Which of the following is false regarding when to use the learning curve?
All processes and items can benefit from or exhibit improvement from learning.
Users apply _____ to projects where there is a single known time for each activity with no variance, while _____ applies to projects where time estimates are variable or uncertain.
CPM...PERT
Which of the following is not a question that value analysis teams should ask to determine if opportunities exist for item, product, or service improvement?
Can we use a different color of paint?
A/An _____ visually displays the tasks and times associated with a project and consists of a horizontal bar chart with activities listed vertically and times or dates displayed horizontally.
Gantt chart
Which of the following is not one of the network rules for PERT/CPM?
Networks start and finish at multiple events.
In a PERT network, which of the following is not one of the times shown?
On time start.
Which of the following is not one of the six phases of a project?
Precompletion
_____ is a tool that reduces processes to their component parts or activities and helps identify and then eliminate non-value-adding activities (waste) or delays within a process.
Process mapping
_____ is a technique used to examine the incremental costs between quantities within a supplier's price quotation.
Quantity discount analysis
Which of the following is not one of the critical steps to process mapping?
Utilize all sequential activities whenever possible as concurrent activities are wasteful.
_____ techniques are primarily applied to existing products and services, while _____ is the application of value principles during product or service design.
Value analysis....value engineering
A/An _____ consists of activities or steps that can be performed at the same time during the main flow of work.
concurrent process
In a PERT network, a/an _____ is the earliest time a project can finish given the expected activity time.
early finish
In a PERT network, a/an _____ is the earliest point in time an activity can begin.
early start
All of the following are characteristics of the postcompletion phase of a project except _____.
identify broad budget, personnel, and resource requirements
In a PERT network, a/an _____ is the latest time an activity can finish without delaying the entire project.
late finish
In a PERT network, the difference between the _____ and the _____ is slack.
late finish....early finish
In a PERT network, a/an _____ is the latest point in time an activity can begin without delaying the entire project.
late start
In a PERT network, the difference between the _____ and the _____ is slack.
late start....early start
[A/An] _____ establishes the rate of improvement due to learning as producers realize direct-labor cost improvements as production volumes increase.
learning curve
The term _____ applies to the average direct labor required to produce a unit of output in the short run, while the term _____ refers to the longer-term factors of production that systematically reduce production costs.
learning curve....experience curve
When referring to learning improvement, the _____ represents a reduction in the cumulative average number of labor hours as production doubles from a previous level.
learning rate
The _____ (in time) through a PERT network is the _____.
longest path....critical path
All of the following are points that should be considered before initiating a project except _____.
measure subjectively
A/An _____ is a series of tasks that require the completion of specific objectives within a certain time frame; has defined start and stop dates; consumes resources, particularly time, personnel, and budget; and operates with limited resources.
project
A _____ is one in which the set of steps or activities comprising the activity occur one after the other.
sequential process