CM 4211

Réussis tes devoirs et examens dès maintenant avec Quizwiz!

Which of the following statements is true? Select one: a. Whether a project will require union labor or not is something that will be found in the general conditions. b. Bid forms may require information about the contractor's work history and financial strength. c. The bid form itself is drafted and completed by the contractor d. Instructions to Bidders is where prospective bidders find out how to get to the owner's office to pick up the bid documents.

Bid forms may require information about the contractor's work history and financial strength.

Most negotiated contracts use the unit price method of construction.

False

Which of the following statements is true? Select one: a. . If the contract contains a "no-damages-for-delay" clause, the contractor will not be entitled to either a time adjustment nor a cost adjustment in the contract caused by a delay. b. Contractors prefer a contract to have a narrow list of excusable delays. c. In the dispute resolution clause of a private project contract, it is important to know whether or not sovereign immunity has been waived. d. If a contract has no differing site conditions clause, then the contractor is responsible for the costs if conditions are encountered that are more costly to overcome.

If a contract has no differing site conditions clause, then the contractor is responsible for the costs if conditions are encountered that are more costly to overcome.

Which of the following statements is true? Select one: a. In a cost-plus-incentive-fee (CPIF) contract the contractor can lose money. b. In a guaranteed-maximum-price (GMP) contract the contractor can never lose money. c. A fixed price contract holds more risk for the owner than a cost-plus contract. d. A schedule-of-items contract is a type of cost-plus-incentive-fee contract.

In a cost-plus-incentive-fee (CPIF) contract the contractor can lose money.

Which of the following statements is true? Select one: a. Standard form contracts are used because they contain provisions deemed to be fair to the parties. b. The four most important things that should be in an advertisement (for a construction project) are (1) project identification, (2) contractor identification, (3) time and place for the bid opening, and (4) instructions how to get the bid documents. c. The completed "bid form" is the contract in a construction project. d. In an AIA standard form contract, if there is any bias it is in favor of the contractor.

Standard form contracts are used because they contain provisions deemed to be fair to the parties.

Which of the following statements is true? Select one: a. "Liquidated damages" are assessed based on the actual damages suffered by the owner. b. The time provisions in a construction contract are usually measured in work days. c. The owner usually has the unilateral right to terminate a construction contract. d. A contractor cannot be assessed damages for missing milestone completion dates provided that he completes the entire contract timely.

The owner usually has the unilateral right to terminate a construction contract.

Which of the following statements is NOT true? Select one: a. There is no implied obligation for the owner to provide access to the construction site b. A default termination by the owner may be justified if the contractor is doing unsatisfactory work. c. "Liquidated damages" is the amount per day that a contractor owes for completing the contract late d. . It is normal for a contract to provide for monthly progress payments to the contractor.

There is no implied obligation for the owner to provide access to the construction site

"ESOP" stands for Employer Stock Operation Plan.

false

"LLC" stands for Limited Liability Corporation.

false

"Liquidated damages" are assessed based on the actual damages suffered by the owner.

false

A contract may be formed even when the objective is unclear.

false

A contractor cannot be assessed damages for missing milestone completion dates provided that he completes the entire contract timely.

false

A corporation is formed under federal laws

false

A fixed price contract holds more risk for the owner than a cost-plus contract

false

A partnership agreement must be in writing.

false

A partnership is an association of four or more entities formed to carry on a business for mutual profit.

false

A permanent license surety bond guarantees a contractor before the contractor becomes licensed.

false

A prime contract is any contract in which one of the parties is a construction contractor

false

A schedule-of-items contract is a type of cost-plus-incentive-fee contract.

false

A subcontractor has a contract with the owner.

false

An S corporation can have an unlimited number of stockholders

false

An offer is a conditional willingness to enter into an agreement.

false

Consideration must always be in terms of money for there to be a contract.

false

Contractors prefer a contract to have a narrow list of excusable delays.

false

Corporation is the simplest form of business entity.

false

Design-Build is the traditional approach to construction.

false

Fast-track services work best when there are separate contracts for design and construction

false

If the contract contains a "no-damages-for-delay" clause, the contractor will not be entitled to either a time adjustment nor a cost adjustment in the contract caused by a delay

false

In a cost-plus-percentage-fee (CPPF) contract, in addition to the contractor's reputation, there is a profit incentive for the contractor to hold down the costs of the construction.

false

In a guaranteed-maximum-price (GMP) contract the contractor can never lose money

false

In agency construction management the construction manager is at risk.

false

In an AIA standard form contract, if there is any bias it is in favor of the contractor.

false

In the dispute resolution clause of a private project contract, it is important to know whether or not sovereign immunity has been waived

false

In the traditional approach to construction, there will be one prime contract.

false

Instructions to Bidders is where prospective bidders find out how to get to the owner's office to pick up the bid documents.

false

Long-term financing is used to pay the construction costs.

false

Most construction projects are not unique because they resemble each other.

false

Officers of a corporation are not considered to be agents of the corporation.

false

Preemptive rights give a stockholder of a corporation the right to preempt actions by a creditor.

false

Retainage (or retention) is an amount kept by the owner from the progress payments to the contractor in order to penalize the contractor for completing the project late.

false

Supplementary conditions supplement the general conditions and usually remain the same from contract to contract.

false

The bid form itself is drafted and completed by the contractor.

false

The completed "bid form" is the contract in a construction project.

false

The contractor does not need to inspect the site prior to submitting a bid unless the bid documents expressly require such an inspection.

false

The five-threshold red flag construction contract clauses are (1) dispute resolution, (2) changes, (3) differing site conditions, (4) payments and progress payments, and (5) terminations and partial terminations.

false

The four most important things that should be in an advertisement (for a construction project) are (1) project identification, (2) contractor identification, (3) time and place for the bid opening, and (4) instructions how to get the bid documents.

false

The time provisions in a construction contract are usually measured in work days.

false

There is no implied obligation for the owner to provide access to the construction site.

false

Unless provided otherwise in a contract, the contractor is entitled to be paid for the invoice cost of materials delivered to the site even though they may not have been incorporated into the project at the time of billing the owner

false

Value engineering refers to saving money by cutting the quality of materials.

false

Whether a project will require union labor or not is something that will be found in the general conditions.

false

"Liquidated damages" is the amount per day that a contractor owes for completing the contract late.

true

A "variation in quantities" clause is intended to prevent an unfair gain or loss by the contractor due to a difference in the quantities actually incorporated into the project compared to what was estimated in the contract.

true

A default termination by the owner may be justified if the contractor is doing unsatisfactory work.

true

A design-build (DB) contract reduces the likelihood of a disagreement between the designer and the contractor.

true

A general partner of a partnership is an agent of the partnership.

true

A joint venture is an entity formed for one project.

true

A limited liability company is one of the formations used by construction companies.

true

A limited partnership means that the general partner is limited in his liability for partnership debts.

true

A set-aside is an amount of work reserved for small disadvantaged business enterprises

true

An "exculpatory" clause is one that shifts liability from one party to another (usually from the owner to the contractor).

true

An S corporation is a corporation that has elected to be taxed as a pass-through entity.

true

An acceptance that has conditions attached to it is a counter offer.

true

An architect is usually the lead designer on a commercial construction project

true

An illegal contract is unenforceable.

true

An indemnification clause can hold an owner harmless from losses on the project even if they are caused by the owner.

true

Bid forms may require information about the contractor's work history and financial strength.

true

Building codes are enforced by the use of permits, inspections, and testing reports

true

Competitive bidding and negotiated contract are the two basic ways to select a contractor

true

Competitive bidding is said to accomplish efficiency and innovation.

true

Consent to a contract cannot be coerced.

true

Custom residential building is when the owner has a building designed and built for the owner.

true

Directors of a corporation are not considered to be agents of the corporation.

true

Escalation clauses are used on long-term contracts to allow for increased labor and material costs.

true

Fast-Track refers to overlapping design and construction.

true

Hospital construction is one of the four broad categories of construction

true

If a contract has no differing site conditions clause, then the contractor is responsible for the costs if conditions are encountered that are more costly to overcome.

true

In a cost-plus-fixed-fee (CPFF) contract the contractor is incented to complete the project as soon as possible.

true

In a cost-plus-incentive-fee (CPIF) contract the contractor can lose money

true

In a dissolution of a partnership a partner who lends money to the partnership is paid ahead of any creditors of the partnership

true

It is normal for a contract to provide for monthly progress payments to the contractor.

true

More than half of the construction companies in the United States are proprietorships

true

Privity is the existence of a contractual relationship.

true

Public and private are the two broad classes of owners on a construction project.

true

Some of the largest projects in the United States were built by joint ventures

true

Standard form contracts are used because they contain provisions deemed to be fair to the parties

true

The changes clause usually gives the owner the unilateral right to make changes to the contract.

true

The contractor may rely on physical condition reports provided by the owner, supported by pre-bid inspection, unless the contract states otherwise

true

The owner acts as the prime contractor on a day labor construction project.

true

The owner usually has the unilateral right to terminate a construction contract.

true

The prime contractor is in privity with the owner on a construction project.

true

The two main reasons for licensing a contractor is to protect public health and safety.

true

Usually, inference is not enough to form a third-party relationship.

true


Ensembles d'études connexes

Psychology of Learning Troy University Test 5 - Rost

View Set

Money & Banking HW #2, Econ 3229 quiz 4, Money & Banking Chapter 4.2, Ch 4 Econ 3311, MB Chaper 4 Quiz, chapter 4, Midterm #1 Quiz Practice, Chapter 4 Quiz, Chapter Three, Mishkin Chapter 3 What is Money?, Chapter 3, Monetary Policy Chapter Three, Mo...

View Set

Fundamentals of Nursing Unit 7 Ch. 41.

View Set