Scrum 3
What are the two primary ways a Scrum Master keeps a Development Team working at its highest level of productivity?
By facilitating Development Team decisions By removing impediments that hinder the Development Team Feedback A Scrum Master is a servant-leader for the Development Team. Facilitation and removing impediments serves a team in achieving the best productivity possible.
Upon what type of process control is Scrum based?
Empirical
True or False: When multiple teams work together on the same product, each team should maintain a separate Product Backlog.
False Feedback Products have one Product Backlog, regardless of how many teams are used. Any other setup makes it difficult for the Development Team to determine what it should work on.
The three pillars of empirical process control are:
Inspection, Transparency, Adaption Feedback Scrum is founded on empirical process control theory, or empiricism. Empiricism asserts that knowledge comes from experience and making decisions based on what is known. Three pillars uphold every implementation of empirical process control: transparency, inspection, and adaptation.
Which statement best describes the Sprint Review?
It is when the Scrum Team and stakeholders inspect the outcome of a Sprint and figure out what to do next.
Which of the following services are appropriate for a Scrum Master in regard to the Daily Scrum?
Teach the Development Team to keep the Daily Scrum within the 15 minute time-box. Feedback The Scrum Master ensures that the Development Team has the meeting, but the Development Team is responsible for conducting the Daily Scrum. The Scrum Master teaches the Development Team to keep the Daily Scrum within the 15-minute time-box. The Scrum Master enforces the rule that only Development Team members participate in the Daily Scrum.
Who is responsible for managing the progress of work during a Sprint?
The Development Team Feedback The Development Team uses the Daily Scrum to inspect progress toward the Sprint Goal and to inspect how progress is trending toward completing the work in the Sprint Backlog.
The Development Team should not be interrupted during the Sprint. The Sprint Goal should remain intact. These are conditions that foster creativity, quality and productivity.
The Sprint Backlog is fully formulated in the Sprint Planning meeting and does not change during the Sprint. Feedback The Sprint Backlog makes visible all of the work that the Development Team identifies as necessary to meet the Sprint Goal. The Development Team modifies the Sprint Backlog throughout the Sprint, and the Sprint Backlog emerges during the Sprint.