Which is true about the agile method?
It uses several iterations or deliveries of software instead of waiting until the end of the project to provide a product.
Which project would be compatible with the use of the agile approach?
Projects that have more flexible scheduling
Which activity is a part of the Scrum planning process?
Creating sprint backlog
The burndown chart is a Scrum created artifact that provides a list of features prioritized by business value.
False
A sprint review is a meeting in which the team demonstrates to the product owner what it has completed during the sprint.
True
In the Scrum method, team members work as a self-directed group coached by the ScrumMaster.
True
The two main items for monitoring and controlling in the Scrum framework are the daily Scrum and the sprint retrospectives.
True
What important Scrum artifact is used to graphically display progress on each sprint during the monitoring and controlling process?
burndown chart
In the Scrum method, during which meeting is the improvement of the product and process discussed?
sprint retrospective
A _____ is usually not necessary to the Scrum method, because Scrum implies that team members work as a self-directed group.
team charter