distinguish types of product requirements that influence customer satisfaction.

Scope creep

is the addition of scope after it is defined in the scope document.

project life span / project life cycle

is the total of the phases through which a project passes from the time it is initially conceived until the time it is either in use as a success or abandoned as a failure.

Factor for using Agile methods include

prioritization of tasks is done by key stakeholders. works well with true teamwork and collaboration. shortened development cycles.

Goal of the project selection

process is to analyze project viability, approve or reject project proposals based on established criteria.

Fixed-price incentive fee contracts

risk on both seller and buyer

Cost-plus percentage fee contracts

risk on both seller and buyer. Client faces more because contractor has motivation to increase cost.

Stakeholder analysis includes

stakeholder characteristics, level of interest of the stakeholders in the specific project, ability to affect the project policies through power and/or leadership.

Requirements Traceability Matrix

table captured to map all the requirements of all stakeholders in order to track them until the project is complete.

During the early stages of a project

tactics are NEVER more integral to success than strategy

The more the authority and the responsibility are shared between the functional and project managers

the better the chances of project success.

Fixed-price contracts

this is the cost and that's it. Max. risk on seller. Lowest risk for buyer. For the contractor, any cost-plus contract is better than fixed-price contracts with respect to risks.


Conjuntos de estudio relacionados

Statistics - Ch5 z Scores and standardized distributions

View Set

39. Purine and Pyrimidine Metabolism

View Set

Lecture 3: Male reproductive tract-common species

View Set

chapter 23: Pharmacologic Pain Management- OB

View Set

InQuizitive: Chapter 11. Health and Society

View Set

Macro FINAL Ch. 11 practice quiz

View Set

FAMILY CHILD AND HUMAN DEVELOPMENT FINAL

View Set