Project + Practice Qs (CompTIA Certmaster)

Réussis tes devoirs et examens dès maintenant avec Quizwiz!

While you are executing your project, you are tracking your costs. Your original definitive estimate for a task's cost was $15,000. This means that the actuals should come in at between:

$14,250 and $16,500 (The -5% to +10% range is the range for the definitive estimate, so -5% of $15,000 is -$750 or $14,250, and +10% is $1,500, yielding $16,500.)

The project is 50% complete. The project plan was up to 10 months, 150 gadgets ($55 each) per month. The total budget is $9,000. The value of the project is

$4500 ($9000 * 50%)

You are working on a project with an original $650,000 budget. Halfway into the project, the management team tells you that they are increasing your budget by 20%. That means that your new budget is:

$780,000 (20% of $650,000 is $130,000, which is added to the original $650,000 for a total of $780,000, regardless of how much has already been spent.)

Which of the following is a formula for estimating?

(Optimistic + (4 x Most Likely) + Pessimistic) / 6

The budget is $200,000 is in month #9 and it has an earned value of $180,000 and actual costs of $190,000. The cost variance is:

-$10,000 (CV = EV - AC)

(2.1 part 1) When you created your original budget in project initiation, you used a Rough Order of Magnitude (ROM) estimate. Now that you are moving into executing, you need to give management a definitive estimate. This means that the original accuracy range of the estimate was:

-25% to +75% (A Rough Order of Magnitude (ROM) estimate means that the actual costs will vary from 25% less than the estimate to 75% more than the estimate.)

When you created your original budget in project initiation, you used a Rough Order of Magnitude (ROM) estimate. Now that you are moving into executing, you need to give management a definitive estimate. This means that the accuracy range of the new estimate must be:

-5% to +10% (This range is the one your new definitive estimate must meet.)

A project has EV of $5,000 and cost of $6,000. What is the CPI?

0.83 (CPI=EV/AC)

A quality control engineer at AdventureWorks Cycles has detected that the brake pad polishing machine on the high-speed braking system project has been turning out defective pads. He or she has collected the following data about the malfunctioning machine: (see image) The engineer uses a Pareto chart and determines that 61 percent of the malfunctions can be attributed to some of the sources. How many sources are involved? [Hint: You do not need to create the chart to find the answer.]

2 (2 most-frequent sources of malfunctions accounted for 61% of the problems. 309 malfunctions, and (309 * 0.61) = 189. A dirty polishing wheel and a loose sprocket accounted for the 189 malfunctions.)

You are working on a project to upgrade the Human Resources Management System (HRMS). You started with a team of six, but you recently added three new members. How many lines of communication were added by the increase in team members?

21 (The formula for calculating lines of communication is (n*n-1)/2, so there were originally 15 lines and now there are 36, for an increase of 21, which is more than double. (9*8/2=36, 6*5/2=15 > 36-15=21)

You are working on a project to upgrade the Human Resources Management System (HRMS). You are ten weeks into the 24-week project and your sponsor leaves the organization. The new sponsor decides that the schedule should be cut by at least three weeks. This represents approximately what percentage of a decrease of the remaining duration?

21 percent (There are 14 weeks of duration remaining (24 - 10). A 3 week decrease over the 14 weeks is approximately a 21% decrease.)

A project has five activities, all related in a finish-to-start relationship. The table below depicts the durations and predecessors of each activity. (see image) How long is the critical path? (1.6-part 2)

27 weeks (calculated by adding the durations of each activity on each path and selecting the path with the longest duration. The critical activities are ABCE. ABE is 17 weeks. ADE is 13 weeks. ACE is 20 weeks.)

You have a task in your project that is estimated at 72 hours of effort. You assigned one person full-time to the task working eight hours per day. The task can be worked on effectively by more than one person at the same time. If you assign a second person to the task working four hours a day, how much faster can the task be completed?

3 days (2 resources working a total of 12 hours per day can complete the task in 6 days, whereas the single resource would have taken 9 days.)

The original project plan you created contained six deliverables each requiring equal effort and duration. Through formal change control, another four deliverables - equal in effort and duration - were added to the plan. You have completed one of the original deliverables and two of the new. Based solely on the progress of the deliverables, you can tell the stakeholders that the project is currently:

30% complete (You have completed three of a total of ten deliverables of equal effort and duration)

An engineering company has completed design and construction of a petroleum refinery to produce gasoline. Part-way through construction, the engineers added a new process to produce another product unrelated to gasoline. Near the end of the construction effort, the owners decided to add a warehouse to store chemicals used in the gasoline refining process. When the refinery construction was completed, the engineering company began to operate the refinery. At this time, a contractor was brought in to correct problems that occurred during construction. How many projects were associated with this effort?

4

The new bridge over the Troubled Waters stream involves an activity to grade the approaches to the bridge. From previous projects, grading has exhibited a range of durations, as shown below: Optimistic 1 day Most Likely 3 days Pessimistic 12 days What is the PERT three-point duration estimate for this activity?

4.2 days (PERT=[Optimistic time + 4(Most Likely time) + Pessimistic time] / 6)

A quality control engineer at AdventureWorks Cycles has detected that the brake pad polishing machine on the high-speed braking system project has been turning out defective pads. He or she has collected the following data about the malfunctioning machine: (see image) The engineer uses a Pareto chart to determine the percentage of the malfunctions due to the top three sources. What is the result of this investigation? [Hint: You do not need to create the chart to find the answer.]

75 percent (The Pareto chart would show that the top 3 problems accounted for 300 occurrences out of the 400 total occurrences, or 75%)

Activity A on the AdventureWorks high-speed braking system project has a start-to-start precedence relationship with Activity B; further, Activity B has a 2 day lag. If A's duration is 8 days, and B's duration is 5 days, what is the total amount of time it should take to complete both A and B?

8 days (A and B will take a total of 8 days. A will start on day 1 and finish on day 8. B will start on day 3 and finish on day 7. The duration of A is longer than the sum of the lag of B and the duration of B, hence the total duration for A and B will be the duration of A, or 8 days.)

Activity A on the AdventureWorks high-speed braking system project has a finish-to-finish precedence relationship with Activity B. If A's duration is 2 days and B's duration is 8 days, what is the shortest total duration for completing both A and B?

8 days (The shortest duration will be 8 days because Activity B must finish after A because of the finish-to-finish relationship. Remember that in a finish-to-finish relationship, when the predecessor (A) finishes, then the successor (B) can finish.)

The Public Works Department manager of a project to build a new bridge over the Troubled Waters stream is planning the duration of an activity to demolish the old bridge. From previous projects, this activity has exhibited a range of durations, as shown below: Optimistic 3 days Most Likely 8 days Pessimistic 15 days What is the PERT three-point duration estimate for this activity?

8.3 days (PERT = [Optimistic time + 4(Most Likely time) + Pessimistic time] / 6)

A project manager must understand the sponsor's priorities among the triple constraints because:

A change in any one causes a change in at least one other

Which statement best describes a portfolio?

A collection of projects that are grouped to achieve the strategic business objective of an organization.

You are working on the installation of a new Customer Relationship Management (CRM) system and are developing the project change control plan. Which of the following is NOT a component?

A completed scope change request (A change control plan would define scope changes but not include any specific ones. - Definition of what is considered a change that will require a formal change request - Levels of authority of the various types of approval bodies - A description of who is allowed to submit change requests)

What is the definition of a Service Level Agreement (SLA)?

A contract between an organization that provides a service and the user of the service. The contract specifies what the customer will receive and the performance standards or level of service the provider is obligated to meet.

What is the difference between a cost estimate and a budget?

A cost estimate entails accumulating the cost components for an activity or task. A budget is the agreed-upon cost estimate that cost performance will be measured against.

What are the components of a balanced scorecard?

A focus on strategic issues, use of a small number of data items to monitor, and a mix of financial and non-financial indicators

Meetings are a way of life for project teams, and the manager of the new order-entry system project feels like they are constantly in a meeting. Which of the following is not a valid reason to postpone a meeting between the functional manager and the project manager?

A functional manager wants to meet with the project manager at the same time as a project team meeting.

What is the definition of a histogram?

A graphical display of data using bars

What is the basic difference in appearance between a histogram and a control chart?

A histogram is a bar chart, and a control chart is a line chart.

You are moving the corporate servers to a new building in Buffalo, NY in January and February. You have included snow in your risk list. This is an example of:

A known

You are moving the corporate servers to a new building in Buffalo, NY in January and February. You know that the building is not occupiable in those months and have added it in your risk list. This is an example of:

A known-unknown

What is the difference between a letter of intent and a Memorandum of Understanding (MOU)?

A letter of intent outlines the terms of an agreement before the agreement is finalized. A Memorandum of Understanding (MOU) is an agreement between two or more parties to form a business partnership. It is not legally binding, but is used where the parties do not wish to enter into a formal contract.

What is the purpose of a run chart?

A line graph of data plotted as a function of time, that is used to examine a trend in the data

A real estate developer is preparing to begin work on a subdivision that will consist of 20 single-family homes, and four construction managers will be needed. The developer will need a marketing specialist to market the subdivision, a finance expert to arrange for a loan to purchase the land, and a team of attorneys to handle legal issues. What mechanism will be used to manage these people?

A program manager

You are being interviewed for a job as a project manager, and the interviewer has asked you to list some of the key characteristics of a project. Which of the following responses is correct?

A project is temporary.

What is the difference between a proposal and a quote?

A proposal is commonly used when deliverables are not well-defined or when other selection criteria will be used in addition to price. A quote is commonly used when deliverables are commodities for which there are clear specifications and when price will be the primary determining factor.

In Agile project management, what is the purpose of a retrospective and when is it held?

A retrospective is a meeting held at the end of a sprint. It is facilitated by the scrum master to review the sprint that was just concluded and to identify what can be changed to make the next sprint more productive.

A risks/issues log is used by project managers to track significant project elements. What is the difference between a risk and an issue?

A risk is an uncertain event that, if it occurs, can have a positive or negative effect on one or more project objectives. An issue is an item that is under discussion and needs to be addressed by the project team.

The scheduler on the Coho Winery wine-bottle filling station project is briefing the rest of the project team on the components of the project schedule. An engineer is confused about the different ways a schedule can be used. Which of the following describes a milestone schedule?

A schedule typically prepared for senior management

You are gathering requirements for a project to update the corporate website. You have most of them documented, but have some follow-up questions for some of the stakeholders. You create a meeting on their calendars for the next day and attach a brief topic list. This is an example of:

A scheduled meeting

Which statement best describes a program?

A set of projects managed in a coordinated way. (Projects within a program do not have to share any objectives.)

Choose the component that should always be included in the project charter.

A statement of project goals via a project statement of work (SOW) and authorization of the project manager to use organizational resources on the project

The Trey Research Project Management Office (PMO) requires all projects to prepare status reports and progress reports. What is the difference between a status report and a progress report?

A status report contains a summary of activities over a cumulative period of time, such as year-to-date or since the start of a project. A progress report provides information on what was accomplished recently, perhaps in the last month.

A new project manager has been asked to add a hammock task to the project schedule to make it easier to read. Which of the following is the best description of a hammock activity or task?

A summary activity or task, with detailed activities or tasks indented beneath it

The bridge over the Troubled Waters stream project will last over six months, and several types of reports will be prepared. Which of the following best describes a status report?

A summary of activities over a cumulative period of time, such as year-to-date or since the start of a project

An engineer working on the Awesome Computers wireless network upgrade project asks the project manager to clarify some of the scheduling terms, specifically predecessor and successor. What determines whether a task is a predecessor to another task, if the two tasks are linked together?

A task that drives the relationship with the other task is always the predecessor.

What is the definition of a warranty of fitness for purpose?

A type of implied warranty that requires goods to be fit for the usage that was intended by the buyer

You are working on the installation of a new Customer Relationship Management (CRM) system and are developing the project change control plan. Which of the following is NOT a component?

A validated change (A change control plan needs to explain HOW changes will be validated. - Definition of what is considered a change that will require a formal change request - The process for submitting a change request - A description of who is allowed to submit change requests)

What is the difference between a warranty of merchantability and a warranty of fitness for purpose?

A warranty of merchantability is a type of implied warranty that requires goods to be fit for ordinary usage. Any sale of an item is subject to a warranty of merchantability. A warranty of fitness for purpose is a type of implied warranty that requires goods to be fit for the usage that was intended by the buyer.

A project has six activities, all related in a finish-to-start relationship. The table below depicts the durations and predecessors of each activity. (see image) What is the critical path, and how long is it?

ABCFG, 50 weeks (adding durations of each activity on each path and selecting path with longest duration: AEFG is 48 weeks. ABCDG is 36 weeks. ABCDEF is 66 weeks; all activities are not in the same finish-to-start relationship, therefore, not all the durations are added together.)

The scheduler on the WingTip Toys mini-drone project needs to compress the schedule for the project by crashing an activity. What should the project team focus on?

Accelerating the performance of those tasks on the critical path

(2.2 part 1) You are working on a project to upgrade the enterprise resource planning (ERP) system, which includes a purchasing system and a new sales system. There is concern that the new system will not be implemented in time to meet the demand for Halloween candy orders, which is historically your biggest sales season. You and the sponsor decide to address this only if it happens, which is an example of which type of risk response?

Accept

You are working on an external contract project to update the operating system on more than 1000 computers at an organization. The contract provides a bonus for finishing the work within two months, but right now the schedule looks like it will take three months, so you leave it at that. This is an example of which type of response strategy?

Accept

You have taken over a project from another project manager and are concerned that the consultant working on the project may leave before the project is completed. Which risk response strategy should you employ?

Accept the risk, but have a contingency

Which of the following are risk responses? (edusum Qs)

Acceptance & Avoidance

The scope of any project can seem complicated to someone who has not written one before. The Coho Winery summer intern has asked about the inputs to the scope for the wine-bottle filling station project. Which of the following is not used to prepare the scope?

Accepted deliverables

You are working on a project to upgrade the Human Resources Management System (HRMS). There has been some talk that the HR manager, who is your sponsor of the project, might be retiring. You see this as a potential risk to the project, but do not do anything proactively to counter this risk. This is an example of which strategy of risk response?

Accepting

What is the hierarchy, from high to low, of roles in the Responsible, Accountable, Consult, Inform (RACI) matrix?

Accountable, Responsible, Consult, Inform

You are working on a project to select and install a new Customer Relationship Management (CRM) system. Which of the following would NOT be considered stakeholders in this project?

Accounts Payable clerks. (- Regional Managers of Sales and Marketing - Salespeople - Vice President of Sales and Marketing)

Which of the following are the techniques that are used to acquire a team?

Acquisition, negotiation, virtual team, pre-assignment

An engineer on the TailSpin Toys robotic cat laser project is still confused about what to do with project issues. Which of the following does a project team keep in an issue log in addition to a description of the issue?

Action items

The estimated demolition of the old bridge over the Troubled Waters stream was exceeded by 12 days due to extremely bad weather. The project manager documented this in the appropriate place and is brainstorming the next steps to take. The brainstorming session concluded that four things should be done immediately: Use overtime to clear the demolition debris. Request an extension to the construction permit end date. Authorize the steel deck vendor to hire an additional crew. Expedite the change order process for the above three items. What is this additional work referred to?

Action items

An engineer is assisting the project manager plan the project. He or she has been asked to decompose the scope. What will be the result of this decomposition?

Activities

The manager of the AdventureWorks Cycles high-speed braking system project has decomposed the scope to produce the Work Breakdown Structure (WBS). Which of the following statements is not true about a WBS?

Activities should appear in the WBS in the order they will be performed.

Which inputs will you use to determine the project budget?

Activity cost estimates, the scope baseline, the project schedule, and contracts

Crashing a schedule includes

Adding resources to critical path activities

When are project costs estimated?

After the Work Breakdown Structure (WBS) is developed and before the budget is prepared

A number of documents are created at the beginning of a project, and the manager of the wireless network upgrade project wants to avoid embarrassment by not asking which document comes after which other one. When is the project charter written?

After the project statement of work, and before the project management plan

Which document governs the formal relationship between two parties?

Agreement

During a project assessment, a project manager determines the initial project cost estimates were incorrect, and there is not enough budget left, including reserves, to complete the project.Which of the following actions should the project manager take?

Alert the project sponsor of the situation.

(3.2 part 1) You are developing the project plan for a new enterprise resource planning (ERP) implementation for your organization. The project will take nearly a year, and you are trying to determine the frequency of communication with your various stakeholder populations. To which stakeholders should you not provide weekly status information?

All employees

You are developing the project plan for a new enterprise resource planning (ERP) implementation for your organization. The project will take nearly a year, and you are trying to determine the frequency of communication with your various stakeholder populations. To which stakeholders should you provide monthly news reports?

All employees

You are developing the project plan for a new enterprise resource planning (ERP) implementation for your organization. The project will take nearly a year, and you are trying to determine the type of communication to use with your various stakeholder populations. Video conferencing would not be feasible with which stakeholders?

All employees

You are developing the project plan for a new enterprise resource planning (ERP) implementation for your organization. The project will take nearly a year, and you are trying to determine the type of communication to use with your various stakeholder populations. Which stakeholders would not want status meetings?

All employees

Why formal project closure is is important?

All of the above: (Releases team members from the project, Transfers team members to other projects, Releases excess funding)

Who should prepare a lessons-learned document, and when should it be written?

All team members should be expected to contribute to the document. It should be started at the beginning of the project and built throughout the project's duration. It can then be edited and formalized during project closure and made available to other projects.

You are four weeks into a two-month project, and you are seeing a wide variety of defects in the products being produced. You want to figure out what is causing these problems. The best tool to use is:

An Ishikawa diagram

What is the definition of a Memorandum of Understanding (MOU)?

An agreement between two or more parties to form a business partnership. It is not legally binding, but is used where the parties do not wish to enter into a formal contract.

What circumstance can cause the cost baseline to change?

An approved modification to the project

AdventureWorks Cycles has submitted a Request for Proposal (RFP) to four vendors to develop a new high-speed braking system. The project manager is using an independent estimate in the proposal evaluation process. Which of the following statements best describes an independent estimate?

An estimate from the AdventureWorks Cycles purchasing department

An engineer with TailSpin Toys is assisting the project manager plan the robotic cat laser project, and has been asked to prepare the schedule activity list. To confirm that the engineer knows exactly what to do, the project manager asks him or her for a brief description of what will be done. The engineer responds that a schedule activity list is _______.

An extension of the Work Breakdown Structure (WBS)

You are gathering requirements for a project to update the corporate website. You have most of them documented, but have some follow-up questions for some of the stakeholders. You bump into one of them at the coffee machine and ask him to stop by your office for a few minutes. This is an example of:

An impromptu meeting

Very little is known about a new Trey Research, Inc. project to develop a mini-microwave laser targeting device. Which type of estimate would be used when estimating durations of activities when very little is known about the project?

Analogous

To ensure the quality of project deliverables, You should __ before variance is identified

Analyze performance information

Which of the following is not used to create the budget?

Cost baseline

A project team is overseeing the installation of a new reptile habitat at the local zoo. During execution, zoo personnel decides to house a different type of reptile that will require a different temperature range than the capacity of the installed system. The modification has been approved.Which of the following constraints are MOST likely to be affected? (Choose 2)

Cost because replacing the system incurs additional expense. & Schedule because this was an unscheduled task and will impact the timeline.

Bob has been asked to travel to a client office for a meeting and to charge the expenses for the trip to the project. Which category is the correct one to use?

Cost resources because money is involved

Fabrikam has entered into a contract with AdventureWorks Cycles to manufacture components for the new high-speed braking system. Of the three basic types of contracts—fixed-price, cost-reimbursable, and time-and-material—which type or types has the most risk for the buyer, AdventureWorks Cycles?

Cost-reimbursable and time-and-material

The team to build a new home for the town mayor is behind schedule, and the mayor is threatening to fire the team and bring in another contractor to finish the job. To avoid this, the project manager decides to add more resources to activities on the critical path. What is this called?

Crashing

You are nine weeks into a three-month project, and your schedule has increased by three weeks. Your sponsor has asked you to hire more resources for the critical path tasks to get back on schedule. This is known as:

Crashing

The routine weekly project meetings have not been going smoothly. They have been disorganized, and too much discussion has revolved around unplanned items. The project manager needs to regain control and is looking for a suggestion. Which of the following items will help improve the meetings?

Create and publish an agenda a day before each meeting, and follow the agenda rigorously.

A portfolio is centered on one or more strategic business objectives. Which of the following represents a strategic business objective?

Creating multi-lingual project teams. (Multi-lingual project teams will allow a company to market its services to a wider range of clients, thus potentially increasing revenue. This qualifies as a strategic business objective, because a company exists to increase revenue and profitability.)

You are managing the conversion of an in-house payroll system to a cloud-based system and are identifying the potential risks. Which of the following is NOT a technique you might use?

Critical path method (these things are considered documentation review, not a distinct risk technique. - Strengths, weaknesses, opportunities, and threats (SWOT) analysis - Cause and effect diagram - Flow chart)

The term "expert judgement" is used frequently to refer to advice provided by individuals who have expertise that is beneficial to a project. Who provides this expert judgement?

Any stakeholder

What documents should be archived with a project's files?

Anything that might be useful to reconstruct the current project or aid another project

When does the project sponsor first get formally involved with a project?

Approval of charter

The e-banking project is almost finished, and the project manager is beginning to gather documents and files that were prepared during project planning and execution. This information includes client correspondence, contracts with vendors, status reports, and financial records. What will the project manager do with this documentation?

Archive it

The project manager and the project team are closing a successful project. They are collecting project documentation, status reports, correspondence with the client, and contracts with vendors. What are they preparing to create?

Archives

Which of the following network diagram methods uses arrows to represent activities, but is limited because it can only represent Finish-to-Start dependencies?

Arrow Diagramming Method (ADM)

How is the project scope statement used?

As input to project transition to align the transition plan with stakeholder expectations, interests, and training requirements

You have been working for a month on a new web project and have developed a great relationship with the client. Last week, the client requested a change to the requirements, which was approved through change control, and yesterday the client e-mailed and asked for another change as an "addendum" to the earlier change request. What should you do?

Ask the client to submit a new change request.

A team member was re-assigned. The project manager should

Assess how the project would be impacted

The part of the project charter that deals with expected conditions in the project are the high level

Assumptions

You are developing a new payroll system for your organization and you are starting to identify and prioritize risks. You are reviewing the project scope statement to determine the validity of its components to see if any of them pose a risk. What specifically are you doing?

Assumptions analysis

You are working on a new purchasing system project and are getting ready to start executing the project. You are wrapping up the communication plan and are deciding on the communication methods to use. Which of the following is not a communication method to consider?

Asynchronous communication

Meetings are an important component of a project that is using the Agile methodology. When should these meetings be held?

At the beginning of the work day

You are executing the project plan for a new Point of Sale system for your retail stores and you inform the team that it is time for the next scheduled project "checkup." What was the trigger for this?

Audits

You are executing the project plan for a new payroll system and following your communication plan. Which of the following is not a communication trigger for communicating with the sponsor?

Audits

You are working on a project to upgrade the enterprise resource planning (ERP) system, which includes a purchasing system and a new sales system. There is concern that the new system will not be implemented in time to meet the demand for Halloween candy orders, which is historically your biggest sales season. You decide to delay implementation to August, which is past the July rush for Halloween orders. This is an example of which type of risk response?

Avoid

There is a conflict in a project team that has no impact on the project. Which of the best conflict resolution technique?

Avoiding

Conflict resolution will be most challenging in which type of organization?

Balanced matrix

The project manager has noticed a vendor is not performing in accordance with the SLA.Which of the following items should the project manager use to highlight the vendor's areas of poor performance?

Balanced score card

A manager is using a tool to help determine which projects to execute, and to ensure that they match the strategic objectives of an organization. What is the name of this tool?

Balanced scorecard

The Lucerne Publishing Co. textbook project schedule has several activities with leads. Which of the following is an example of an activity with a lead?

Beginning to add the graphics to a report before the text has been completed

You are working on a new purchasing system project and are getting ready to start executing the project. Which of the following is an advantage of holding the kick-off meeting in person?

Both oral and visual feedback can occur instantaneously.

__ happens in the planning phase of a project.

Both: (Assignment and explanation of tasks, Execution of project kick off)

This estimating type needs the most effort when creating WBS?

Bottom-up

Which of the following techniques is used to estimate the total project cost after the Work Breakdown Structure has been completed?

Bottom-up

Cost estimating is done by TailSpin Toys using a software application which uses detailed aspects of each project activity as inputs. The costs of the activities are then combined and used to determine the cost baseline. Which type of cost estimate is used by the tool?

Bottom-up estimating

The manager of a project to develop a new math game for young children plans to create 10 interim and two final deliverables for the project. He or she now needs to decompose the Work Breakdown Structure (WBS) deliverables. Which activity will be performed during decomposition?

Breaking the deliverables down into smaller components

A project has been spending approximately $50,000 each month for the past year. What is this amount called?

Burn rate

What is the name of an agile project management graph that shows work remaining on the vertical axis and time on the horizontal axis?

Burndown chart

You are working on a project to install a new enterprise resource planning (ERP) system, which includes a Customer Resource Management (CRM) component. The system selected needs to increase customer retention by at least 10%. This is considered which type of requirement?

Business

You are working on a project to upgrade the Human Resources Management System (HRMS). The system selected needs to reduce applicant processing time by at least 20%. This is considered which type of requirement?

Business

A stakeholder approaches the project manager with an idea for a new project. What document will be prepared as a result of this meeting?

Business case

Alpine Ski House is launching a project to train staff in using the new reservations system that will be installed before ski season begins. Which document will the project sponsor need to see before signing the charter?

Business case

What Initiation-phase document outlines the technical, investment, and regulatory factors that influence a project, with a particular focus on Return on Investment (ROI) and payback period?

Business case

You are executing the project plan for a new Point of Sale system for your retail stores and there has been a city-wide power outage. You inform the sponsor and team and ask the team not to report to the office but to work at home if they have power. What type of trigger is this?

Business continuity response

Trey Research, Inc. begins approximately 100 projects a year, and the Project Management Office (PMO) reviews every charter before it reaches a sponsor's desk for approval. Which of the following items should the PMO insist be in every charter?

Business need of the project

(4.2 Part 1) The manager of the mini-drone project is gathering the inputs to write the charter. Which of the following items is contained in the charter?

Business needs

You are developing the project plan for a new Human Resources Management System (HRMS) for your organization. Which of the following is a type of change that you might need to plan for?

Business process change

You are working on a project to redesign the website, and decide to use a new web design tool that no one on the team has used before. This risk is no longer relevant, so you close it out. How do you communicate this update to your stakeholders?

By whatever process is designated in the communication plan for the results of risk reviews

Which of the following metrics demonstrates to a project manager if a project is overspending or underspending?

CPI (Cost Performance Index)

You are working on a new purchasing system project and you are having difficulty finalizing the requirements with the purchasing department. You are talking on the phone with the purchasing manager but now you both have questions for a purchasing clerk. What is the best approach to get those answers?

Call on the telephone

If you are given a constraint of $25,000, then on the project you:

Cannot spend more than $25,000

You are managing the conversion of an in-house payroll system to a cloud-based system and are identifying the potential risks. To create appropriate response plans for some of your identified risks, you need to look at their sources. Which is the best technique to use?

Cause and effect diagram

A project manager who worked for TailSpin Toys for 10 years resigned and took a similar job with WingTip Toys. The two companies compete in the same market sector, and because TailSpin was concerned about trade secrets finding their way to the competition, the project manager had to sign a form before leaving. Six months later, TailSpin management learned that confidential information was being shared with WingTip. What document did TailSpin Toys send to the project manager?

Cease and desist letter

TailSpin Toys and WingTip Toys are considering whether to join together to produce an educational math game for three- to six-year-old children. The two CEOs have been corresponding for several months about this, and the TailSpin CEO has begun to leak information to the press in an attempt to pressure the WingTip CEO to sign a formal agreement. The WingTip CEO writes a strong letter telling the TailSpin CEO to stop this practice or legal action will be taken. What is this letter called?

Cease and desist letter

Trey Research, Inc. and TailSpin Toys have been exploring a joint venture, where Trey would design a robotic cat laser toy for TailSpin to manufacture and sell. Shortly after the enabling document was signed, the two companies decided to cancel the venture, and relations have become acrimonious. A Trey executive accused a TailSpin executive of leaking information to the press and wrote a pointed letter to Trey. What is this letter called?

Cease and desist letter

An advantage of a functional organization is

Centralized resources

When stakeholders change their minds about the project requirements, they submit change requests that are evaluated and reviewed by a:

Change Control Board (CCB)

Which planning document records a change request initiated in the integrated change control system?

Change control form

The document used to record descriptions, dates, and resolutions to all applications for modifications to existing requirements or other project constraints is called a:

Change log

Which should a project manager look to if unsure who has the authority to approve changes to the project scope?

Change management plan

In reviewing the project deliverables to date, the clients discover that there is a missing piece of work. To formally ask for this work to be added to the project, they need to submit a:

Change request

The project is in the Initiation phase, and the sponsor has just signed a document that authorizes the project to begin. What is this document called?

Charter

You are working on a project to upgrade the operating system on all your company's personal computers. The sponsor on this project is most likely to be the:

Chief Information Officer (CIO)

You are working on a new purchasing system project and are getting ready to end the project. You want to have a meeting with your key team members and other stakeholders to review how the project went and to document lessons learned. What type of meeting is this?

Closing meeting

You are working on a new purchasing system project and are getting ready to end the project. You want to have a meeting with your key team members and other stakeholders to review how the project went, to document lessons learned, and to celebrate project success, but most of them do not want to travel to your location. Why might you still schedule and hold an onsite meeting?

Closing out the project in person helps build relationships needed for subsequent projects.

Intranet sites and wiki pages are examples of which type of tools?

Collaboration

You are developing a new website for your organization and you are starting to identify and prioritize risks. You are using the Delphi technique with a team of Subject Matter Experts (SMEs). What specifically are you doing?

Coming to a consensus on the probability and impact of identified risks

Which is the only component of the change control process that is executed iteratively as needed?

Communicate throughout

You are working on moving the in-house Human Resources Management System (HRMS) to a cloud self-service provider and you are performing the only change control process that is executed iteratively as needed. Which process are you performing?

Communicate throughout

What is the most important function of a project manager?

Communicating

During the planning phase of the project, the team develops a document that details the ways in which the stakeholders will interact. What is this document called?

Communication plan

The project manager of the new order-entry system is creating the planning documents for the project. During a meeting with some of the stakeholders, he or she is soliciting what kind on information they need, how often they would like to receive it, and in what format it should be to be most helpful. Which type of document will result from this meeting?

Communication plan

The project to replace the bridge over the Troubled Waters stream has team members from the Public Works Department and six vendors, each with their own team. The project manager needs to keep this large group of stakeholders informed about the project. Which plan contains the methods to do this?

Communication plan

A client approaches the project manager demanding a change in the execution phase . What should she do?

Complete the change form and evaluate how a change would impact the project

Two members of the project team are having an argument about whether a user manual for a new widget can be written while the widget is being built and tested, and they have come to the manager for help. One person believes that testing should be complete before any writing is done, and the other says that the manual can be written even while the widget is in construction. After discussing the options, the manager suggests that writing begin when the widget is 75 percent complete. Which type of conflict management is being used?

Compromising

The project manager is beginning to prepare the scope. At this time, which is the most important activity of this process?

Confirm that key stakeholders have provided their input.

Which of the following would be important to remember when scheduling a teleconference for a project team?

Considering time zone that meets business hours for whole team

The part of the project charter that deals with limitations is the high level

Constraints

Which of the following is a benefit of daily meetings of the scrum team?

Continuous feedback

When are the requirements for a project using Agile methodology determined?

Continuously

What tool can be used to decide if a project deliverable is out of specification?

Control chart

You are trying to decide whether or not a process is functioning within its prescribed limits. The type of chart you should use is a(n):

Control chart

There are 10 people in the project team, and 10 more people join during execution to handle a major increase in the scope. What can be said about communications on the project?

Controlling communications will be more difficult.

The project manager has many responsibilities. Which of these is most important?

Controlling unnecessary change

Which of the following responsibilities is the most critical in the role of the project manager?

Controlling unnecessary change

In a large project, what is one of the main duties of a project coordinator?

Coordinate the work of several functional groups

You are developing the communication plan for a new Human Resources Management System (HRMS) for your organization. Which of the following is NOT a trigger you need to plan for?

Corporate reorganization (are changes, not communication triggers. - Audits - Milestones - Project planning)

Two network administrators are having a disagreement about a technical issue that can delay the finish date of the project, and they seek help from the project manager. Which of the following actions should the project manager propose?

Meet with the network administrators and learn what is causing them to disagree.

A construction supervisor emails the project manager that two sub-contractors are having an argument that might adversely affect the schedule of the project. Which of the following actions should the project manager take?

Meet with the two sub-contractors separately to learn the details of the problem

Trey Research, Inc. and TailSpin Toys are exploring a joint venture, where Trey would design a robotic cat laser toy for TailSpin to manufacture and sell. Both companies would share in the eventual profits. Executives of the two companies have written a document that outlines the purpose of the joint venture, the roles and responsibilities of each company, financial considerations of the venture, and confidentiality considerations. What is this document called?

Memorandum of Understanding (MOU)

A new engineer is reviewing the schedule for a project to upgrade the wireless network of an office building. He or she sees activities with a value of zero days for some activities and asks why something should take no time to do. What is an activity with zero duration called?

Milestone

You are executing the project plan for a new Point of Sale system for your retail stores and you inform the sponsor and client that the system has been installed. What was the trigger for this?

Milestone

The project manager has been asked to brief senior management on the status of the shopping mall project, but has been allocated only 15 minutes to do this. Which of the following schedule tools would be appropriate for sharing status?

Milestone chart

You are working on the project plan for a new payroll system and you are finalizing the communication plan. Which of the following is NOT a communication trigger for communicating with the team?

Milestones (are triggers for communicating with the sponsor and client about meeting or not meeting the required milestones. - Task initiation/completion - Stakeholder changes - Gate reviews)

While developing a project schedule, which of the following are purposes of a milestone? (Choose 2)

Milestones are considered a placeholder in time for a major event & Milestones have no duration

You are working on a project to upgrade the enterprise resource planning (ERP) system, which includes a purchasing system and a new sales system. There is concern that the new system will not be implemented in time to meet the demand for Halloween candy orders, which is historically your biggest sales season. The sponsor and you decide that you'll implement the new system in parallel so that the old system is still active if need be. This is what type of response strategy?

Mitigate

During which phase of a project does performance measuring and reporting occur?

Monitoring and Controlling

In which phase of a project are requested changes by a buyer or seller addressed?

Monitoring and Controlling

You are developing a new purchasing system for a client and need to provide the probability of meeting a range of completion dates. Which risk technique should you use?

Monte Carlo Simulation

You are three months into a six-month project and the schedule has slipped nearly three weeks. The sponsor informs you that you must be on time, so you need to shave those three weeks of work back off. You have six major deliverables and three minor deliverables. You have started four of the major deliverables and expect to have all four complete on time. The other two major deliverables have not started, but are expected to take two months. The minor deliverables have also not started, and are expected to take four months. What should you do?

Negotiate with the sponsor to move the minor deliverables to a next release

A contract to procure goods or services involves a buyer and a vendor. Most types of contracts can be started by either party and submitted to the other. Does this apply to a purchase order?

No, a purchase order is prepared by a buyer and sent to a vendor.

A project manager rolls up the cost estimates of each activity to generate one cost for the project. Is the resulting number the budget?

No, because it does not include risk reserves and it has not been approved by the sponsor.

Does the project manager approve the initial baseline?

No, it is approved by the sponsor.

The project manager is responsible for "all" work relating to the project. Does this responsibility include approving the high-level requirements?

No, they are approved by the sponsor. see more

A project manager who has worked for TailSpin Toys for 10 years has just resigned and will take a similar job with WingTip Toys. The two companies compete in the same market sector, and TailSpin is concerned about trade secrets finding their way to the competition. To help prevent this, the project manager had to sign a form before leaving. What is this form called?

Non-disclosure agreement

TailSpin Toys and WingTip Toys are considering whether to join together to produce an educational math game for three- to six-year-old children. Each company possesses patents and other intellectual property they will be sharing during their discussions. The legal departments have signed an agreement that will keep each company from divulging information about the other company to third parties. What is this document called?

Non-disclosure agreement

Which of the following tools is a project manager most likely to use to stay current about what is happening on the project?

Observation and conversation

During a very weak economy, a company is evaluating several proposed projects to pursue. Which project is the least likely to be approved?

One to implement a new technology. (Until more is known about the benefits associated with this technology, and a benefit/cost determination is made, there is no reason to pursue it.)

Which stakeholder "owns" the deliverables at the end of a project?

Operations management

TailSpin Toys is investigating the feasibility of developing an educational math game for three-to-six-year-old children. The marketing department has explored the market to learn if there is any likely competition and has concluded that parents and young kids would welcome their game. This characteristic of the game project can be considered a:

Opportunity (external (to the organization) origin and is helpful to the objectives of the project. The lack of competition presents an opening for TailSpin to have some success.)

WingTip Toys is considering whether to create a new kind of mini-drone for hobbyists. It will have an extended battery life and will be very light weight, features not available in competitors' drones. The engineers say it can be ready for market in three months because it will leverage patented features in other WingTip drones. The project manager is performing a Strengths, Weaknesses, Opportunities, and Threats (SWOT) analysis as part of the feasibility study. These characteristics of the mini-drone project can be considered a:

Opportunity (external (to the organization) origin, and is helpful to the objectives of the project. There is no competition for the long-battery-life, light-weight drone that WingTip is designing, so an opportunity exists.

Lucerne Publishing Co. is beginning a project to publish a new textbook, and the project manager has started to plan the team. He or she decides to structure the team around work packages. Each work package will have one owner, and within each work package will be technical writers, graphics designers, and editors. What document is the project manager preparing?

Organization chart

You are working on a project to install a new Customer Resource Management (CRM) component. Your company is also implementing a new purchasing system, which will need many of the same employees as your project. What category of risk is this risk?

Organizational

You are working on a project to install a new enterprise resource planning (ERP) system, which includes a Customer Resource Management (CRM) component. The project is scheduled to take four months. The training department employee assigned to the project will be leaving on maternity leave in two months. What category of risk is this risk?

Organizational

You are developing the communication plan for a new Human Resources Management System (HRMS) for your organization. Which of the following is not a trigger you need to plan for?

Organizational merger/acquisition

You are developing the project plan for a new Human Resources Management System (HRMS) for your organization. Which of the following is a type of change that you might need to plan for?

Organizational merger/acquisition

You are developing the communication plan for a new Human Resources Management System (HRMS) for your organization. Which of the following is NOT a trigger you need to plan for?

Organizational restructuring (is a potential change that might lead to stakeholder or other changes, but is not one of the communication triggers. - Incident response - Resource changes - Project changes)

A company has updated the method it uses to initiate projects. The company requires RFPs from three vendors, and low and high bids must be rejected to determine the selected vendor.Which of the following terms describe this requirement?

Outsourcing

You are developing the communication plan for a new Human Resources Management System (HRMS) for your organization. Which of the following is not a trigger you need to plan for?

Outsourcing

You are developing the project plan for a new Human Resources Management System (HRMS) for your organization. Which of the following is a type of change that you might need to plan for?

Outsourcing

(2.1 part 2) You are four weeks into a three-month project, and you need to compress the project schedule. You decide to fast-track the project to meet the new deadline. This approach means you are:

Overlapping some tasks that would have normally been done sequentially

Which of the following tools is used for determining activity schedules based on optimistic, most likely and pessimistic estimates?

PERT (Program Evaluation Review Technique)

The project manager for the WingTip Toys mini-drone project has been asked why he or she would use a lag in a project plan. Leads and lags can affect the start and finish dates of tasks. Which of the following is an example of a lag?

Paint on a wall drying before pictures can be hung

A network printer has been malfunctioning intermittently for the last month. Which of the following tools would be used to identify and prioritize the causes of the problems?

Pareto chart

A quality control engineer has collected the following data about a malfunctioning printer: (see image) The engineer needs to see the data graphically and to determine the percentage of the malfunctions due to no ink and a printer jam. Which type of chart will be used?

Pareto chart

A project team can take action to rectify issues causing the most of the defects in

Pareto diagram

You have a network diagram with two paths. You have four days of total float on path A in your network diagram and path B is critical. One of the tasks on path A runs two days late and another one runs three days late, but the path B tasks are progressing as scheduled. Which of the following is NOT true about the schedule?

Path B remains the critical path (Path B is no longer the critical path. Path A had four days of float but now has been extended by five days, making it the critical path. - It has lengthened by one day - Path A is now the critical path - Path B now has one day of float)

HR has concerns regarding the work ethic of a team member. The project manager should give them

Performance reports

In which of the stages of team development would the team be most successful?

Performing

Fast tracking a schedule includes

Performing critical path activities at the same time

You are working on the project plan for a new website design project and you are finalizing the communication plan. Which of the following is not considered a communication trigger?

Personal preferences

A TailSpin Toys engineer who is working on the robotic cat laser project has asked the project scheduler about what will be included in the schedule. How should the scheduler respond?

Planned start and finish dates and durations for each activity, links between activities, assigned resources, and milestone dates

(certiology practice Exam 1 PK0-003) During which process groups is the availability of resources for the project determined?

Planning

A new engineer has been assigned to the Awesome Computers wireless network upgrade project and is being briefed on the phases the project will go through before it is complete. During which phase of the project is the scope prepared?

Planning

In which phase of a project would you use iteration?

Planning

Risk management occurs throughout a project. During which phase are the detailed risks assessed?

Planning

Which phase of a project involves developing a strategy, refining objectives, and identifying deliverables?

Planning

Where is a balanced scorecard used?

Portfolio

Alpine Ski House owns & operates 3 ski lodges in Rocky Mtns. company wants to expand, & board authorized construction of 5 new facilities. directors have a strategic objective of being preferred go-to resorts for seniors/retirees within 10 years. Projects related to goal that're under consideration include obtaining venture-capital financing, new marketing campaigns, acquiring new land, completing facility construction, & establishing franchises; may be completed separately for each of the 5 new ski resorts. What type of project organizational structure will be involved at the corporate level?

Portfolio (The expansion projects will be managed as a portfolio. All the projects will be tied to the strategic objective of being the preferred go-to resorts. Within the portfolio will be programs, projects within each program, and eventually operations to manage each new lodge.)

PMO within large company has seen decrease in overall success of company's projects. Coordination among related projects is informal & staffing conflicts, disagreements between sponsors about outcomes, & conflicting priorities. PMO wants to group projects by business unit & product lines to increase alignment between priorities. Toward which type of project organizational structure are they working?

Portfolio management (portfolio is a collection of projects that relate to a strategic business objective, and grouping projects by product lines to increase alignment is strategic in nature.)

In which process groups is the project charter established?

Pre-project setup

(certiology practice Exam 3 PK0-003) A project manager finished the WBS. What would be utilized during activity sequencing?

Precedence diagramming method

You are working on a new purchasing system project and are getting ready to start executing the project. The Executive Sponsor prefers summary level information presented visually, while the rest of the key stakeholders need details. Which of the following is the most appropriate way of sharing the project schedule with the stakeholders?

Prepare a Gantt chart showing milestones and a Gantt chart of the entire schedule. Send both documents to all the stakeholders.

Lucerne Publishing Co. is almost ready to publish its new textbook. The special paper should have been received last week, but the supplier has said that equipment problems with the crating machinery have delayed the shipment. There are two more weeks of slack in the schedule, after which the deadline given by Lucerne's client will be missed. Lucerne's project manager has document this situation appropriately. What should be done next?

Prepare action items for the issue

The manager of the TailSpin Toys robotic cat laser project has just learned that a subject matter expert has resigned. This person is the country's leading expert on artificial intelligence programming of robotic lasers. The schedule is in jeopardy. The project manager has documented the situation appropriately, so what is the next step that should be taken?

Prepare action items for the issue

The manager of the Awesome Computers wireless network upgrade project has finished writing the scope. What project planning task happens immediately after this?

Prepare the Work Breakdown Structure (WBS)

Ten steps are necessary to fill a bottle of water in an automated process. These steps start with placing an empty bottle onto a moving conveyer, and end with the filled bottle being placed into a carton after it has been checked by a photocell and confirmed to be full. Bottles are being consistently underfilled by 10 percent. What tool would the quality engineer use to look for the cause of this problem?

Process flow diagram

Which tool is appropriate for analyzing and communicating the relationships between process steps?

Process flow diagram

The Public Works Dept. is looking for a vendor to demolish the old bridge over the Troubled Waters stream so it can be replaced with a new one. The purchasing manager of the department prepares a document that will be sent to prospective vendors. The document contains, among other items, the following: Drawings of the old bridge Engineering specifications of the old bridge Schedule for demolition work Terms of payment to the selected vendor Safety regulations that must be followed What is the name of this document?

Procurement Statement of Work (SOW)

Which document provides a description of the work authorized to be performed by a supplier?

Procurement Statement of Work (SOW)

In which order are backlogs generated in an Agile project?

Product backlog then sprint backlog

Projects produce two types of deliverables. What are they?

Product deliverables and project deliverables

Agile projects must readily adapt to changes. Who is responsible for change management in Agile projects?

Product owner

Who participates in a sprint planning meeting?

Product owner, scrum master, and scrum team

What is the name of a group of projects that are managed in a coordinated manner?

Program

When you created your original project budget, you used range estimates. Now that you have started executing the project, you create a budget with much more detailed numbers. This concept of adding detail to your budget is known as:

Progressive elaboration

A company in a highly regulated industry is having resource conflicts on several projects to use a group of subject matter experts. Who in the company is responsible for ensuring that these critical resources are used in the most efficient manner by all of the projects?

Project Management Office (PMO)

TailSpin Toys is a company that designs and manufactures a wide variety of toys. Each toy project consists of identical phases: design, manufacture working prototype, scale up to 100 units, test 100 units, full-scale manufacture, and perform quality control on manufactured toys. Who is responsible for governing when a project can move from one phase to the next?

Project Management Office (PMO)

TailSpin Toys is a company that designs and manufactures a wide variety of toys. Many of the company's projects produce similar deliverables during their project life cycles. Who is responsible for maintaining a consistent set of deliverables for TailSpin's projects?

Project Management Office (PMO)

What organization audits projects and provides guidance to help projects improve their performance?

Project Management Office (PMO)

Which administrative unit or department in an organization distributes project management tools to projects under its control?

Project Management Office (PMO)

Which type of organization audits projects and determines the consequences for projects that do not meet auditing criteria?

Project Management Office (PMO)

Who provides standard documentation and templates for projects?

Project Management Office (PMO)

Who sets the standards and practices for managing projects within an organization?

Project Management Office (PMO)

What is a sign of project closure?

Project cancellation

You are executing the project plan for a new Point of Sale system for your retail stores and management has announced that a new store will be open by the time of implementation. You inform the rest of the team that you will need to add one more store to the scope, which will add another week to the schedule. What was the trigger for this?

Project change

An engineer has just joined Trey Research and is anxious to jump into any new project that becomes available. He or she asks when one will start. What authorizes a project to begin?

Project charter

It is time to begin preparing the scope for the order-entry system project. Which document provides the project manager with background information?

Project charter

The Coho Winery board of directors has just decided to spend one million dollars on a new automated wine-bottle filling station. This action will result in the creation of which document?

Project charter

In the absence of the project manager in a large project, which of the following stakeholders can make decisions about the quality of a deliverable?

Project coordinator

In the absence of the project manager in a large project, which of the following stakeholders would make time- and resource-scheduling decisions?

Project coordinator

Perfect Plating Products is a small manufacturing company with 20 employees who all have many responsibilities. There are no formal "project managers." The company has just begun a new project to manufacture 50,000 platinum-plated screws with exceptionally tight tolerances for a defense contractor. Who has the responsibility of managing the project?

Project coordinator

Who on a project has limited authority and ensures that tasks are completed on schedule?

Project coordinator

The Lucerne Publishing Co. project manager is reviewing the project dashboard. Which of the following are examples of dashboard items?

Project cost variance, schedule variance of a milestone, remaining budget

You are working on a project to install a new enterprise resource planning (ERP) system, which includes a Customer Resource Management (CRM) component. This is the first time you have ever managed a project this size and you are concerned that your effort estimates may be too low. What category of risk is this risk?

Project management

The Public Works Dept. director has asked to see what the team has been working on for the past two weeks, after the charter for the new bridge over the Troubled Waters stream was approved. What is the name of the comprehensive document that is used during project Execution, Monitoring And Controlling, and Closing?

Project management plan

The new project manager of the WingTip Toys mini-drone project is meeting with the planning team after the charter was approved. One of the team members has asked what they will be doing before actually getting started designing the mini-drone. Which deliverable is the main output of the Planning phase of a project?

Project management plan

In the Monitoring and Controlling phase of a project, where does information come from?

Project management plan and work performance information

A project manager has been asked to begin planning a project for which he or she has very little experience. What would be the best source of help for this person?

Project management plans from previous projects

A project produces many artifacts, including project management documents and the deliverables of the project's product or result. Who is responsible for the overall quality of these artifacts?

Project manager

During the course of a project, resources might be needed on an "ad hoc" or occasional basis. To whom do these resources report in a projectized organization?

Project manager

In a projectized organization, to whom do the project resources report?

Project manager

Stakeholders have a wide variety of interests. Who has the responsibility for managing these various interests?

Project manager

Who is responsible for ensuring that changes are processed through the integrated change control process?

Project manager

Who is responsible for managing the quality assurance aspects of a project?

Project manager

The sponsor of the robotic cat laser project has asked to see a project dashboard every two weeks. Which of the following are examples of dashboard information?

Project percent complete, number of milestones completed

You are creating the quality management plan for a new Point of Sale system for your retail stores and you ask the sponsor and client to review it. What was the trigger for this?

Project planning

You are working on the project plan for a new payroll system and you are finalizing the communication plan. Which of the following is not a communication trigger for communicating with the team?

Project planning

You have been asked to increase the scope of a current project, with no increase in time. _ Will be impacted the most.

Project quality and cost

Which of the following project team members has the least authority?

Project scheduler

Microsoft Project, Oracle Primavera, and Basecamp are examples of what?

Project scheduling software

Final project acceptance requirements are found in the

Project scope document

A milestone task on the critical path has been completed.Which of the following should the project manager notify?

Project sponsor

An organization has multiple projects that are taking place simultaneously.Which of the following should be tasked with ensuring resources are appropriately allocated to projects?

Project sponsor

Who approves the budget for a project?

Project sponsor

Who approves the business case for a project?

Project sponsor

Who contributes their expertise to complete project tasks?

Project team members

Who is responsible for completing the technical deliverables of a project?

Project team members

Who should estimate the durations of project tasks?

Project team members

Who is the best person(s) to estimate the technical work of a project, including tasks, durations, dependencies, and effort?

Project team members who will be performing the tasks

Transition plans involve

Project warranty

In which type of organization does the project manager have the highest degree of authority?

Projectized

You are working in an organization where you and your team were all hired for the duration of the project. You report to the head of the corporate Project Management Office (PMO) and your team members report to you, but none of you are guaranteed a job after the project ends. This means that you work in what type of organizational structure?

Projectized

Now that the charter has been approved, it is time to write the scope document. What is the purpose of scope?

Provides an understanding of the project's major objectives by identifying what is within the scope and what is currently out of scope

The manager of the Awesome Computers wireless network upgrade project has been holding weekly team meetings. Agendas are distributed at the beginning of each meeting. The meetings usually begin late because some people are not interested in some of the early topics, and they end late because these same people want "quick summaries" of what they missed—and the summaries are not quick. What can the project manager do to rectify this problem?

Publish the agenda in advance with times allotted for each topic; start and end the meetings on time; have the most important topic first on the agenda; do not revisit any topic.

You are working on a new purchasing system project and are two months into the three-month project. You write a newsletter for the stakeholders, post it online, then send an email to suggest that they read it when they get a chance. This is an example of which communication method?

Pull communication

A consultant has signed a contract with a client to provide various services for one year. The client sends the consultant a request that specifies exactly what services are needed in the next month, and the amount they will pay for these services. What type of document did they send?

Purchase order

AdventureWorks Cycles has contracted with Fabrikam to provide the components for its new high-speed braking system. The contract contains the technical specifications and the cost of the components, as well as the standard contractual terms concerning delivery, payment terms, and warranty information. When AdventureWorks needs parts, it will email Fabrikam with the quantity, and the email will form a part of the contract. Which type of contract is this?

Purchase order

The Coho Winery automated bottle-filling station project is almost complete, and the quality engineer is ready to begin testing the final deliverable. He or she needs corks and has located a supplier who can meet Coho's specifications. The engineer sends a request for 1,000 corks, which will be enough for the quality tests, to be delivered in four weeks at a previously agreed price. What is the name of the document that Coho has sent?

Purchase order

A sponsor has authorized the project manager for an new project. He put it in writing. What would be key element in this document?

Purpose of the project

You are working on a new purchasing system project and have just started executing the project. You are sending out your first status email to all the stakeholders. This is an example of which communication method?

Push communication

A project manager conducted a risk probability assessment this happened during

Qualitative risk analysis

You are six weeks into a four-month project and you are discovering defects on your project's product. This means you should review and revise which of the following plans?

Quality Assurance Plan

You are three weeks into a four-month project and you are reviewing your processes and procedures to be sure they are delivering the intended outputs. The name for what you are doing is:

Quality audit

You are working on a project to upgrade the enterprise resource planning (ERP) system, which includes a purchasing system and a new sales system. The project will take nearly a year, and three months in, management decides that implementation can proceed with up to 10% of the code malfunctioning. This is an example of what type of change?

Quality change

You are working on a six-month project to redesign the corporate website and add product purchasing functionality. You have noticed that several of the test cases are not finding the errors you know are in the data, so you update the assurance processes. This is an example of what type of change?

Quality change

You are working on a six-month project to upgrade the operating systems on more than 4,000 corporate computers. The Chief Information Officer (CIO) has decided that the systems must power up in under one minute instead of under two minutes. This is an example of what type of change?

Quality change

You are working on moving the in-house Human Resources Management System (HRMS) to a cloud self-service provider. The Vice-President of Human Resources has decided that the response time for the system in the Service Level Agreement (SLA) must decrease to five seconds. This is an example of what type of change?

Quality change

During monitoring /controlling, an error is found in the project deliverable. During what process did this occur?

Quality control

You are required to determine how much it will cost for a 3rd party to complete certain deliverables and the steps they will take to complete them. To gather this information you should issue a

RFP (request for proposal)

You are working on a six-month project to upgrade the operating systems on more than 4,000 corporate computers in three different countries. Which of the following would NOT be a communication concern for conducting weekly status meetings with each location via video conferencing?

Rapport building/relationship building (Rapport building/relationship building is not really a concern in status meetings. - Frequency - Criticality - Technology)

You are working on moving the in-house Human Resources Management System (HRMS) to a cloud self-service provider. One of your team members submitted a change request that will increase the project budget by 15%. You are creating a back-out plan in case the change is approved and implemented but doesn't work as intended. What process are you performing?

Regression planning

You are developing the project plan for a new Human Resources Management System (HRMS) for your organization. Which of the following is a type of change that you might need to plan for?

Relocation

A city Public Works Department is looking for a company to design and build a new bridge over the Troubled Waters stream. The department's purchasing manager sends letters to engineering firms asking if the firms are interested in working on the project. Which type of document has the purchasing manager written?

Request for Information (RFI)

AdventureWorks Cycles needs a special type of gear for its high-speed braking system project and will be contracting with a vendor in approximately three months. The company has not dealt with the 10 suppliers of this gear before and has written a letter to each one requesting the following information: Numbers of years in business ISO certifications References from last three clients What is the name of the document AdventureWorks has written?

Request for Information (RFI)

Fabrikam is being considered by AdventureWorks Cycles to manufacture components for a new high-speed braking system. Fabrikam has received a written request for the following information: Number of years in business Copies of ISO certifications Resumes of project manager and manufacturing supervisor List of three clients who are available for reference checks Company organization chart What is the name of this document?

Request for Information (RFI)

Which procurement document is generally used to develop lists of qualified vendors or sellers?

Request for Information (RFI)

What does RTP represent

Request for Proposal

Fabrikam is being considered by AdventureWorks Cycles to manufacture components for a new high-speed braking system. Fabrikam has received a written request for the following information: Schedule for delivery of components Estimated budget Resumes of project manager and manufacturing supervisor Scope Project organization chart What is the name of this document?

Request for Proposal (RFP)

The delivery of project software and hardware required, timely installation and maintenance, training and support, and costs will be the determining factors in your choice of suppliers. What type of procurement document is this?

Request for Proposal (RFP)

When purchasing components for a networking project, a company wants to make sure that the components meet engineering specifications and can be purchased for a reasonable price. Which type of document will they use?

Request for Proposal (RFP)

(4.3 part 1) An office manager needs to purchase 10,000 paperclips, which are to be manufactured according to a standard specification. The seller who submits the lowest price will be awarded the work. What type of purchasing document will the manager send to prospective sellers?

Request for Quote (RFQ)

The Coho Winery automated bottle-filling station project is almost complete, and the quality engineer is ready to begin testing the final deliverable. He or she needs corks and is looking for a supplier who can meet Coho's specifications. The engineer sends a request to three companies for prices of 1,000 corks, which will be enough for the quality tests, to be delivered in four weeks. What is the name of the document that Coho has sent?

Request for Quote (RFQ)

Which procurement document is commonly used when deliverables are commodities for which there are clear specifications and when price will be the primary determining factor?

Request for Quote (RFQ)

During project planning, stakeholders provide you with information on what the project's product or service must be able to do. This type of information is referred to as:

Requirements

During project planning, the team determines the specific expectations of the stakeholders with enough precision that they can be validated to confirm whether they have been met. These expectations can also be called what?

Requirements

You are working on a new corporate website and the marketing department has asked you to incorporate the new logo into the pages. This is a change in:

Requirements

(3.4 Part 2) You are working on a six-month project to upgrade the operating systems on more than 4,000 corporate computers. Just prior to executing, the Chief Information Officer (CIO) decides to go with an even newer version of the operating system. This is an example of what type of change?

Requirements change

You are working on a project to upgrade the enterprise resource planning (ERP) system, which includes a purchasing system and a new sales system. The project will take nearly a year, and after two months of executing, the Vice-President of Marketing decides to change the layout of several of the screens. This is an example of what type of change?

Requirements change

You are working on a six-month project to redesign the corporate website and add product purchasing functionality. Initially the purchases were to be limited to 10 or fewer products, but the sales manager has decided there should be no item limit. This is an example of what type of change?

Requirements change

You are working on moving the in-house Human Resources Management System (HRMS) to a cloud self-service provider. The sponsor has mentioned that you might be buying another company, which would mean the system would need to handle 1000 more employees than originally planned. This is an example of what type of change?

Requirements change

The project manager is facilitating a meeting of a group of stakeholders to obtain information about the needs the project must meet. What document should be prepared as a result of the meeting?

Requirements document

A new department manager at Fabrikam has been assigned as the sponsor for the project to build the components for the AdventureWorks high-speed braking system. This is the first time he or she will be sponsoring a project, and the project manager has asked for approval of the scope baseline. Which of the following documents is not included in the scope baseline?

Requirements documentation

During project planning, which of the following is created first?

Requirements documentation

You are working on creating a chart that displays which resource is working on which task. What are you developing?

Resource Allocation Matrix (RAM)

What is the name of the document that lists project resources and is used to facilitate planning and controlling of project work?

Resource breakdown structure

You are working on a project to upgrade the enterprise resource planning (ERP) system, which includes a purchasing system and a new sales system. The project will take nearly a year, and two months prior to implementation, management approves the hiring of consultants to help complete the project. This is an example of what type of change?

Resource change

You are working on a six-month project to redesign the corporate website and add product purchasing functionality. You are three months in and one of your team members is hospitalized with appendicitis. This is an example of what type of change?

Resource change

You are working on a six-month project to upgrade the operating systems on more than 4,000 corporate computers. One of your team members is selected to go on a country-wide training session tour for another project. This is an example of what type of change?

Resource change

You are working on moving the in-house Human Resources Management System (HRMS) to a cloud self-service provider. One of your key team members leaves the organization and you hire a new consultant. This is an example of what type of change?

Resource change

(3.3) You are executing the project plan for a new payroll system and there have been many changes to date. Which of the following changes is a communication trigger for communicating with functional managers and the team?

Resource changes

You are executing the project plan for a new Point of Sale system for your retail stores and the testing team has just finished developing the test plans. A new tester has been assigned to help with the actual tests. You inform the team and their functional managers that the new tester will be available when needed, decreasing the effort of the rest of the testers. What was the trigger for this?

Resource changes

The team of the WingTip Toys mini-drone project is developing the Work Breakdown Structure (WBS). Which of the following is not a true statement about a (WBS)?

Resource estimates cannot be made until cost estimates have been completed.

A project manager has assigned resources to all of the tasks and has noticed that several of the resources will be working more than the standard eight-hour day. This overallocation will be a problem because overtime pay has not been authorized. Which of the following tools can be used to solve the overallocation issue, so the resources are not working more than eight hours a day?

Resource leveling

The WingTip Toys project manager of the mini-drone project is reviewing the workload of the team and sees that resources are not being used consistently. Some people are scheduled to work two hours on some days, most are scheduled for eight hours a day, and a few are scheduled to work 16 hours a day. Which of the following techniques could help solve this problem?

Resource leveling

Which of the following statements represents an advantage of a projectized organization?

Resources focus exclusively on projects

A RACI matrix is a common type of responsibility assignment matrix. What do the initials R, A, C, and I stand for?

Responsible, Accountable, Consult, and Inform

Someone in senior management requests a minor change to the project, and it appears that the quality of the deliverables will not be affected. What should the project manager do with this request?

Review the change with respect to the entire project (scope, schedule, and cost), not just quality.

What can a process diagram be used for?

Reviewing the steps in a process, analyzing a process to determine sources of risk, assessing the root cause of a problem in a process, and designing a process

You are working on an external contract project to update the operating system on more than 1000 computers at an organization. The contract provides a penalty for taking more than three months to finish the work. Which of the following is an example of mitigating the risk?

Right now, the schedule looks like it will take three months, so you do market research to see who might be available to hire if the schedule starts to slip.

You are working on an external contract project to update the operating system on more than 1000 computers at an organization. The contract provides a penalty for taking more than three months to finish the work. Which of the following is an example of avoiding the risk?

Right now, the schedule looks like it will take three months, so you hire three new resources.

You are working on an external contract project to update the operating system on more than 1000 computers at an organization. The contract provides a penalty for taking more than three months to finish the work. Which of the following is an example of accepting the risk?

Right now, the schedule looks like it will take three months, so you leave it at that.

The most useful tool for communicating to the stakeholders about the approach you will use for reviewing and re-assessing risks throughout the project is the:

Risk Management Plan

You have taken over a project from another project manager and are deciding how to handle project risk. The document you need to consult is the:

Risk Management Plan

__ Will decrease the effect of a project threat

Risk Mitigation

You are developing a new purchasing system for a client and you are starting to identify and prioritize risks. You have performed qualitative analysis and are now using a part of your Risk Management Plan to decide the priority of responses to each risk event. The piece you are using is known as a(n):

Risk Probability and Impact Matrix

(2.2 part 2) The most useful tool for communicating to the stakeholders about the specific risks you've identified on your project is the:

Risk Register

You are developing a new purchasing system for a client and you are starting to identify and prioritize risks. You have performed qualitative analysis and have recorded the results in what document?

Risk Register

You are developing a new purchasing system for a client and you are starting to identify and prioritize risks. You have performed quantitative analysis and have recorded the results in what document?

Risk Register

You are two months into a four-month project and you are deciding whether or not each risk is still a risk. You record the updates to the project risks in what document?

Risk Register

In what context is a Strengths, Weaknesses, Opportunities, and Threats (SWOT) analysis used?

Risk analysis

You are working on a project to upgrade the enterprise resource planning (ERP) system, which includes a purchasing system and a new sales system. The project will take nearly a year, and three months in, the vendor informs you that their planned upgrade to one of the critical modules is behind schedule. This is an example of what type of change?

Risk event

You are working on a six-month project to redesign the corporate website and add product purchasing functionality. You are testing the site and more defects are discovered than were anticipated in the plans. This is an example of what type of change?

Risk event

You are working on a six-month project to upgrade the operating systems on more than 4,000 corporate computers. Two months in, an electrical surge at one of the plants damages 12 computers that now need replacing. This is an example of what type of change?

Risk event

You are working on moving the in-house Human Resources Management System (HRMS) to a cloud self-service provider. A hurricane hit the service-provider's location last week and it will be another week until they are back online. This is an example of what type of change?

Risk event

You have taken over a project from another project manager and are getting ready to update the risk register to account for changes in risks since the last update. Which risk process are you performing?

Risk reassessment

When a risk event occurs, which of the following documents is BEST suited for recording and tracking new items corresponding to the risk?

Risk register

You are executing the project plan for a new Point of Sale system for your retail stores and you hear through the grapevine that the vendor you have selected may be shutting down. You note this and inform the team and the sponsor of potential changes to the plan and budget if this happens. What was the trigger for this?

Risk register updates

You are developing a new purchasing system for a client and you are starting to identify and prioritize risks. You have performed qualitative analysis. Which of the following is NOT a product of this process?

Risk responses for each risk (- Probability and impact of each risk - Risk score for each risk - Priority ranking for each risk)

You are managing the conversion of an in-house payroll system to a cloud-based system and are identifying the potential risks. To create appropriate response plans for some of your identified risks, you need to understand the stakeholders' opinions on seeking or foregoing opportunities. This is referred to as their:

Risk tolerance

Which risk response strategies involves the use of insurance, performance, bonds, or warranties?

Risk transfer

You are managing the conversion of an in-house payroll system to a cloud-based system and are identifying the potential risks. There is a potential opportunity to implement the system a month earlier, but that decreases the chance of successful implementation by 35%. The sponsor says not to pursue it, which implies what level of risk tolerance?

Risk-averter

You are working on a project to upgrade the enterprise resource planning (ERP) system, which includes a purchasing system and a new sales system. There is concern that the new system will not be implemented in time to meet the July demand for Halloween candy orders, which is historically your biggest sales season. If implemented in June, you might increase your orders, but your sponsor moves the implementation date to August. This shows that he is a:

Risk-averter

You are managing the conversion of an in-house payroll system to a cloud-based system and are identifying the potential risks. There is a potential opportunity to implement the system a month earlier, but that decreases the chance of successful implementation by 35%. The sponsor asks what the benefits would be of moving earlier, which implies what level of risk tolerance?

Risk-neutral

You are working on a project to upgrade the enterprise resource planning (ERP) system, which includes a purchasing system and a new sales system. There is concern that the new system will not be implemented in time to meet the July demand for Halloween candy orders, which is historically your biggest sales season. If implemented in June, you might increase your orders. Your sponsor asks for a comparison of losses to increased sales. This shows that the sponsor is a:

Risk-neutral

You are managing the conversion of an in-house payroll system to a cloud-based system and are identifying the potential risks. There is a potential opportunity to implement the system a month earlier, but that decreases the chance of successful implementation by 35%. The sponsor says go for it, which implies what level of risk tolerance?

Risk-seeker

You are working on a project to upgrade the enterprise resource planning (ERP) system, which includes a purchasing system and a new sales system. There is concern that the new system will not be implemented in time to meet the July demand for Halloween candy orders, which is historically your biggest sales season. If implemented in June, you might increase your orders, so your sponsor sets the implementation date to June. This shows that the sponsor is a:

Risk-seeker

You are redesigning the corporate website and have evaluated the risks using a scale of 1 (low) - 10 (high) for both probability and impact, as shown below: (see image) If your risk management plan says you must have risk responses for the top 25% of your risks, which ones must you have plans for?

Risks 5 and 8 (The risk score for risk 5 is 63 and for risk 8 is 56, making them the top two (25% of 8) risks requiring responses.)

You are developing a new payroll system for your organization and you are starting to identify and prioritize risks. You are examining a collection of potential problems and deciding why they might happen. What specifically are you doing?

Root cause analysis

(4.1 Part 1) The Volcano Coffee Company is testing a new coffee bean roaster. The Quality Control manager wants to see a line graph of the number of batches of beans roasted each day. Which type of chart is this?

Run chart

A project manager determines the trends a process is exhibiting she used

Run chart

Coho Winery has designed a new automated wine-bottle filling station. As bottles pass along the conveyor belt, they are filled then capped. The quality engineer is testing its functionality and needs a graph that shows the amount of wine in each bottle, along with a line that depicts the target amount, one liter. What tool is the engineer using?

Run chart

Assuming an iterative approach, which of the following will be conducted at the end of each iteration?

SCRUM retrospective

(certiology practice Exam 2 PK0-003) Several members have been out sick and the team has been unable to meet certain deadlines. What should the project manager use to determine how the project schedule is affected

SV (schedule variance)

AdventureWorks Cycles is looking for vendors to manufacture components for a new high-speed braking system. They've sent out a request for proposal (RFP) to several vendors. Which of the following information pieces would NOT be included in the RFP?

Salary information of the project manager and other important roles (RFP wouldn't include a request for the salary info for those roles doing work. vendor would only outline cost of project. Salaries would not be provided, nor would AdventureWorks require salary info to budget or select vendor. - Scope - Estimated budget - Schedule for delivery of components)

An analyst wants to plot variables against each other on a graph to determine the amount of correlation that exists between the variables. What is the name of this tool?

Scatter chart

You are leading a project to update the operating system on all the computers in your organization. You have a team member who is not staying current on tasks and you want to have a discussion about this. What is the best approach to take?

Schedule a private face-to-face meeting

You are working on a new purchasing system project and you are having difficulty finalizing the requirements with the purchasing department. You have been told that the purchasing manager, who works in a different city, does not like technology. What is the best approach to get the requirements finalized?

Schedule a telephone call

You are working on a new purchasing system project and are getting ready to end the project. You want to have a meeting with your key team members and other stakeholders to review how the project went and to document lessons learned, but most of them cannot travel to your location. The best option is to:

Schedule and hold a virtual meeting

You are executing the project plan for a new Point of Sale system for your retail stores and the training department has hired a new trainer who will be responsible for the Point of Sale system training. The trainer believes you need to add an additional week to the training you have allocated. You inform the project sponsor, client, and functional managers. What was the trigger for this?

Schedule change

You are working on the project plan for a new payroll system and you are finalizing the communication plan. Which of the following is NOT a communication trigger for communicating with the team?

Schedule changes (are triggers for communicating with the sponsor, client, and functional managers about the related effects on time, cost, and risk. - Business continuity response - Incident response - Resource changes)

You are two months into the conversion to a new purchasing system project and you have discovered that several of the deliverables have errors. The incorrect deliverables were all the work of the same team member and you need to find out what is causing the problem. What communication method would you use for this conversation?

Scheduled face-to-face meeting

You are two months into the conversion to a new purchasing system project and you have noticed that there is some tension among the team members. You decide to conduct a team-building session to help develop better relationships. What communication method would you use for this session?

Scheduled face-to-face meeting

A large project has the following members on the project management team: project manager, assistant project manager, scheduler, and expediter. Who is responsible for asking project resources for the status of their tasks?

Scheduler

A large project has the following members on the project management team: project manager, assistant project manager, scheduler, and expediter. Who is responsible for making updates to the project timeline?

Scheduler

A large project has the following members on the project management team: project manager, assistant project manager, scheduler, and expediter. Who is responsible for preparing reports concerning the status of the schedule?

Scheduler

The Coho Winery project manager has received approval from the sponsor to design and construct a new automated wine-bottle filling station. He or she is organizing the following information to prepare the next project management deliverable: Project objectives, deliverables, exclusions, and requirements Project constraints and assumptions Product acceptance criteria What will this deliverable be?

Scope

Which of the following are inputs to a project budget? (1.4)

Scope baseline, project schedule, and contractual agreements

You are working on a project to upgrade the enterprise resource planning (ERP) system, which includes a purchasing system and a new sales system. The project will take nearly a year, and three months in, management decides to drop the implementation of the purchasing component. This is an example of what type of change?

Scope change

You are working on a six-month project to redesign the corporate website and add product purchasing functionality. You are three months into the project when the sales manager decides that there should also be an order tracking feature on the website for both online and other types of orders. This is an example of what type of change?

Scope change

You are working on a six-month project to upgrade the operating systems on more than 4,000 corporate computers. The Chief Information Officer (CIO) decides to include the 1,500 computers in your subsidiary company, too. This is an example of what type of change?

Scope change

You are working on moving the in-house Human Resources Management System (HRMS) to a cloud self-service provider. The Vice-President of Finance wants to include payroll in the move, which was not previously included. This is an example of what type of change?

Scope change

Which of the following is NOT an example of scope creep?

Scope changes accepted through formal change control (- Adding features to a deliverable from a change request - Adding features to a deliverable because they are cool - Making just one little change in an accepted deliverable)

Which component of the project charter specifies what the project will produce? (1.3-part 1)

Scope definition

The manager of the TailSpin Toys robotic cat laser project is reviewing the project management plan prepared by the team, and something does not look right. Some of the subsidiary plans appear correct, but others do not. Which of the following are correct subsidiary plans?

Scope management plan, cost management plan, schedule management plan, human resource plan

The manager of the TailSpin Toys robotic cat laser project is reviewing the project management plan prepared by the team, and something does not look right. Some of the subsidiary plans appear correct, but others do not. Which of the following are correct subsidiary plans?

Scope management plan, risk management plan, procurement management plan, human resource plan

The term "baseline" is confusing the engineer who is working on the project plan for the Awesome Computers wireless network upgrade project. What are the components of the scope baseline?

Scope statement, Work Breakdown Structure (WBS), and WBS dictionary

In the Agile methodology, who is responsible for making decisions that govern what the team is doing to meet the customer's requirements?

Scrum team members

Which of the following is NOT a project?

Seasonally switching the output of a petroleum refinery from gasoline to heating oil. (It is an operation, which is repeated each year. - Initiating the final phase of a project - Closing a department store because of poor sales - Upgrading the order-entry system for a small steel-manufacturing company)

Which of the following is included on a qualified sellers list?

Sellers' names

You are working on a new purchasing system project and you are developing the communication plan. You are planning to select a vendor for the package. Which is NOT a way to let potential vendors know about the detailed requirements without distributing confidential information in the procurement documents?

Send an email (email not effective b/c confidential info can be forwarded too easily to unexpected recipients such as competitors. - Voice-conference - Face-to-face - Video conference)

You are working on a project to upgrade the Human Resources Management System (HRMS). The sponsor on this project is most likely to be the:

Senior Vice President of Human Resources

Who has the responsibility to resolve conflicts that arise between project priorities and day-to-day business priorities? (1.2-part 2)

Senior management

You are two months into the conversion to a new purchasing system project and you have been sending the same status information to all the stakeholders, but it appears that has not been as effective as you'd hoped. You plan on differentiating the status now. To which stakeholders should you just send status dashboard updates?

Senior management

You are developing a new purchasing system for a client and want to know which constraint will have the greatest impact on the success of the project. Which risk technique should you use?

Sensitivity analysis

A health care consultancy has a help desk that businesses can subscribe to. The standard contract states that 95 percent of the help desk calls will be answered with less than 10 minutes of hold time, or one percent of the monthly subscription fee will be refunded. This is an example of what?

Service Level Agreement (SLA)

Your company has a contract to design and maintain the customer-facing website for a consumer-goods company. The contract has a requirement that the site must be available 99.99 percent of the time to minimize missed sales opportunities for your client. What does this contract provision refer to?

Service Level Agreement (SLA)

You are bidding on an external contract project to update the operating system on more than 1000 computers at an organization. You realize you don't have enough resources to complete the project as specified, so you partner with another firm to split the work. This is an example of which type of response strategy?

Share

Where does authority reside in a matrix organization?

Shared between the project manager and the functional manager

The scheduler on the WingTip Toys mini-drone project needs to compress the schedule for the project. What are the two schedule compression techniques—fast-tracking and crashing—used for?

Shortening total project schedule duration

What is true of lessons learned during the project?

Should be documented throughout the project

Which of the following is true of project archives?

Should include key information such as baselines and performance data

Two engineers come to their manager with a problem and ask for help resolving it. The manager listens to both sides of the issue, then summarizes as follows: " It does not sound like there is a real problem here, but rather two slightly different ways to look at the same thing. Let's talk about what led to these viewpoints, and maybe we can conclude that there is nothing that needs changing." Which type of conflict resolution is the manager using?

Smoothing

You are five weeks into a nine-week project, and you have lost one of your team members. You divide that resource's tasks among the remaining resources, but now they are all over-allocated. You are told that you cannot increase the schedule, so what do you need to try to remove the over-allocation?

Smoothing

You are working on an update to the corporate website and you are close enough to open it for beta testing. What is the best method for getting the largest number of beta testers quickly?

Social media

(3.1) You are working on a new purchasing system project and you are developing the communication plan. You are planning to select a vendor for the package. What media would you plan to use for telling the possible vendors about the availability of the request?

Social media post

You are working on a new purchasing system project and you are developing the communication plan. The new system will affect how clients place their orders. What media would you plan to use for telling them when the new system is ready?

Social media post

Stakeholders are involved in a project in many ways. Which of the following is the best description of a stakeholder?

Someone who is affected by a project or who affects a project

Which statement best describes a project?

Something that produces a unique product, service, or result and has a start date and end date

Early in a project, the team will prepare a list of high-level requirements which will be used to develop more detailed requirements and the scope. These requirements are intended to satisfy a set of project objectives. Who approves this initial list of high-level requirements? (1.2-part 1)

Sponsor

Which stakeholder provides or obtains the financial resources for a project?

Sponsor

Who approves the initial project baselines and changes to the baselines?

Sponsor

Who has the responsibility to "market" a project to stakeholders who either see no benefit to the project or who are opposed to it?

Sponsor

Who is responsible for helping the project team overcome roadblocks to the success of the project?

Sponsor

Who is responsible for justifying the project to the organization?

Sponsor

You are a project manager whose project to build a new website has been over budget for several months. None of your management skills have worked, and each month is worse than the last. You suspect that the problems might be caused by several application developers. Who should you turn to for help?

Sponsor

You have prepared a charter for a new project. Who will sign the document?

Sponsor

Who should sign off on the completion of the project?

Sponsor and an external client, if there is one

You are executing the project plan for a new payroll system and you are likely to miss the next milestone date. Which stakeholders do you need to inform?

Sponsor and client

You are executing the project plan for a new payroll system and you discover that your quality assurance processes are not working and you need to update the quality management plan. Which stakeholders do you need to inform?

Sponsor and client

You are executing the project plan for a new payroll system. Which stakeholders do you need to communicate with about the impact on the project of business continuity responses?

Sponsor and team

You are executing the project plan for a new payroll system. You have performed a risk review and have updated the risk register. Which stakeholders do you need to inform?

Sponsor and team

You are executing the project plan for a new Customer Relationship Management (CRM) system and the project is running two weeks late. You are not likely to catch up, so you adjust the schedule. Which stakeholders do you need to inform?

Sponsor, functional managers, and client

A person with a vested interest in the outcome of a project is defined as a:

Stakeholder

You are executing the project plan for a new Point of Sale system for your retail stores and you have been informed by the business analyst that the training department has hired a new trainer who will be responsible for the Point of Sale system training. You inform the team and welcome the trainer to the project. What was the trigger for this?

Stakeholder changes

You are executing the project plan for a new payroll system and following your communication plan. Which of the following is NOT a communication trigger for communicating with just the team?

Stakeholder changes

A project does not have a formal "steering committee" to provide ongoing guidance to the project manager throughout the duration of the project. Who will serve in the absence of a steering committee?

Stakeholders

You are working on a new purchasing system project and are getting ready to start executing the project. Which of the following is an advantage of holding the kick-off meeting via video conferencing?

Stakeholders can participate from wherever they are and still have both auditory and visual feedback.

You are working on a new purchasing system project and are getting ready to start executing the project. Which of the following is an advantage of emailing the project plan to selected stakeholders?

Stakeholders may communicate at their convenience.

You are working on a new purchasing system project and are getting ready to start executing the project. Which of the following is a disadvantage of holding the kick-off meeting in person?

Stakeholders need to be in the same physical location at the same time.

You are working on a new purchasing system project and are getting ready to start executing the project. Which of the following is a disadvantage of holding the kick-off meeting via video conferencing?

Stakeholders need to have the communication technology installed in their locations.

You are working on a new purchasing system project and are getting ready to start executing the project. Several components of the project plan are confidential. Which is NOT a reason you might want an in-person meeting to discuss it rather than email it to selected stakeholders?

Stakeholders need to have the communication technology installed in their locations. (Stakeholders do not need any specific type of technology other than the corporate standard email and document systems to receive an emailed document or to participate in an in-person meeting. - The confidential content might be forwarded to inappropriate recipients. - Stakeholders will participate more in person. - You need to have everyone's email address to email it to them.)

What can project management software be used for?

Start and finish dates, links between activities, cost estimates, resource assignments, Work Breakdown Structures (WBS), and project reports

The critical path of the network diagram is

Start-C-E-Finish

Which of the following is the primary purpose of an MOA or an MOU?

State expectations of all signatory parties to reduce potential misunderstandings.

What does SOW stand for?

Statement of Work

Which project document exists in two forms: a brief document that is written during the Initiation phase or a very detailed document that is written in the Planning or Execution phase?

Statement of Work (SOW)

(4.2 Part 2) The new order-entry system project is in the Executing phase, and the project manager is preparing a report for the sponsor. It will contain how much work should have been done (hours and cost) by this point in the project; and how much work was actually done (hours and cost). Which type of report is being prepared?

Status report

A real estate developer is preparing to begin work on a subdivision that will consist of 20 single-family homes. This will be a large undertaking, requiring the expertise of architects, construction managers, marketers, financial specialists, and attorneys. The developer recruits one person from each area to provide guidance and support throughout the work. What is this team known as?

Steering committee

During which stage of team development will the manager use most of his or her conflict management skills?

Storming

TailSpin Toys is investigating the feasibility of developing an educational math game for three-to-six-year-old children. The company has had many successes in the game field and wants to leverage this success with a game for children this young. The developers are confident that they can create an eye-catching and fun game that parents and kids will love. This characteristic of the game project can be considered a:

Strength

WingTip Toys is considering whether to create a new kind of mini-drone for hobbyists. It will have features not available in competitors' drones, and can be ready for market in three months because it will leverage patented features in other WingTip drones. The project manager is performing a Strengths, Weaknesses, Opportunities, and Threats (SWOT) analysis as part of the feasibility study. These characteristics of the mini-drone project can be considered a:

Strength (internal (to the organization) origin, and is helpful to the objectives of the project. WingTip Toys can capitalize on previous products and patents, which should help it get the new product to market quicker than the competition.)

You are managing the conversion of an in-house payroll system to a cloud-based system and are identifying the potential risks. You want to be sure to consider both positive and negative risks. Which of the following is the best technique for this?

Strengths, weaknesses, opportunities, and threats (SWOT) analysis

The project manager is most senior in which organizational structures?

Strong Matrix

You are working on the installation of a new Customer Relationship Management (CRM) system and the marketing manager has submitted a change request. You have determined that the appropriate Change Control Board (CCB) is the steering committee for IT projects. What is the next step in the process?

Submit the change to the Change Control Board (CCB) to gain approval

Which of the following is a role of a project coordinator?

Support the project manager and assist in administrative tasks

When stakeholders discuss product deliverables, they are referring to:

Tangible products or services produced by the project work

You are executing the project plan for a new Point of Sale system for your retail stores and the testing team has just finished developing the test plans. You inform the rest of the team. What was the trigger for this?

Task initiation/completion

The project team is meeting to discuss which tasks in a new project for Lucerne Publishing Co. will be most important. It is early in the project, and the Work Breakdown Structure (WBS) has not been prepared yet. Choose the tasks with the highest priority.

Tasks subject to the highest risk

You are executing the project plan for a new Customer Relationship Management (CRM) system and the project is running two weeks late. Despite this, you have just passed the latest gate review. Which stakeholders do you need to inform?

Team

You are executing the project plan for a new Customer Relationship Management (CRM) system and the project is running two weeks late. Last week three tasks were started and another two were completed. Which stakeholders do you need to inform?

Team

You are executing the project plan for a new payroll system and it is approaching the time for a scheduled audit. Which stakeholders do you need to inform?

Team

You are executing the project plan for a new payroll system and the change control board has approved a project change. Which stakeholders do you need to inform?

Team

You are executing the project plan for a new payroll system and the test system goes down. Which stakeholders do you need to inform of this incident?

Team

You are executing the project plan for a new Customer Relationship Management (CRM) system and two of the stakeholders have left the organization and have been replaced by new stakeholders in your project. Which stakeholders do you need to inform?

Team and affected stakeholders

You are executing the project plan for a new payroll system and need to make some resource changes. Which stakeholders do you need to inform about any impacts on schedule, cost, or risk?

Team and functional managers

During the daily meeting of an Agile scrum team, several team members are texting on their mobile phones, violating a ground rule that no mobile devices should be used in the meetings. Who should enforce this rule?

Team members

Virtual teams are becoming more common as communication technology improves, but they pose management challenges because team members are geographically dispersed. A project manager requested that the 15-person team for a new project be co-located and received permission from senior management. Which of the following statements best describes co-location?

Team members are physically relocated to one facility.

Which of the following documents are contracts between the organization and one or more external entities to work together?

Teaming agreements

You are managing the conversion of an in-house payroll system to a new server and are identifying the potential risks. There is a risk that your internal server will not have the bandwidth for all the users of the new system. What category risk is this?

Technical, quality, or performance

You are working on a project to install a new enterprise resource planning (ERP) system, which includes a Customer Resource Management (CRM) component. The system that has been selected has only been implemented in 10 other companies. What category of risk is this risk?

Technical, quality, or performance

You are working on a project to install a new enterprise resource planning (ERP) system, which includes a Customer Resource Management (CRM) component. The system selected needs to run with your existing database management system (DBMS). This is considered which type of requirement?

Technical/Non-functional

You are working on a project to upgrade the Human Resources Management System (HRMS). You are going to be using a new in-house server that is being installed as its own project. Which of the following is the type of requirement this adds to your project?

Technical/Non-functional

(3.2 part 2) You are working on a six-month project to upgrade the operating systems on more than 4,000 corporate computers in three different countries. Which of the following would NOT be a communication concern?

Technology (not a consideration b/c the stakeholders work for your company and already have all the same hardware and software. - Intra-organizational communication patterns - Culture - Geography)

You are two months into the conversion to a new purchasing system project and you have discovered that several of the deliverables have errors. You need a decision from the sponsor today on how to proceed. What communication method would you use for this conversation?

Telephone call

You are trying to confirm requirements with the stakeholders of the purchasing system update project. There are just one or two questions you have for each stakeholder and they are scattered in different locations across the country. Which of the following communication methods would be best to use?

Telephone calls

Which of the following is NOT considered a barrier to effective communication?

Templates (Templates, especially for status reports, meeting agendas, and the like are important aids in communication. They help ensure uniform approaches and minimize information gaps. - Relationships - Culture - Technology)

You are two months into the conversion to a new purchasing system project and you have discovered that several of the deliverables have errors. You are in a taxi on the way to a meeting with the sponsor about the problems, but there is a traffic and you are going to be late for the meeting. What do you do?

Text

You are working on a new purchasing system project and you are developing the communication plan. What media would you plan to use for notifying team members of a failed test requiring their immediate attention?

Text message

You are working on a new purchasing system project and you are in the middle of testing when a major component fails and needs your team's immediate attention. What media would you use to notify team members?

Text message

Which of the following is the condition in which the team just cannot finish the last piece of work and cannot complete the project?

The 95 percent phenomenon

You are managing the development of a new Human Resources Management System (HRMS) and are getting ready to do a test conversion of payroll data. Which stakeholders should NOT have access to this test data and results?

The Human Resources Management System (HRMS) vendor team (Anyone who is an external team member should not have access to confidential internal data such as payroll information. - You as project manager - Human resources clerks - The sponsor)

Which tool is used to collect, archive, and distribute project information so that project performance can be determined?

The Project Management Information System (PMIS)

Which tool is consistently used to document the roles and responsibilities of a project?

The Responsibility Assignment Matrix

In a Responsible, Accountable, Consult, Inform (RACI) matrix, what is the difference between Responsible and Accountable?

The Responsible role is given to one or more persons who do the work on an activity. The Accountable role is given to one person who is ultimately answerable for the work. The accountable person approves and/or signs off on the work.

You are working on a project to upgrade the enterprise resource planning (ERP) system, which includes a purchasing system and a new sales system. Two months after you have signed the contract with the vendor, it announces that it is being acquired by another software firm that markets a competing ERP system. Which of the following is NOT likely to happen to your project?

The acquisition will not affect your project. (it will have some effect, even if it is just a change in salesperson. - The enterprise resource planning (ERP) system you purchased will be pulled by the acquiring vendor. - You may need to extend the implementation date. - You will need to renegotiate the contract with the new vendor)

Which of the following is the best indicator of project performance?

The budget for developing the software was $150,000, and the actual amount spent was $120,000.

A company is mid-way through a project to replace its present order-entry system. The new project is very expensive, and senior management is concerned about maintaining its financial viability. Which of the following factors will be of greatest concern to the project manager?

The business case

The Volcano Coffee Company is testing a new coffee bean roaster. The Quality Control manager is reviewing a line graph of the number of batches of beans roasted each day, against a daily target of 500 batches. He or she notes that in the last week, the number of batches has fallen below the target and it appears that this pattern will continue. Which type of chart is this, and what conclusion can be drawn from the data?

The chart is a run chart. The engineer can conclude that the downward trend will continue unless some action is taken to reverse it.

What general conclusion can be made about a scatter chart?

The closer the data points represent a diagonal line, the better the correlation between the two variables.

You are working on an update to the corporate website and project execution has started. As your team members work with one another, what is an advantage of communicating via instant messaging?

The communication is immediate.

You are working on a new purchasing system project and are getting ready to start executing the project. Which of the following is a disadvantage of emailing the project plan to selected stakeholders?

The content might be forwarded to inappropriate recipients.

You are developing the project plan for a new enterprise resource planning (ERP) implementation for your organization. The project will take nearly a year, and you are trying to determine the frequency of communication with your various stakeholder populations. Which stakeholders might want daily status meetings?

The core team

You are developing the project plan for a new enterprise resource planning (ERP) implementation for your organization. The project will take nearly a year, and you are trying to determine the type of communication to use with your various stakeholder populations. Which stakeholders would accept text messages about the project?

The core team

You are two months into the conversion to a new purchasing system project and you have been sending the same status information to all the stakeholders, but it appears that has not been as effective as you'd hoped. You plan on differentiating the status now. To which stakeholders should you send detailed status information on all the tasks?

The core team

The project team has been working diligently to meet all of the milestones of their project. Acceptance of the interim and final deliverables is a key objective. What should the deliverables be compared to?

The current baselines

AdventureWorks Cycles tested the high-speed braking system that it developed because the quality engineer wanted to know if there was a relationship between the speed a cycle is going and stopping distance. He or she conducted 100 tests, with cycle speeds ranging from 60 mph to 120 mph. The data was plotted, and the graph showed 100 dots that, if connected, looked like a nearly straight line. Which tool was used, and what can the engineer conclude from the results?

The engineer used a scatter chart, with speed on one axis and stopping distance on the other axis. The resulting nearly straight line means there is a very good relationship between speed and stopping distance.

You are developing the project plan for a new enterprise resource planning (ERP) implementation for your organization. The project will take nearly a year, and you are trying to determine the frequency of communication with your various stakeholder populations. From which stakeholders should you gather weekly status information?

The entire team

You are two months into the conversion to a new purchasing system project and you have been sending the same status information to all the stakeholders, but it appears that has not been as effective as you'd hoped. You plan on differentiating the status now. To which stakeholders should you send detailed information just on things that affect their tasks?

The entire team

You are working on a project to upgrade the Human Resources Management System (HRMS). You are ten weeks into the 24-week project and your sponsor leaves the organization. The new sponsor decides that the schedule should be cut by at least three weeks, and you cannot increase resources. Which of the following is true about the effect of this cut?

The existing resources will need to work overtime.

Your company has six locations around the globe and you are working on a project to implement a new project management information system company wide. Which of the following statements is NOT true?

The fact that there are multiple global locations does not affect the project. (- The new system must work on the infrastructure environment in each location. - Someone from each location should be on the project team. - The project will need to include training for each location's employees.)

The communication plan is a critical component of the project management plan. What does the communication plan NOT contain?

The feedback implementation process

You are working on a project to upgrade the Human Resources Management System (HRMS). You are going to be using a new in-house server that is being installed as its own project. Which of the following is NOT a deliverable of your project?

The installation of the new server (deliverable of the server project. - The installation of the Human Resources Management System (HRMS) - Training the users for the Human Resources Management System (HRMS) - A company-specific user manual for the Human Resources Management System (HRMS))

You are working on a project to upgrade the Human Resources Management System (HRMS). You are going to be using a new in-house server that is being installed as its own project. Which of the following is NOT true about the relationship between these two projects?

The installation of the new server is an internal project task. (this is a separate project, it is an external task. - The installation of the new server is an external project task. - If the new server installation project is delayed, your project may be delayed. - Your project is dependent on the new server project.)

You are developing the project plan for a new enterprise resource planning (ERP) implementation for your organization. The project will take nearly a year, and you are trying to determine the type of communication to use with your various stakeholder populations. Communicating by instant messaging would be most appropriate for which stakeholders?

The internal team

The schedule to manufacture the new robotic cat laser has over 100 activities. On the schedule, some are marked as being on the critical path. Which of the following is true for activities on the critical path? (1.6-part 1)

The late finish and early finish are the same.

You are working on a project to upgrade the Human Resources Management System (HRMS). The sponsor on this project is the HR Vice-President, who is retiring in two months, three months before the project is completed. This is a risk to your project because:

The new HR Vice-President may not support the project.

A project is undertaken for a specific and justifiable reason or purpose. Which of the following choices is a valid reason to update a company's sales website?

The new design will result in a 10 percent increase in the number of repeat customers within the first six months of being implemented. (The outcome should be specific enough to be confirmed through quantitative means.)

A new product catalog website is being developed using the Agile methodology. Midway through the project, the client asks for a new screen that will contain warranty information for each product in the catalog. How will the Agile team handle this scope change?

The new requirement should be prioritized against other requirements in the product backlog, and the product backlog re-written according to this new priority.

One technique for gathering requirements is to watch people perform their jobs in their normal environments. Which of the following is NOT a reason to use this technique?

The new system may not be able to be modified to accommodate local differences. (- The same process may need to be performed differently in different environments. - If people are brought into a test environment, they may try to do things differently in the different environment. - People may not know they do things differently if you just interview them.)

The manager of the Public Works Department project to build a new bridge over the Troubled Waters stream has almost fifty people working on the project and needs to see how they relate to each other. Which document shows the reporting structure within the project and its relationship to its parent organization, the Public Works Department?

The organization chart

You are starting the risk planning process on your new project to update the purchasing system for the organization. Which of the following is NOT a potential threat?

The organization decides to also upgrade the hardware infrastructure. (t is an opportunity, not a threat, because it gives you a more up-to-date infrastructure. - A key team member will leave the project mid-way. - The new purchasing system will not run on the existing hardware infrastructure. - The budget will be cut.)

You are working on a project to upgrade the enterprise resource planning (ERP) system, which includes a purchasing system and a new sales system. Two months after you have signed the contract with the vendor, your company announces it is spinning off the pet foods division. This means that:

The pet foods division will become a standalone company.

You are two weeks into a four-month project and one of your team members has requested a two-week vacation during the time they are scheduled to work on the project. You have updated the resource calendar to reflect this request. Which of the following is something else that you may have to change?

The project duration

During the Monitoring and Controlling phase, which two types of data are compared to produce which result?

The project management plan and work performance information are used to generate variances.

The project sponsor has cut the resources required for project completion. The project manager cannot complete the project without additional resources.Which of the following should the project manager do to obtain the resources?

The project manager should identify and document the reasons for the additional resources in a change request.

Building and managing a team includes setting expectations for team members, and ground rules provide a way to do this. Which of the following statements about ground rules is NOT true?

The project manager should rigidly enforce ground rules. (PM should not be the sole enforcer of ground rules. Team should be enforcing, in addition to the PM. - Ground rules should be set early, and all team members should commit to abiding by them. - Ground rules should include boundaries for acceptable behavior. - Team members should participate in setting ground rules.)

You have moved into executing the project plan for the Customer Resource Management (CRM) system and management announces that it is reorganizing the marketing department. All internal and external salespeople and the marketing communications team now report to a single vice president of Marketing and Sales, who is/has been your project sponsor. Which of the following is NOT a way in which your project is likely to be affected?

The project will be canceled. (It is not likely that the new VP will cancel the project, especially if he/she is already the project sponsor. - You will need to review the communication plan. - There might be a delay in project approvals. - You will need to review and update the stakeholder register.)

You are working on a project to upgrade the Human Resources Management System (HRMS). You are ten weeks into the 24-week project and your sponsor leaves the organization. The new sponsor decides that the schedule should be cut by at least three weeks. Which of the following is NOT true about the effect of this cut?

The quality will need to be decreased. (Presuming cost and/or scope can be adjusted, there would be no need to reduce quality. - The scope may need to be decreased - The cost may need to be increased - You may need to add more resources)

Trey Research, Inc. begins approximately 100 projects a year, and the Project Management Office (PMO) requires every project plan to include an organization chart. Which of the following should be included in the organization chart of their projects?

The reporting structure of the project and how it fits into the organization to which it belongs (for example, the company)

When stakeholders tell you they are disappointed in the quality of the project's product or service, it means that:

The results do not match their requirements

An engineer with TailSpin Toys is assisting the project manager plan the robotic cat laser project and is learning about baselines. He or she knows that the scope baseline consists of the scope statement, Work Breakdown Structure (WBS), and WBS dictionary, but is unsure what goes into the cost baseline. What is included in the cost baseline?

The rolled-up activity costs, plus any activity contingency reserves, plus any work package contingency reserves

You are working on a project to upgrade the enterprise resource planning (ERP) system, which includes a purchasing system and a new sales system. Two months after you have signed the contract with the vendor, your company announces it is outsourcing its manufacturing to a company based in Mexico. Which of the following is most likely to happen with your project?

The sales portion will continue as planned, but the purchasing system will not, as purchasing will now be the responsibility of the Mexican firm.

You are two months into the conversion to a new purchasing system project and you have been sending the same status information to all the stakeholders, but it appears that has not been as effective as you'd hoped. You plan on differentiating the status now. To which stakeholders should you just send status dashboard updates and details on variances?

The sponsor

Project A is in the Planning phase, and Project B is in the Execution phase. Project A is using resources that have been assigned to Project B. Both projects need one of the resources at the same time. Project B contends that an Execution-phase project should have priority over a Planning-phase project, and will not temporarily release the resource. Where can the two project managers turn for help?

The sponsors of the two projects

The staffing management plan is used during team selection. How does this document relate to other documents?

The staffing management plan is a component of the human resource plan.

A new product catalog website is being developed using the Agile methodology. Midway through the project, the client asks for a new screen that will contain warranty information for each product in the catalog. This requirement has been added to the project, and the team is ready to begin work on it with a new sprint. What should happen next?

The team should hold a sprint planning meeting, where the sprint goal will be set and user stories will be developed.

Which of the following statements is not true about project deliverables?

The total list of deliverables is not known until the schedule is developed.

A Pareto chart is a tool that is used to determine the relative impact each quality problem has on project performance. Which statement best describes the philosophy of the Pareto Principle?

The vast majority of defects are caused by a small percentage of the identifiable causes. Therefore, improvement efforts should be reserved for these vital few problems.

Which option helps notify the work package owners when to begin work on project deliverables? (1.3-part 2)

The work authorization system

You are working on an update to the corporate website and project execution has started. As your team members work with one another, what is an advantage of communicating via text messaging?

They can contact one another when they are not at their desks.

An engineer is assisting the project manager plan the project. He or she has added activities and dependencies to the plan, but is unsure how to determine the start and finish dates for them. Who should calculate the start and finish dates of an activity?

They do not come from a person, but from the scheduling tool.

WingTip Toys is considering whether to create a new kind of mini-drone for hobbyists. It will have an extended battery life and will be very light weight, features not available in competitors' drones. The engineers say it can be ready for market in three months because it will leverage patented features in other WingTip drones. But the marketing department thinks that a competitor might get there first. The project manager is performing a Strengths, Weaknesses, Opportunities, and Threats (SWOT) analysis as part of the feasibility study. These characteristics of the mini-drone project can be considered a:

Threat

TailSpin Toys is investigating the feasibility of developing an educational math game for three-to-six-year-old children. There are a number of similar games that target young children, but the company hopes their reputation will allow them to be successful. This characteristic of the game project can be considered a:

Threat (external (to the organization) origin and is harmful to the objectives of the project. Competition in the marketplace poses a threat to the success of the project.)

Although there can be many constraints on a project, the three constraints that are commonly considered to make up the triple constraint triangle are:

Time, cost, and scope

You are working on a project to upgrade the enterprise resource planning (ERP) system, which includes a purchasing system and a new sales system. The project will take nearly a year, and three months in, management decides that at least the new sales system component must be implemented by year-end, two months earlier than originally planned. This is an example of what type of change?

Timeline change

You are working on a six-month project to redesign the corporate website and add product purchasing functionality. You realize that you underestimated how long design would take and you calculated a new duration. This is an example of what type of change?

Timeline change

You are working on a six-month project to upgrade the operating systems on more than 4,000 corporate computers. You need to update the purchasing department computers before their new software can be installed, yet they weren't scheduled until much later in the original plan. This is an example of what type of change?

Timeline change

You are working on moving the in-house Human Resources Management System (HRMS) to a cloud self-service provider. Your vendor has noted that it will not have your servers online until two weeks after it was supposed to get them online. This is an example of what type of change?

Timeline change

The reason for a post-project review is

To analyze project performance

The team has been hard at work writing all of the subsidiary documents that make up the project management plan, and it is time to have the fruits of their labor approved. What is the benefit of having the project sponsor and the stakeholders review the project management plan?

To finalize the plan so it can be signed off

Which of the following is a benefit of formally closing a project?

To provide historical data for future projects

What is the primary role of a functional manager in a matrix project?

To provide human resources to the project

Which of the following project alternatives would be the least likely for management to pursue?

To replace all laptops in the company older than five years. (Unless given more information, there is no justification that laptops of that vintage should be replaced.)

What is the primary benefit of having a vendor knowledge base?

To research which vendors might have the ability to fill a purchasing need

A new inexperienced team member is not performing you should

Train the team member

You are working on a project to upgrade the enterprise resource planning (ERP) system, which includes a purchasing system and a new sales system. There is concern that the new system will not be implemented in time to meet the demand for Halloween candy orders, which is historically your biggest sales season. You purchase insurance on the implementation, which is an example of which type of risk response?

Transfer

You are working on moving the in-house Human Resources Management System (HRMS) to a cloud self-service provider. One of your team members submitted a change request that has been approved and implemented and validated. What is the next step in the process?

Update documents and apply version control

You are working on the installation of a new Customer Relationship Management (CRM) system and the marketing manager has submitted a change request that has been approved, implemented, and validated. What is the next step in the process?

Update documents and apply version control

When you created your project plan, the sponsor wanted you to focus on completing the project in three months. Now, after four weeks, the sponsor is more concerned about how much the project will cost. He asks you to cut the cost by at least 10%. To do this, you will likely need to do which of the following?

Use lower cost resources and extend the schedule

After identifying all known tasks, the project manager has started to sequence and set durations.Which of the following describes how the project manager should BEST determine the initial sequence and durations? (cert library)

Use milestones identified in the project charter.

You are working on moving the in-house Human Resources Management System (HRMS) to a cloud self-service provider. One of your team members has submitted a change request that has been approved and implemented. What is the next step in the process?

Validate change/quality check

You are working on the installation of a new Customer Relationship Management (CRM) system and the marketing manager has submitted a change request that has been approved and implemented. What is the next step in the process?

Validate change/quality check

Which type of analysis is used to compare budgeted costs with actual costs?

Variance

You are executing, monitoring, and controlling your project, so you are comparing the amount of scope that should have been done by now to what has been done. You are conducting:

Variance analysis

The manager of a project that will be doing a substantial amount of purchasing needs to get ready for this phase of the project. He or she wants to keep the purchasing on schedule, so the manager decides to collect data about similar past projects and potential contractors who might submit proposals. This information consists of past contracts, lessons-learned documents, and purchasing files. He or she also researches the Internet to find contractors who have not worked for the company before. What is the result of all of this research?

Vendor knowledge base

A Request for Proposal (RFP) is frequently followed by a bidder conference. Which of the following is not an advantage of a bidder conference?

Vendors can examine the proposals of their competitors.

You are working on a project to upgrade the enterprise resource planning (ERP) system, which includes a purchasing system and a new sales system. As you are executing your communication plan, you notice that your remote stakeholders are not participating actively in meetings. Which method should you switch to for better participation?

Video conference

You are working on a project to upgrade the enterprise resource planning (ERP) system, which includes a purchasing system and a new sales system. You are creating your communication plan and you have some concern that your remote stakeholders may not participate actively in meetings. Which is the best method for ensuring participation?

Video conference

You are working on a new purchasing system project and you are having difficulty finalizing the requirements with the purchasing department. You notice that the stakeholders you need to contact for some simple follow-up are all listed as available right now in your meeting software, so you send them all a meeting notice and ask them to join you in the meeting software for 10 minutes. What type of meeting is this?

Virtual impromptu

You are working on a new purchasing system project and you are having difficulty finalizing the requirements with the purchasing department. You send a meeting notice to the purchasing manager and two purchasing clerks for a 15-minute meeting tomorrow in your online meeting software with an agenda of finalizing the requirements. What type of meeting is this?

Virtual scheduled

You are trying to finalize the Work Breakdown Structure (WBS) for updating the purchasing system project and you would like input from the team. They are scattered in different geographical locations across the country. Which of the following communication methods would be best to use?

Virtual synchronous meeting

You are working on a project to upgrade the enterprise resource planning (ERP) system, which includes a purchasing system and a new sales system. You are creating your communication plan and you have remote stakeholders who work from home, some in rural areas without broadband connectivity. Which is the best method for holding meetings with these stakeholders?

Voice conference/Teleconference

You are working on a project to upgrade the enterprise resource planning (ERP) system, which includes a purchasing system and a new sales system. You are planning the kick-off meeting and you have remote stakeholders who work from home, some in rural areas without broadband connectivity. Which is the best method for holding the kick-off meeting?

Voice conference/Teleconference

Which tool would be used to decompose a project?

WBS (work breakdown structure)

You order a new printer for your office, and when it arrives, you see that it is defective. You contact the supplier and ask for a replacement. What is the correct term for this situation?

Warranty of merchantability

TailSpin Toys is investigating the feasibility of developing an educational math game for three-to-six-year-old children. The company has had many successes in the game field, but has not developed an interface for children this young. Nevertheless, the developers are confident that they can create an eye-catching and fun game that parents and kids will love. This characteristic of the game project can be considered a:

Weakness

WingTip Toys is considering whether to create a new kind of mini-drone for hobbyists. It will have features not available in competitors' drones, and can be ready for market in three months because it will leverage patented features in other WingTip drones. However, WingTip has never made a product with the extended battery life and light weight of the new mini-drone. The project manager is performing a Strengths, Weaknesses, Opportunities, and Threats (SWOT) analysis as part of the feasibility study. These characteristics of the mini-drone project can be considered a:

Weakness

You are moving the corporate servers to a new building in Buffalo, NY in January and February. You have included snow in your risk list. Your sponsor asks you what your contingency is for this risk. What is she asking?

What your plan is if it does snow and it impacts the move.

An engineer working on the wireless network upgrade project asks the project manager to clarify some of the scheduling terms, specifically the types of relationships that can occur between two activities. Which of the following is an example of a finish-to-start relationship?

When Activity A finishes, Activity B can start.

When is a project complete?

When formal acceptance from the client has been obtained

A scheduler was recently hired by Lucerne Publishing Co. to work on the project for a new textbook. The scheduler has included the appropriate governance gates in the schedule, but does not know who should sign off on them. In which instance would a client sign off on governance gates?

When stipulated in a contract

Trey Research has many clients, in both the private and public sectors. In which instances would legislative approval be required to set governance gates?

When stipulated in a contract where the client is a government/legislative entity

A project manager has assigned resources to all of the tasks and has noticed that several of the resources will be working more than the standard eight-hour day. This overallocation will be a problem because overtime pay has not been authorized. One solution to the overallocation is to shift some of the work to another resource who has the same hourly pay rate, so that both can work on a task simultaneously and avoid overtime pay. When would this be a good option?

When the resources have the appropriate skills, and when the task is effort-driven

When should a contract be closed?

When the scope of the contract has been completed to the satisfaction of the buyer, and all contract terms have been met by the buyer and the seller

When should contracted resources be released from a project?

When their work on the project has been completed

A RACI (Responsible, Accountable, Consult, Inform) matrix would help solve which of the following sources of confusion?

Who is responsible for doing what

Which of the following is not shown on the Responsible, Accountable, Consult, Inform (RACI) matrix?

Who reports to whom

The manager of the bridge over the Troubled Waters stream project has prepared the minutes of the first weekly project meeting. To whom should the minutes of a project meeting be distributed?

Whomever has been stipulated in the communication plan

The project team wants to create an online repository where documents can be stored and modified by other team members. The repository should also have links in the documents, that can be followed to learn more about a topic. What is this called?

Wiki

What is the name of a repository where a Project Management Office (PMO) can publish their policies, templates, and other documentation, and which can be structured to provide links for procedures the PMO may require?

Wiki pages

A project manager is developing a definitive cost estimate. Which of the following would be most beneficial?

Work Breakdown Structure (WBS)

An administrative assistant has just been assigned to the Fabrikam team to manufacture components for the AdventureWorks Cycles high-speed braking system project. He or she is looking at a graphical representation of the deliverables included in the project. What is this graphic called?

Work Breakdown Structure (WBS)

Which of the following would be most useful when assigning resources to the WingTip Toys mini-drone project?

Work Breakdown Structure (WBS)

A team member is confused about the difference between two work packages with similar names. The best document to have that team member consult is the:

Work Breakdown Structure (WBS) Dictionary

Your Change Control Board has approved a change to the scope of your project. You have updated the Work Breakdown Structure (WBS) to include the new work. What other parts of the Scope Baseline should you review and update if necessary?

Work Breakdown Structure (WBS) Dictionary and Scope Statement

What term describes the lowest level of detail in a Work Breakdown Structure (WBS)?

Work packages

(4.3 part 2) A homeowner goes to the store to purchase weatherproof stain for use on an outdoor deck, but the sales person gives him or her stain for indoor-only use. After a rainstorm, the deck is ruined and the homeowner complains. Has a warranty been violated, and, if so, which type of warranty?

Yes, a warranty of fitness for purpose has been violated.

You began a project on May 1 and the target completion date is December 15. On November 1, the client instructed you to stop work on the project immediately because they no longer need the project's deliverables. You are to permanently archive everything you have done to this point. Should you now move to the close phase activities of the project management process?

Yes, because the project is considered complete.

You are creating the communication plan on a new purchasing system project. Who should you list as minimum stakeholders to attend the closing meeting?

You and the team

You are finalizing a contract with a vendor for development of your new website and have a few remaining questions. When you contact the vendor representative you've been dealing with, which of the following is a not a technical consideration?

You are in two different time zones.

You are working on a project to install a new enterprise resource planning (ERP) system, which includes a Customer Resource Management (CRM) component. There was a risk that one of your key team members would leave the organization before implementation and you mitigated that risk by cross-training another team member. The back-up team member has since left the organization. As you are reviewing your risk register, what is NOT an option for that risk now?

You can lower the probability of the risk. (- You need to mitigate the original risk again by cross-training another person. - You need to increase the impact on the risk. - You need to add a contingency response.)

You are working on a project to upgrade the enterprise resource planning (ERP) system, which includes a purchasing system and a new sales system. During the original risk planning, there was concern that the new system will not be implemented in time to meet the July demand for Halloween candy orders, which is historically your biggest sales season. Your implementation date was set to June 15th. It is now May and the project is slightly ahead of schedule. As you are reviewing your risk register, what is true about that risk now?

You can lower the probability that it will happen.

You are working on a project to redesign the website, and decide to use a new web design tool that no one on the team has used before. A risk to this project was that you would not be able to train the team members on the new tool in the allotted time. The project is proceeding as scheduled and all the team members are effectively using the new tool. When you review your risks, what should you do with this one?

You can reduce the probability and impact to zero to close out the risk.

You are working on moving the in-house Human Resources Management System (HRMS) to a cloud self-service provider. One of your team members has submitted a change request and you have determined that you have the authority to approve or deny the change. What is the next step in the process?

You deny or approve the change

Scope creep means that:

You have accepted additional project work without following appropriate change control processes

You purchase a set of house plans from a magazine, and build your new home by following the plans exactly. Your friend across town likes your new home, and uses the same set of plans to construct a home. Have the two of you completed one project or two?

You have completed two projects.

You are working on a project to upgrade the enterprise resource planning (ERP) system, which includes a purchasing system and a new sales system. During the original risk planning, there was concern that the new system will not be implemented in time to meet the July demand for Halloween candy orders, which is historically your biggest sales season. Your implementation date was set to June 15th. It is now March and you have learned that your largest competitor has gone bankrupt. As you are reviewing your risk register, what is true about that risk now?

You need to raise the impact if it happens.

You have taken over a project from another project manager and are concerned that the consultant working on the project may leave before the project is completed. Which of the following is an example of a contingency response?

You plan to hire another consultant if the original consultant does leave.

You are working on an external contract project to update the operating system on more than 1000 computers at an organization. The contract provides a penalty for taking more than three months to finish the work. Which of the following is an example of transferring the risk?

You purchase completion insurance to offset the penalty amount.

You have moved into executing the project plan for the Customer Resource Management (CRM) system and your company announces that your current building lease has not been renewed. You will be moving to another location, as yet to be determined. Which of the following is NOT a way in which your project is likely to be affected?

You will have new stakeholders. (will not affect the project stakeholders, but it might affect their locations. - Your Customer Resource Management (CRM) software might be needed to do a mass email to customers about the move. - There might be a delay in project execution during the move. - The project might be canceled due to lack of funding.)

You have moved into executing the project plan for the Customer Resource Management (CRM) system and management announces that it is forming a project management office (PMO) and you now report to the PMO. Which of the following is NOT a way in which your project is likely to be affected?

You will need a new team. (It is likely that your team would still report to the same functional managers they did prior to the reorganization, so the team should not be affected. - You will need to update the communication plan. - There might be a delay in project approvals. - You will need to review and update the stakeholder register.)

When you created your original project plan, you were counting on getting highly skilled, experienced resources; however, you were only able to acquire novice resources. Which of the following is not true about adjustments you may need to make?

You will need to decrease the schedule. (- You will need to increase the schedule. - You will need to increase the work effort estimates. - You will need to decrease scope.)

You are working on a project to redesign the website, and will be using a new web design tool that no one on the team has used before. Which of the following is NOT a risk to the project?

You will need to hire someone who knows the tool. (- You will not be able to train the team members on the new tool in the allotted time. - The new design tool does not work as specified it would. - Remote access to the new design tool is limited to one person per company.)

You have moved into executing the project plan for the Customer Resource Management (CRM) system and your Project Management Office (PMO) issues an updated version of the corporate project management methodology, which goes into effect immediately. The revised methodology requires weekly status updates to the PMO. How does this affect your project?

You will need to update the communication plan to add the new status reporting requirement.

You have moved into executing the project plan for the Customer Resource Management (CRM) system and your purchasing department issues a new vendor management methodology. Which of the following is NOT a way in which your project is likely to be affected?

You will no longer be able to purchase software. (A new policy would not tell you that you could no longer purchase a software package. - Your project will need to follow the new policy. - There might be a delay in purchasing to redo work according to the new policy. - The project will be put on hold.)

You have moved into executing the project plan for the new website design when your company announces that it is being acquired by another company. Which of the following is NOT a way in which your project is likely to be affected?

Your project budget will be increased. (If there is an effect on budget from the acquisition, it would likely decrease it, not increase it. - The project will be canceled. - You may have a new sponsor who will want to make changes in your direction. - The project will be put on hold.)

(3.5) You have moved into executing the project plan for the new website design when your company announces that it is selling off one of your major divisions and it will become a new company. Which of the following is NOT a way in which your project is likely to be affected?

Your project budget will be moved to the new company. (The scenario does not state you are part of that division, so you will not be moved to the new company. - The website requirements will need to be updated. - Work already completed will need to be redone. - The project will be put on hold.)

You have moved into executing the project plan for the new website design when your company announces that it is merging with another company. Which of the following is NOT a way in which your project may be affected?

Your project implementation date will be moved up (earlier). (If there is an effect on time from the merger, it would extend the schedule, not decrease it. - You will have new stakeholders and may need to update the requirements. - You may have a new sponsor who will want to make changes in your direction. - You will likely have new team members from the newly acquired company.)

Paperwork is not being signed in the correct order,to fix this you should

document routing

Two team members are arguing over two different approaches to complete a task. The project manager listens to both sides, determines neither approach will work, and directs the team members to use a third option.This type of conflict resolution is known as:

forcing

A project manager wants to create a tool for the sponsor and senior management to review the health of the project quickly. The tool should have the following features: It should be user-friendly, with a visually-appealing design. It should be easily customized to match the demands of the users. It should be accessible on a variety of interfaces, including full-screen monitors and mobile devices. A user should be able to decipher the information in a few seconds. What is this tool called?

Dashboard

The project sponsor has asked to see a simple summary of the project status, with as little text as possible. Ideally, the report should have colored graphical indicators that provide at-a-glance identifiers of schedule and cost. What type of report is this?

Dashboard

What is another name for a graphical summary of project measures that is used for a quick status check of a project?

Dashboard

You are three months into a six-month project and the sponsor informs you that senior management has required that all projects' costs be cut by 10%. Which of the following is NOT an option?

Decrease the duration of the project by having hourly workers work overtime. (- Increase the duration of the project by using less skilled, lower cost resources - Decrease the scope of the project by removing features not already started - Change the schedule to eliminate the need to pay overtime to overallocated resources)

The project charter is created during Initiation. What does the charter not do?

Define the scope

The bridge over the Troubled Waters stream project will involve Public Works Dept. staff and several vendors. The project manager needs the communication plan to be complete and to be understandable by all. Which of the following should be included in a communication plan?

Definitions of communication terms

What best describes WBS?

Deliverable-oriented and hierarchical in nature

Construction of the mayor's new home is well underway, and the external walls and roof are on and it is time for the plumbing and electrical work to begin. Will's Water and Watts is the contractor for this work, and the plumber has arrived on-site. The electrician is on another job for the day. There is no requirement that one trade begins work before the other, so the plumber starts while the electrician is on the other job. Which type of dependency is this?

Discretionary

A project team member has identified a change that must be made to the project's product to meet one of its requirements. What should be the next step that this team member should take?

Document the change

You are working on moving the in-house Human Resources Management System (HRMS) to a cloud self-service provider. The Vice-President of Human Resources has submitted a change request. What is the previous step in the process?

Document the change

You are working on the installation of a new Customer Relationship Management (CRM) system and the marketing manager has submitted a change request. What is the previous step in the process?

Document the change

The manager of the TailSpin Toys robotic cat laser project has just learned that a subject matter expert has resigned. This person is the country's leading expert on artificial intelligence programming of robotic lasers. The schedule is in jeopardy. What is the first thing the project manager should do?

Document the resignation in an issue log

Which of the following is the best description of what a Project Management Office (PMO) controls?

Documentation, policies, and reporting

You are two months into the conversion to a new purchasing system project and you have discovered that several of the deliverables have errors. You need to update the sponsor on the progress. What communication method would you use for this conversation?

Email

You are working on a new purchasing system project and you have finished with your draft project management plan. You want to get input and possible corrections from the team and other stakeholders, many of whom are scattered in different geographical locations across the country. Which of the following communication methods would be best to use?

Email

You are working on an update to the corporate website and project execution has started. The marketing manager has a change request that needs to get approved. What is the best method for sharing this document with you?

Email

You are working on a new purchasing system project and are getting ready to start executing the project. The Project Sponsor prefers summary level information presented visually, while the team prefer details. Which of the following is the most appropriate way of sharing status with the Project Sponsor and team members?

Email a Status Dashboard Report with color-coded summary status to the Project Sponsor and team and provide links to a detailed schedule and issue log.

You are working on an update to the corporate website and project execution has started. One of your team members has a printed document that needs to be shared with all the team members. What is the fastest media for sharing this document?

Email a picture

You are working on an external contract project to update the operating system on more than 1000 computers at an organization. There is a chance that the organization will hire you to also upgrade the office productivity software, so you ask your sales department to schedule a meeting with your client. This is an example of which type of response strategy?

Enhance

The Coho Winery automated wine-bottle filling station project is in the Planning phase, and the project manager has started to write the communication plan. Which of the following is a succinct definition of the plan's purpose?

Ensuring that the right people receive the right information in the most appropriate format at the right time

You are four weeks into a six-month project and the company announces a hiring freeze on all full-time and contract positions. This is an example of a change to your project's:

Enterprise Environmental Factors (EEFs)

Which of the following terms is used to describe issues that can influence the process of planning procurements, such as market conditions and supplier information?

Enterprise environmental factors

You are working on a project to upgrade the Human Resources Management System (HRMS). You are going to be using a new in-house server that is being installed as its own project. Which of the following is the type of constraint this places on your project?

Environmental

As a project progresses, changes can result in a revised final cost estimate and, hence, a change in the budget. The Earned Value Management methodology has a name for this revised estimate. What is it called?

Estimate at Completion (EAC)

A project scheduler has asked a new hire on the team to estimate activity resources for the project. Which task is related to this process?

Estimating the type and number of resources required to complete activities

The deadline to respond to the RFP has expired while still in the execution phase. . You should then

Evaluate and choose a seller response.

You are working on moving the in-house Human Resources Management System (HRMS) to a cloud self-service provider. One of your team members has submitted a change request. What is the next step in the process?

Evaluate impact and justification

You are working on the installation of a new Customer Relationship Management (CRM) system and the marketing manager has submitted a change request. What is the next step in the process?

Evaluate impact and justification

The project manager has just learned that a key resource is being assigned to a higher priority project at a critical point in the project. Which option should the project manager pursue to minimize the impact of the transfer?

Evaluate the impact of the transfer on the project and meet with the project sponsor.

The sponsor informs the project manager that something else needs to be added to the scope statement in the execution phase. The project manager should

Evaluate the impact on the project.

In which phase of a project are virtual teams used?

Executing

The project manager is starting to assign people to specific roles on the project. One person immediately comes to mind as the perfect candidate for lead database designer, and that person is quickly assigned to the project. In which phase of the project lifecycle did this happen?

Executing

In which phase of a typical project are most of the expenses incurred?

Execution

You are developing a new product for a client and you are trying to decide which of a variety of options has the lowest overall cost or largest income. Which risk technique should you use?

Expected Monetary Value (EVM)

(certiology practice Test 2 PK0-003) In status meeting a positive project risk is identified that can be controlled. You should

Exploit

You are working on an external contract project to update the operating system on more than 1000 computers at an organization. The contract provides a bonus for finishing the work within two months, so you hire additional workers to push for that two months' timeframe. This is an example of which type of response strategy?

Exploit

The mayor's new home is almost finished, and it is time to schedule the housing department inspection prior to receiving the Certificate of Occupancy. The building inspector is out of town until next Thursday, and the mayor will not be able to move in until Friday at the earliest. Which type of dependency is this?

External

You are working on a project to upgrade the enterprise resource planning (ERP) system, which includes a purchasing system and a new sales system. During the original risk planning, there was concern that the new system will not be implemented in time to meet the July demand for Halloween candy orders, which is historically your biggest sales season. Your implementation date was set to June 15th. It is now March and you have learned that your largest competitor has gone bankrupt. What type of risk is this new risk?

External

You are working on a new purchasing system project and you are developing the communication plan. You are planning to select a vendor for the package and will host a bidders' conference that all potential bidders must attend. What media would you plan to use for holding the bidders' conference?

Face-to-face

You are working on a new purchasing system project and you are developing the communication plan. You are planning to select a vendor for the package. What media would you plan to use for the closing meeting?

Face-to-face

You are working on the project plan for a new website design project and you are finalizing the communication plan. Which of the following is not considered a communication trigger?

Face-to-face meetings

Which of the following is NOT considered a barrier to effective communication?

Feedback (Feedback is an important aid in communication. receiver should always provide feedback to the sender. - Language - Distance - Personal preferences)

A balanced scorecard is comprised of four components. What are they?

Financial perspectives, internal business process perspectives, customer value perspectives, and learning and growth perspectives

(4.1 Part 2) Coho Winery has designed a new automated wine-bottle filling station. As bottles pass along the conveyor belt, they are filled then capped. At the end of the filling station, a person removes the bottles and places them in cartons. The quality engineer randomly opens filled cartons in the warehouse and sees that a small percentage of the bottles are broken. He or she has determined that the breakages could be due to faulty glass, conveyor problems, the capping process, or operator errors. Which tool would he or she use to narrow down the source even further?

Fishbone diagram

A project team is trying to find the cause of a malfunctioning process to fill bottles of water that are moving along a conveyor belt. They have identified the following categories and contributors to each category: (see image) Which tool are they using?

Fishbone diagram

During product testing, the team identifies a problem and needs to trace it back to its root cause. Which quality tool would they use?

Fishbone diagram

What is another name for an Ishikawa diagram?

Fishbone diagram

Fabrikam has entered into a contract with AdventureWorks Cycles to manufacture components for the new high-speed braking system. Of the three basic types of contracts—fixed-price, cost-reimbursable, and time-and-material—which type has the most risk for the vendor, Fabrikam?

Fixed-price

The project manager is meeting with the external client for a project and confuses the client by using the term "slack" when referring to an activity. The client interprets this as loose or sloppy. What is another name for slack in the project management context?

Float

You are managing the conversion of an in-house payroll system to a cloud-based system and are identifying the potential risks. You think that several risks might arise from missing steps in the conversion process. Which of the following is the best technique to look for these gaps?

Flow chart

When handling multiple changes on a project, which of the following would be the BEST format in which to inform the team?

Follow the communication plan

You are in a meeting with a stakeholder and are asked to describe the project scope. The stakeholder is asking you:

For all the work you are including in the project

Your order of a new laptop computer arrives two weeks late because of a hurricane that partially destroyed the vendor's shipping facility. What is the correct term to describe the concept that will address this situation?

Force majeure

Two team members have concluded that documentation is not required due to the size of the current project. The project manager has encouraged them to align strictly within the process.Which of the following conflict resolution techniques has the project manager utilized?

Forcing

Which conflict resolution method produces only a temporary solution to the problem?

Forcing

During which stage of team development is conversation relatively unstructured but the manager plays a dominant role?

Forming

In which of the following team development stages would the project manager MOST likely determine the structure of the project team?

Forming

(1.8) Teams go through an evolutionary process as they become more developed. What are the steps in this process?

Forming, storming, norming, performing, adjourning

In which organizational structure does the project manager have the least authority?

Functional

You are working on a project to install a new enterprise resource planning (ERP) system, which includes a Customer Resource Management (CRM) component. The system selected needs to store at least 10,000 customers. This is considered which type of requirement?

Functional

You are working on a project to upgrade the Human Resources Management System (HRMS). The new system must be able to store an individual's training history. Which of the following is the type of requirement this adds to your project?

Functional

In a functional organization, to whom do project resources report?

Functional manager

Which of the following controls resources and manages a business unit?

Functional manager

Which of the following is NOT a likely resource to be allocated to an information technology project?

Functional manager. (functional will not be assigned to a project team, but will provide HR to the PM. - Project manager - Conference room - Network administrator)

In a weak matrix organization, who has more power?

Functional managers

Who manages the resources in a matrix organization? (1.5)

Functional managers

You work in an environment where both you and your team members report to functional managers, and work on projects when you are available. This means that you work in a(n):

Functional organization

You are working on a project to upgrade the enterprise resource planning (ERP) system, which includes a purchasing system and a new sales system. The project will take nearly a year, and three months in, management implements across the board budget cuts of 10%. This is an example of what type of change?

Funding change

You are working on a six-month project to redesign the corporate website and add product purchasing functionality. You are two months in when you get a $20,000 grant toward the project. This is an example of what type of change?

Funding change

You are working on a six-month project to upgrade the operating systems on more than 4,000 corporate computers. You have completed less than half when the vendor increases the cost of each copy. This is an example of what type of change?

Funding change

You are working on moving the in-house Human Resources Management System (HRMS) to a cloud self-service provider. One of your team members submitted a change request that will increase the project budget by 15%. This is an example of what type of change?

Funding change

A client has requested a three-week delay in the order-entry system project due to unanticipated hardware issues at their headquarters' office. The project manager has incorporated the delay into the project management plan. In which document will the delay be best shown?

Gantt chart

A project manager is entering the names and durations of a project's activities into a document. When completed, the document will show how all of the activities are related to each other and when the project will end. What is the name of this document?

Gantt chart

A project manager needs to show planned and actual information about a project's activities in a graphical format. Which of the following is the correct choice?

Gantt chart

The project manager and IT department manager are meeting to discuss the names of three IT resources who would best fill the needs of the project. Which document will help them make a decision?

Gantt chart

The project manager of the order-entry project has been reassigned, and a replacement took over the project this morning. He or she is meeting with the team and wants to review the schedule, with a focus on the details of what has been accomplished and what still needs to be done. Which of the following would accomplish this best?

Gantt chart

Which schedule format depicts the duration of a task as a horizontal bar and shows the task's predecessors and successors?

Gantt chart

The manager of the TailSpin Toys robotic cat laser project needs to have a very thorough discussion of the project schedule in the next status meeting because a number of important milestones are behind schedule. Which type of schedule would be used for this meeting?

Gantt chart showing all activities

You are executing the project plan for a new Point of Sale system for your retail stores and the Steering committee has given you the go ahead to move forward to installation of the software and equipment. You inform the team. What was the trigger for this?

Gate reviews

You are executing the project plan for a new payroll system and following your communication plan. Which of the following is not a communication trigger for communicating with the sponsor?

Gate reviews

You are finalizing a contract with a vendor for development of your new website and have a few remaining questions. When you contact the local vendor representative you've been dealing with, which of the following would you not need to consider?

Geographical considerations

You are working on a new purchasing system project and are getting ready to start executing the project. Which of the following is an advantage of printing and distributing the project plan?

Gives stakeholders a sense of legitimacy about the content

TailSpin Toys is a company that manufactures eccentric playthings. Its projects typically consist of three major phases: design, build, and test. At the end of the design and build phases, a decision is made whether to move on to the build and test phases, respectively. What is this process called?

Governance

The manager for the Awesome Computers wireless network upgrade project has asked the scheduler to pay particular attention to the project's quality gates. The scheduler just began work on the project, but has experience with governance gates from other projects and does not know if the two types of gates are the same. What is the difference, if any, between governance gates and quality gates?

Governance gates, also called phase gates, apply to all types of projects. Quality gates apply to software development projects.

The management of Trey Research has seen a number of complex projects finishing late during the last year, and it is affecting profits and upsetting clients. Which tool can they use to reduce the number of late projects?

Governance-gate reviews

You are working on a new purchasing system project and you are developing the communication plan. The new system will affect how clients place their orders. What media would you plan to use for explaining to them the new process?

Hard copy instructions

__ Is in the project charter

High level plan

Awesome Computers makes peripherals for desktop and laptop computers and is considering a project to develop a new PowerPoint slide advancer that will have several features not available in the marketplace. The project is still in the Initiation phase, and senior management is anxious to move forward before a competitor introduces its product first and grabs a significant share of the market. If this happens, Awesome will cancel the project and potentially lose significant money. What does this situation demonstrate?

High-level risk

Risk management is a critical activity in managing projects. During the Initiation phase of the project, what type of risks are identified?

High-level risks

In the Initiation phase of a project, the project team creates a document that lists the major work to be done, with no details about each of the components. What is this document called?

High-level scope definition

A quality control engineer has collected the following data about a malfunctioning printer: (see image) The engineer needs to see the data graphically and plans to use bars to represent the number of occurrences for each malfunction. Which type of chart will be used?

Histogram

You are working on moving the in-house Human Resources Management System (HRMS) to a cloud self-service provider. One of your team members submitted a change request that will increase the project budget by 15%. You consult the change control plan to see who needs to approve project cost changes of 15%. What process are you performing?

Identify approval authority

You are working on moving the in-house Human Resources Management System (HRMS) to a cloud self-service provider. One of your team members submitted a change request and you have evaluated its impact and justification. What is the next step in the process?

Identify the approval authority

You are working on the installation of a new Customer Relationship Management (CRM) system and the marketing manager has submitted a change request. You have evaluated its impact and justification. What is the next step in the process?

Identify the approval authority

(3.4 part 1) You are working on moving the in-house Human Resources Management System (HRMS) to a cloud self-service provider. The change request submitted by the Vice-President of Human Resources has just been validated. What was the previous step in the process?

Implement the change

You are working on moving the in-house Human Resources Management System (HRMS) to a cloud self-service provider. The Vice-President of Human Resources has submitted a change request that has been validated. What was the previous step in the process?

Implement the change

You are working on the installation of a new Customer Relationship Management (CRM) system and the change request submitted by the marketing manager has just been validated. What was the previous step in the process?

Implement the change

Your Change Control Board (CCB) has approved a change to the scope of your project. What is the next step in the process?

Implement the change

You are working on the project plan for a new website design project and you are finalizing the communication plan. Which of the following is not considered a communication trigger?

Impromptu meeting

What is the difference between a merger and an acquisition?

In a merger, the companies are equals, but in an acquisition, the acquiring company is in control.

You are working on a new purchasing system project and are getting ready to start executing the project. A large number of the project team is located in a different location. Which of the following is NOT an appropriate way of holding a status meeting?

In person

You are working in an organization where you and your team were all hired for the duration of the project. You report to the head of the corporate Project Management Office (PMO) and your team members report to you, but none of you are guaranteed a job after the project ends. Which of the statements below is NOT a reason that the organizational structure matters to you and your project?

In projectized organizations, project managers earn more money. (Projectized or not, the organizational structure has no effect on a project manager's salary. - In functional organizations, functional managers have control over work assignments for team members. - In any style matrix organization, team members report to both functional managers and project managers. - In a projectized organization, project managers are responsible for hiring, firing, promoting, and training their team members.)

A three-point estimate was used to estimate the demolition of the old bridge over the Troubled Waters stream. The most likely duration, eight days, was selected. Extremely bad weather caused the demolition to take 20 days (even longer than the pessimistic duration used in the calculation). Where should this be documented?

In the issue log

Lucerne Publishing Co. is almost ready to publish its new textbook. The special paper should have been received last week, but the supplier has said that equipment problems with the crating machinery have delayed the shipment. There are two more weeks of slack in the schedule, after which the deadline given by Lucerne's client will be missed. Where should Lucerne's project manager document this situation?

In the issue log

You are working on a new purchasing system project and you are having difficulty finalizing the requirements with the purchasing department. You run into the purchasing manager and two purchasing clerks in the break room and ask them to clarify the outstanding items. What type of meeting is this?

In-person impromptu

You are working on a new purchasing system project and you are having difficulty finalizing the requirements with the purchasing department. You send a meeting notice to the purchasing manager and two purchasing clerks for a 15-minute meeting tomorrow in your office with an agenda of finalizing the requirements. What type of meeting is this?

In-person scheduled

You are executing the project plan for a new Point of Sale system for your retail stores and the testing team has discovered that one of the batches of scanners has defective equipment. You inform the rest of the team that there will be a delay while the vendor ships new scanners. What was the trigger for this?

Incident response

You are six weeks into a four-month project and the sponsor tells you that you must deliver the project a month earlier than originally planned without decreasing the scope. Your only remaining option is:

Increase cost

AdventureWorks Cycles has just replaced its project manager for the high-speed braking system project. The new manager believes strongly in building trust among the team members, and has some good ideas on how to accomplish this. Which of the following is the strongest reason to build trust in a team?

Increased team performance

Which of the following is an advantage of an intranet?

Information can be shared according to the needs of individuals.

What information is contained in a status report?

Information on the present state of the project, usually from the beginning of the project

The term "baseline" is confusing the engineer who is working on the project plan for the Awesome Computers wireless network upgrade project. When are initial baselines set, and when are they changed?

Initial baselines are set when the scope, schedule, and cost have been approved during project planning. They are changed when formal change requests have been approved.

The project life cycle in order is

Initiating→ planning→ executing→ monitoring→controlling→ closing

In what phase should project criteria be determined?

Initiation phase

You are working on installing a new financial system. The first module is installed and you are comparing the general ledger chart of accounts in the new system to the chart of accounts in the old system. You are performing a(n):

Inspection

You are working on a project to upgrade the Human Resources Management System (HRMS). You are going to be using a new in-house server that is being installed as its own project. Which of the following is NOT within the scope of the server project?

Installing the Human Resources Management System (HRMS) (is within the scope of your project, not the server project. - Creating a server backup plan - Training the server administrators - Connecting the new server to the rest of the network servers)

You are finalizing the requirements on your new purchasing system project and you have some follow-up questions for some of the stakeholders. They all work in your building with you, so which of the following would you not need to consider?

Inter-organizational communication patterns

You are working on a six-month project to upgrade the operating systems on more than 4,000 corporate computers in three different countries. Which of the following would NOT be a communication concern?

Inter-organizational communication patterns (Inter-organizational communication patterns are not a consideration because the stakeholders work for your company. - Cultural differences - Rapport building/relationship building - Geography)

You are working on a six-month project to upgrade the operating systems on more than 4,000 corporate computers in three different countries. Which of the following would NOT be a communication concern for holding a kick-off meeting with key stakeholders in each location?

Inter-organizational communication patterns (not a consideration b/c stakeholders work for your company. - Cultural differences - Rapport building/relationship building - Geography)

You are working on a new purchasing system project and are getting ready to start executing the project. You are holding an in-person, face-to-face meeting with the stakeholders to kick things off. Which of the following is the communication method you are using?

Interactive communication

You are developing the project plan for a new Human Resources Management System (HRMS) for your organization. Which of the following is a type of change that you might need to plan for?

Internal reorganization

A new project manager wants to do some research regarding project management tools, templates, and best practices that are not available within the organization. Which of these would be the best source to look at?

Internet sites

You are finalizing a contract with a vendor for development of your new website and have a few remaining questions. When you contact the vendor representative you've been dealing with, which of the following would you not need to consider?

Intra-organizational communication patterns

An engineer on the TailSpin Toys robotic cat laser project is confused about issues and risks and wants to use the correct term. Which of these statements best describes issues and risks?

Issues and risks are different, and they should be managed differently.

The project manager for the WingTip Toys mini-drone project has been asked why he or she would use a lead in a project plan. When a lead occurs in an activity, what is its effect upon other activities?

It accelerates a successor task.

The new project manager of the WingTip Toys mini-drone project is starting to write the charter and wants it to be complete. Which of the following characteristics does the project charter possess?

It authorizes the start of work on the project.

A project manager has decided to level the resources on a project. Which of the following is NOT an advantage of resource leveling?

It can delay the finish date of the project. (Resource leveling can delay the finish date of a project; this is a disadvantage. - It can minimize overtime charges. - It results in a maximum number of work hours each day for a resource. - It shows when a resource might not be fully allocated to work on the project.)

The town finance manager is reviewing the plan for the Public Works Department's bridge over the Troubled Waters stream before allocating funds to it. The plan contains a number of milestones, and the finance director does not know what they signify. Which of the following about a milestone is correct?

It can indicate the beginning or completion of a significant point in the project.

Which statement about a scatter chart is not true?

It consists of time plotted on the horizontal axis and another variable plotted on the vertical axis.

The project scheduler is planning the relationship between two activities and knows that one will lag the other by two days. What effect will this lag have upon other activities?

It delays the start of a successor activity.

(certiology practice Test 1 PK0-003) As the project manager you should formally close a project when

It has been terminated unexpectedly

The Public Works Department's bridge over the Troubled Waters stream project has a number of activities that are on the critical path. Which statement is true about the critical path?

It has zero total float.

What is the primary benefit of having the team create a Work Breakdown Structure (WBS)?

It helps attain buy-in from the project team members during project execution.

The project manager of the WingTip Toys mini-drone project can either estimate activity durations himself or herself or have them estimated by members of the project team. Which is the most significant benefit of having team members involved in this?

It helps attain buy-in from the team.

You are working on a new purchasing system project and are getting ready to start executing the project. What is the best reason to hold the kick-off meeting in person?

It helps team members get to know one another so they feel comfortable interacting throughout the project.

Which of the following statements is not true about the Initiation phase of a project?

It identifies the type of contract that is part of the procurement plan.

Which of the following statements about administrative closure of a project is not true?

It includes closing contracts and resolving disputes with vendors.

Which is true of using project intranets for communication?

It is an effective way to provide information to a variety of users.

A summer intern is working on the Coho Winery wine-bottle filling station project and is learning all he or she can about project management. Which of the following statements is not true about a project management plan?

It is approved by all of the stakeholders.

You are working on a new purchasing system project and are getting ready to start executing the project. Which of the following is a disadvantage of printing and distributing the project plan?

It is expensive to print and distribute, especially if it requires an external paid mail service.

The Project Management Office (PMO) has published a set of Key Performance Indicators (KPIs) that each project within the organization must use when preparing its monthly status reports. Is this necessary, and if so, why?

It is necessary so PMO analysts can compare the performance of the projects using a consistent set of tools.

Which of the following statements is NOT true about a project? (certmaster 1.1)

It is strategic to the company. (project not always undertaken for strategic reasons, and many are "ordinary." example is development of new staff recruiting manual. - It is unique, and has never been done before. - It creates a product or service. - It is progressively elaborated.)

The project team for the WingTip Toys mini-drone project is using bottom-up estimating to build a schedule. Which of the following is not an advantage to the project if they use this type of estimate?

It is time-consuming to create.

Which of the following is a valid reason to create a transition plan?

It provides training to the recipients of the transition plan.

Which of the following is the key characteristic of the WBS?

It represents the entire scope of work for the project

You have moved into executing the project plan for the Customer Resource Management (CRM) system and your company just announced it is outsourcing all the Information Technology work to a vendor. What will likely happen to your project?

It will be outsourced with the rest of the Information Technology work.

You have moved into executing the project plan for the Customer Resource Management (CRM) system and the vendor you selected has split its company into two organizations. What will likely happen to your project?

It will continue with a contract with the new company.

You have moved into executing the project plan for the cloud-based (SaaS) Customer Resource Management (CRM) system and your company announces that it is consolidating data centers into a new location in Topeka, KS. How will this likely affect your project?

It will not affect the project.

A milestone is defined as a significant point or event in a project. Which of the following represents a milestone in an Agile project? (1.7)

Iteration review

Another higher priority project has been started that requires the highly skilled resources assigned to your project. They will not be available to you for two weeks. Which of the following is NOT an option for your project?

Keep the resources working on your project. (- Continue working on the project tasks not being performed by those resources - Postpone the current project until the resources are available - Hire temporary resources to continue the work of the reassigned resources)

KPI means

Key Performance Indicator

A project sponsor wants to know how a project is performing without reading detailed reports. He or she asks the project manager for an end-of-month tabulation of the following data: What is the term for this information?

Key Performance Indicators (KPIs)

It is the end of April, and the project manager posts information about what the project accomplished during the month. This data includes the number of milestones completed, work-hours expended, costs incurred, and the percentage of activities completed in the month. These values can be grouped into what tool?

Key Performance Indicators (KPIs)

A fictional U.S. government military department is evaluating whether to purchase a new mini-microwave laser targeting device from a contractor. The government acquisitions office has specified cost, schedule, and operational thresholds that must be met before the purchase contract can be signed. Parameter values below any of these thresholds will result in the contractor's proposal being removed from consideration. What are these thresholds called?

Key Performance Parameters (KPPs)

Which of the following tools is used exclusively by the U.S. government?

Key Performance Parameters (KPPs)

You are working on a new purchasing system project and are getting ready to start the executing phase. You call a meeting with your key team members to review the schedule, tasks, and project expectations. This is called a(n):

Kick-off meeting

The client accepts the critical design review.Which of the following meetings should be held to move to the NEXT step in the project?

Kickoff

You are working on the project plan for a new website design project and you are finalizing the communication plan. Which of the following is not considered a communication trigger?

Language

You are working on a new purchasing system project and are getting ready to end the project by holding a closing meeting. What is the major deliverable of this meeting?

Lessons learned document

TailSpin Toys and WingTip Toys are considering whether to join together to produce an educational math game for three-to- six-year-old children. The CEO of TailSpin has written to the WingTip CEO with suggested business terms for their project. What is this communication called?

Letter of intent

Two companies are discussing whether to join forces to pursue a Request for Proposal (RFP) that neither has the capability to respond to alone. There are several steps in this process; which order is correct?

Letter of intent, non-disclosure agreement, Memorandum of Understanding (MOU)

During the Planning phase of a project, the team prepares a schedule of the work needed to complete the project's objectives. What does this schedule consist of?

Linked activities with planned start and finish dates, durations, milestones, and assigned resources

The project manager is evaluating a change request that appears warranted, but it will result in a large impact to the scope. What should the project manager do next?

Look for alternatives that might have less impact on the scope

You are working on a new purchasing system project and are getting ready to start executing the project. Which of the following is not an advantage of printing and distributing the project plan?

Low-cost way of broadcasting a message to a large number of people simultaneously

You are working on an update to the corporate website and project execution has started. One of your remotely-located team members has a hard-copy book they wants to share with you. What is the best method for sharing this document?

Mail

What step will a project manager take to help prevent cash flow problems?

Make efforts to engage the finance department to put in place a cash flow forecast

TailSpin Toys has four web designers who routinely work on several projects (A, B, and C) at the same time. A designer on Project A has been under pressure from the manager of Project B to devote more time to Project B because it is behind schedule. Select the best option to address this situation.

Managers of Projects A and B should meet to resolve the problem.

Lucerne Publishing Co. is getting ready to distribute a new textbook. The books cannot be bound until they have been printed. Which type of dependency does this represent?

Mandatory

One deliverable of the Awesome Computers wireless network upgrade project is a new server. It has been delivered and is awaiting the next steps. After the server has been configured for the project, it will be tested. Which type of dependence does this represent?

Mandatory

The Lucerne Publishing Co. is finishing a textbook and knows that it must be printed before it can be bound. Which type of dependency does this represent?

Mandatory dependency

A project manager is in a meeting with the company's external client and states that he or she will need to level the resources on the project. Choose the appropriate task the project manager is referring to.

Manually determining where to adjust resources

In which type of organization does the authority of the project manager range from weak to strong?

Matrix

On a large engineering project, people have been complaining about reporting to more than one person. They have said that these people seem to have two differing agendas. Which type of organization are these workers in?

Matrix

TailSpin Toys is in the planning phase of its educational math game for 3- to 6-year old children. One of the activities will involve testing the final deliverable by a small group of children, and the duration of this activity has been estimated at two weeks. Which of the following tools would NOT be used when determining the duration of an activity?

Maximum likelihood estimating. (statistical method. - Three-point estimating - Analogous estimating - Parametric estimating)

You are working on a new purchasing system project and you are having difficulty finalizing one of the deliverables with the vendor you've selected. You need to get the problems resolved quickly or you may miss a milestone. What is the best approach to get the issues fixed?

Meet face-to-face

You are working on a new purchasing system project and you are having difficulty finalizing the requirements with the purchasing department. You suspect that the purchasing manager has some concerns that are not being voiced and you want to meet to discuss things. What is the best approach?

Meet face-to-face


Ensembles d'études connexes

Intro to Criminal Justice Chapter 3

View Set

Chapter 8: Cognition and Perception

View Set

HESI/Saunders Module 7: Basic Care and Comfort

View Set