PMG201 Course 2

Réussis tes devoirs et examens dès maintenant avec Quizwiz!

24.To calculate early start (ES) and early finish (EF) perform a: A.Forward pass B.Backward pass C.Critical pass D.Lateral pass

A

1.True or False: The term resources only refers to people, it does not include money or materials or equipment. A.False B.True

A

12.When you have good historical information which can be used in a reliable formula or model, you will probably use: A.Parametric estimating B.Exact estimating C.Analogous estimating D.Bottoms up estimating

A

16.You are building an apartment complex with four, 10,000 square foot buildings based on the same drawings you used in another city two years ago. What is the danger of estimating using the same parametric model of $50 per square foot? A.Historical cost relationships may no longer be applicable. B.It will take much more time than a bottoms up estimating. C.The technical design is unstable. D.It's not very easy to scale.

A

19.True or False: The S-Curve depicts the relationship between the cost baseline budget and the schedule because it shows the planned cost baseline budget across the planned project timeline. A.True B.False

A

20.Earned value management integrates scope, cost, and schedule measures to: A.assess project performance and progress. B.assess whether all requirements were met. C.develop a preliminary budget. D.assess communication effectiveness among project team members.

A

22.True or False: If develop online modules must be 100% completed before review online modules can begin, that is called a finish to start relationship. A.True B.False

A

3.True or False: When you are concerned that your estimates might not be correct, especially if you think they are too low, you should pad the estimate and add extra. A.False B.True

A

30.Once the logic of a network is laid out, the project manager will conduct a forward pass and a backward pass through the network. This will provide information regarding ______ and will identify the________. A.The total duration of the project, critical path B.The high risk activities, non-critical path C.Resource shortages, high risk activities D.The slack for each activity, high risk activities

A

6.True or False: When it comes to projects, the emphasis is on strategic quality management. Quality is not an accident, quality is part of the plan, and quality is everyone's job. A.True B.False

A

9.The Process Improvement Plan is: A.a subsidiary, or component of the project management plan. B.The number one component of the project management plan.

A

10.True or False: Performing quality assurance within the context of a project involves applying the planned, systematic quality activities to ensure that the project correctly employs all processes needed to meet project objectives and product requirements. A.False B.True

B

14.Which one of these most correctly defines management reserve? A.Management reserve is tied to a specific milestone or event. B.Management reserve is not tied to specific work packages it is for the entire project. C.Per our lesson, management reserve and contingency are exactly the same. D.Management reserve is tied to specific work packages.

B

15.You are preparing an estimate of the cost for an IT system expansion for a new branch office location. It is a very similar to the IT system expansion undertaken for a branch office that opened six months ago. Which technique might you use if you are pushed for a quick estimate? A.Bottoms up B.Analogous C.Parametric D.Probabilistic

B

17.What description defines Bottoms Up Estimating? A.A technique that uses a mathematical model to estimate costs. B.A technique that involves estimating the cost of individual work packages or individual schedule activities with the lowest level of detail. C.A technique that analyzes activities on past projects and using them as a basis for estimating costs.

B

18.True or False: The Project Budget is equal to only the cost baseline budget. A.True B.False

B

23.If develop online modules needs to finish before review online modules can finish, that is called a: A.Start to start relationship. B.Finish to finish relationship. C.Start to finish relationship. D.Finish to start relationship.

B

25.True or False: The critical path is the shortest path through the network and represents the work that can be delayed without delaying the end of the project. A.True B.False

B

28.In a project schedule, the sequence of activities which cannot be delayed during the course of the project without extending the project end date is referred to as the: A.Schedule baseline B.Critical path C.Action plan D.Slack line

B

29.A significant event in a project that may indicate completion of a major phase is a/an: A.Activity B.Milestone C.Work package D.Deliverable

B

5.The WBS is used to derive all but one of the following: A.The project schedule baseline B.The business need for the project C.The project cost performance baseline D.The activity list

B

7.The discipline of quality management complements the discipline of project management. Both recognize the importance of: A.Company satisfaction, continuous improvement, and management protocol B.Customer satisfaction, prevention over inspection, continuous improvement, and management responsibility C.Team satisfaction and inspection over prevention D.Responsibility of only the sponsor, continuous improvement, and inspection

B

8.True or False: Product quality focuses on the project management processes used to meet project objectives A.True B.False

B

11.An estimate created by looking at a similar project or activity and then adding or subtracting to or from the estimate based on the differences between the two is called: A.Exact estimating B.Parametric estimating C.Analogous estimating D.Bottoms up estimating

C

2.In our lessons the acronym RAM stands for: A.Responsible Accountable Manageable B.Resource Aligned Management C.Responsibility Assignment Matrix D.Responsibility Accountability Matrix E.Resource Acquisition Management

C

21.When you schedule work in a specific order because it cannot be completed any other way this is what type of dependency? A.External B.Discretionary C.Mandatory D.Internal

C

26.The network diagram is the best tool for demonstrating: A.Schedule performance over time B.Resource requirements C.The sequence of project activities D.Schedule variances

C

27. All of the following are inputs to estimating activity durations except: A.Activity list and activity attributes B.Resource calendars and scope statement C.Requirements specifications D.Organizational process assets

C

3.When you use the RACI or Responsible, Accountable, Consult, Inform version of the RAM, those who are responsible are: A.Providing subject matter expertise B.Not completing the work C.Completing the work D.Supervising the work

C

4.A work package is a/an: A.Activity at the lowest level of the WBS B.Required level of reporting C.Activity that can be assigned to one or more organizational units D.Deliverable at the lowest level of the WBS

D


Ensembles d'études connexes

Econ 2040 Exam 4 Ch. 21 Review Questions

View Set

ACT English Multiple Choice Questions

View Set

Biotech CHAPTER 6 Types of Assays

View Set

Chapter 7: Emerging and Early Adulthood

View Set

Plasma Membrane & Plant Cell Wall

View Set