Which of the following is a limitation of PERT and CPM? A. There is the inherent danger of placing too much emphasis on the critical path. B. They can be used only to monitor schedules. C. The graphical nature of a network delays comprehension of the activity list's interrelationships. D. They are applicable to only a narrow variety of projects and industries.
A. There is the inherent danger of placing too much emphasis on the critical path.
Which of the following is a direct responsibility of the project manager? A. making sure that the people assigned to the project receive the motivation, direction, and information needed to do their jobs B. calculating completion probabilities for all tasks in the project C. drawing the network diagram D. performing all of the activities in the project
A. making sure that the people assigned to the project receive the motivation, direction, and information needed to do their jobs
Which of the following does NOT belong to the planning phase of project management? A. monitoring resources B. goal setting C. defining the project D. team organization
A. monitoring resources
The three phases involved in the management of large projects are A. planning, scheduling, and controlling. B. scheduling, operating, and evaluating. C. scheduling, designing, and operating. D. planning, scheduling, and evaluating.
A. planning, scheduling, and controlling.
Which of these statements is NOT true about project scheduling? A. Project scheduling identifies the precedence relationships among activities. B. Project scheduling helps make better use of resources by identifying the non-critical paths through the network. C. Project scheduling shows the relationship of each activity to others. D. Project scheduling encourages the setting of realistic time and cost estimates for each activity.
B. Project scheduling helps make better use of resources by identifying the non-critical paths through the network.
Among the following, critical path and slack time analysis MOST help A. highlight relationships among project activities. B. pinpoint activities that need to be closely watched. C. point out who is responsible for various activities. D. managers define the project activities.
B. pinpoint activities that need to be closely watched.
Gantt charts are A. not widely used. B. planning charts used to schedule resources and allocate time. C. not easy to understand. D. widely used network techniques.
B. planning charts used to schedule resources and allocate time.
The project organization may be LESS helpful when A. work tasks can be defined with a specific goal and deadline. B. the job is familiar to the existing organization. C. the work contains complex interrelated tasks requiring specialized skills. D. the project cuts across organizational lines.
B. the job is familiar to the existing organization.
Which of the following activities are NOT part of project scheduling? A. Decide how long each activity will take. B. Compute resources needed at each stage of production. C. Make sure all necessary activities are finished in proper sequence and on time. D. Chart separate schedules for personnel needs by type of skill and materials needs.
C. Make sure all necessary activities are finished in proper sequence and on time.
Which of the following is NOT true regarding PERT and CPM? A. PERT and CPM are useful in monitoring costs. B. PERT and CPM are useful when controlling large projects. C. Managers only need to closely monitor the critical path. D. Time estimates are subject to fudging by managers.
C. Managers only need to closely monitor the critical path.
Computerized PERT/CPM reports and charts do NOT include A. detailed cost breakdowns for each task. B. variance reports. C. probability estimates for on-time completion. D. cost distribution tables.
C. probability estimates for on-time completion.
Which of the following is the THIRD level in work breakdown structure (WBS)? A. activities to be completed B. project C. subtasks in major tasks D. major tasks in the project
C. subtasks in major tasks
Which of the following is NOT true about Gantt charts? A. Gantt charts also can be used for scheduling repetitive operations. B. Gantt charts are planning charts used to schedule resources and allocate time. C. Gantt charts are low-cost means of helping managers make sure that activities are planned. D. Gantt charts adequately illustrate the interrelationships between the activities and the resources.
D. Gantt charts adequately illustrate the interrelationships between the activities and the resources.
What is the most popular example of specialized software for managing projects? A. Microsoft Management Tool B. PERT/CPM+ C. Project Apple D. Microsoft Project
D. Microsoft Project
Which of the following is an advantage of PERT and CPM? A. Project activities have to be clearly defined, independent, and stable in their relationships. B. Useful in monitoring only schedules. C. Precedence relationships must be specified and networked together. D. Straightforward concept and not mathematically complex.
D. Straightforward concept and not mathematically complex.
Which of the following activities does NOT belong to the controlling phase of project management? A. revise plans B. monitor resources, costs, quality, and budgets C. shift resources D. define the project
D. define the project
Which of the following is NOT part of project controlling? A. close monitoring of resources, costs, quality, and budgets B. shifting resources to where they are needed most C. using a feedback loop to revise the project plan D. sequencing and allotting time to all project activities
D. sequencing and allotting time to all project activities
Which of the following is NOT a technique that allows managers to plan, schedule, and control projects? A. CPM B. Gantt charts C. PERT D. Factor-rating method
D. Factor-rating method
Which of the following activities are NOT part of the project scheduling?
Decide how long each activity will take.
How is the EF computed?
ES + Activity time
Which of the following is NOT true regarding PERT and CPM?
Managers only need to closely monitor the critical path
The latest finish of an activity is
Min{ LS of all immediate following activities}
the main difference between PERT and CPM is that
PERT employs three time estimates for each activity
which of the following statements regarding CPM is true?
all activities on the critical path have their LS equal to the maximum EF of all immediate predecessors.
Dummy activities
are used when 2 activities have identical starting and ending events
the _______ distribution is used by PERT analysis to calculate expected activity times and variances
beta
Which of the following represents the FIRST step to crash a project?
computer the crash cost per week for each activity in the network
What is the shortest duration required to complete an activity?
crash time
which of the following does NOT belong in the controlling phase of project management
define the project
Which of the following steps is NOT a basic step followed b PERT and CPM?
identify and eliminate the non-critical activities
which of the following statements regarding CPM networks is true?
if a specific project has multiple critical paths, all of them will have the same duration
With respect to PERT and CPM, slack
is the amount of time a task may be delayed without changing the overall project completion time
The critical path of a network is the
longest time path through the network
which is the most popular example of specialized software for managing projects
microsoft project
The most realistic estimate of the time required to complete an activity is referred to as what?
most likely time
Which of the following is a basic assumption of PERT?
no activity in the network must be repeated
the difference between AON and AOA networks is that
nodes consume no resources or time in AOA networks nodes designate activities in AON, while arrows designate activities in AOA both are acceptable in practice, however, microsoft project uses AON AOA networks sometimes require dummy activities ALL OF ABOVE ARE TRUE
Which of the following is used for computations in CPM?
normal time
which of the following statements regarding critical path is true
on a specific project, there can be multiple critical paths, all with exactly the same duration
the time an activity will take assuming very unfavorable conditions is
pessimistic time
Which of these estimates is NOT used in PERT?
standard time
Which of these time estimates is NOT used in PERT?
standard time
PERT analysis computes the variance of the total project completion time as
the sum of variances of all activities on the critical path
which of the following is a limitation of PERT and CPM
there is an inherent danger of placing too much emphasis on the critical path
which of the following statements is an assumption PERT makes regarding the probability of finishing the project on time
total project completion time follows a normal probability distribution