159 Information Tech Project Manager Chapter 5
_____ refer to "conditions or capabilities that must be met by the project or present in the product, service, or result to satisfy an agreement or other formally imposed specification."
Requirements
Creating the _____ involves subdividing the major project deliverables into smaller, more manageable components.
WBS Work Breakdown Structure
Subdividing the project deliverables into smaller pieces is known as _____.
decomposition
Some organizations prescribe the form and content for WBSs for particular projects. These are known as _____.
guidelines
_____ is a technique that uses branches radiating out from a core idea to structure thoughts and ideas when creating a WBS.
mind mapping
The main outputs of scope definition are the _____ and project document updates.
project scope statement
The _____ includes the approved project scope statement and its associated WBS and WBS dictionary
scope baseline
_____ involves controlling changes to the project scope while keeping project goals and business strategy in mind.
scope control
PMI uses the term "_____" to describe each level of work in the WBS.
task
_____ is the difference between planned and actual performance.
variance