Project Time Management - Chapter 6
A black diamond: a milestones Thick black bars: summary tasks Lighter horizontal bars: durations of tasks Arrows: dependencies between tasks
Gantt Chart Symbols
Resource breakdown structure
Hierarchical structure that identifies the project's resources by category and type
Sequencing activities
Identifying and documenting the relationships between project activities
Mandatory dependencies
Inherent in the nature of the work being performed on a project, sometimes referred to as hard logic
External dependencies
Involve relationships between project and non-project activities
Activity definition
Involves developing a more detailed WBS and supporting explanations to understand all the work to be done so you can develop realistic cost and duration estimates
Sequencing activities
Involves reviewing activities and determining dependencies
Specific Measurable Assignable Realistic Time-framed
Milestones should be
Critical Path Method
Network diagramming technique used to predict total project duration
Crashing
Obtaining the greatest amount of schedule compression for the least incremental cost
Resources
People, equipment, and materials
Slide 19 - look for bursts and nodes
Process for creating AOAs
empowerment incentives discipline negotiation
Project managers should use
Gantt Chart
Provide a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a calendar format
Activity attributes
Provide more information such as predecessors, successors, logical relationships, leads and lags, resource requirements, constraints, imposed dates, and assumptions related to the activity
Expert judgement, analytical techniques, and meetings
Schedule management plan inputs
Network diagram
Schematic display of the logical relationships among, or sequencing of, project activities
Milestone
Significant event that normally has no duration; useful for setting schedule goals and monitoring progress
Meyers-Briggs
Slide 5
Free slack/float
The amount of time an activity can be delayed without delaying the early start of any immediately following activities
Total slack/float
The amount of time an activity may be delayed from its early start without delaying the planned project finish date
Slack/float
The amount of time an activity may be delayed without delaying a succeeding activity or the project finish date
Critical Path
The series of activities that determines the earliest time by which the project can be completed; the longest path and has the least amount of slack
Arrow & Precedence Methods
Two main forms of network diagrams
Schedule issues
What are the main reason for conflicts on projects, especially during the second half of project?
PERT and Monte Carlo simulations
What are three-point estimates needed for?
Delivering projects on time; because time has the least amount of flexibility
What do managers often cite as one of their biggest challenges? Why?
Slide 9
What does a schedule management plan include?
The activity name An activity identifier/number A brief description of the activity
What does the activity list include?
dependencies
You must determine ____________ in order to use critical path analysis
Theory of Constraints
a management philosophy developed by Eliyahu M. Goldratt and introduced in his book The Goal
Feeding buffer
additional time added before tasks on the critical path
Project buffer
additional time added before tasks on the critical path
Buffer
additional time to complete a task
Probabilistic time estimates
duration estimates based on using optimistic, most likely, and pessimistic estimates of activity durations, or a three-point estimate
Defining activities
identifying the specific activities that the Project team members and stakeholders must perform to produce the project deliverables
Duration
includes the actual amount of time worked on an activity plus elapsed time
Effort
is the number of workdays or work hours required to complete a task
PERT
network analysis technique used to estimate project duration when there is a high degree of uncertainty about the individual activity duration estimates
Dependency/relationship
sequencing of project activities or tasks
Murphy's Law
states that if something can go wrong, it will
Parkinson's Law
states that work expands to fill the time allowed
Activity/task
An element of work normally found on the WBS that has an expected duration, cost, and resource requirements
-Adding more resources or changing scope -Crashing -Fast Tracking
3 main techniques for shortening schedules
- Finish-to-Start - Start-to-Start - Finish-to-Finish - Start-to-Finish
4 types of Task Dependencies
Critical change scheduling
A method of scheduling that considers limited resources when creating a project schedule and includes buffers to protect the project completion date
Activity list
A tabulation of activities to be included on a project schedule
Arrow Diagramming Method (ADM) Activity-on-Arrow (AOA)
Activities are represented by arrows; nodes or circles are the starting and ending points of activities; can only show finish to start dependencies AKA?
Precedence Diagramming Method (PDM)
Activities are represented by boxes; arrows show relationships between activities; more popular than ADM method and used by project management software; better at showing different types of dependencies
Three-point estimate
An estimate that includes an optimistic, most likely, and pessimistic estimate; such as three weeks for the optimistic, four weeks for the most likely, and five weeks for the pessimistic estimate
Developing the schedule
Analyzing activity sequences, activity resource estimates, and activity duration estimates to create the project schedule
Resources
Before estimating activity durations, you must have a good idea of the quantity and type of ________ that will be assigned to each activity
Controlling the schedule
Controlling and managing changes to the project schedule
Discretionary dependencies
Defined by the project team; sometimes referred to as soft logic and should be used with care since they may limit later scheduling options
Forward pass
Determines the early start and finish dates through the network diagram
Backward pass
Determines the late start and finish dates
Planning schedule management
Determining the policies, procedures, and documentation that will be used for planning, executing, and controlling the project schedule
Fast Tracking
Doing activities in parallel or overlapping
Duration
Effort does not normally equal ________
Estimating activity resources
Estimating how many resources a project team should use to perform project activities
Estimating activity durations
Estimating the number of work periods that are needed to complete individual activities
Customer sign-off on key documents or completion of specific products
Examples of milestones