exam one study guide cts
Project quality management
Which project management knowledge area ensures that the project will satisfy the stated or implied needs for which it was undertaken?
Project Communications Management
Which project management knowledge area primarily involves generating, collecting, disseminating, and strong project information?
Project organization
Which section of the project management plan includes external interfaces, internal structure, as well as roles and responsibilities?
Schedule
Which section of the project plan lists the planned dates for completing key deliverables?
Change control system
Which term is used for a formal, documented process that describes when and how official project documents may be modified, the people authorized to make modifications, and the paperwork required for these changes?
True
Information systems can help an organization support a strategy of being a low-cost producer.
False
A Gantt chart is the same as a project management plan.
Project management office
A _____ is an organizational group responsible for coordinating the project management function throughout an organization.
Team Charter
A _____ is usually not necessary to the Scrum method, because Scrum implies that team members work as a self-directed group.
Project
In a _____organizational structure, program managers, rather than functional managers or vice presidents, report to the CEO. Their staffs have a variety of skills needed to complete all required tasks within their programs.
The degree to which management's decisions take into account the effect of outcomes on employees within the organization
In organizational culture, what does people focus refer to?
Project Integration Management
An organizational process assets update is the output of which closing process?
False
Corrective actions reduce the probability of negative consequences associated with project risks, while preventive actions should result in improvements in project performance.
Resources
Galaxy, a construction company, buys a particular brand of tiles manufactured by Tiles and Floors, an eco-friendly tile manufacturing company. However, Tiles and Floors has declared bankruptcy and closed down. At present, Galaxy is facing a crisis because there are no other manufacturers in the market that supplies eco-friendly tiles. Which constraint is Galaxy currently facing?
True
In project integration management, directing and managing project execution involves carrying out the project management plan by performing the activities included in it.
False
Initiating processes are not required to end a project.
True
Initiating processes take place during each phase of a project.
True
Interface management involves identifying and managing the points of interaction between various elements of a project.
False
Internal stakeholders include groups affected by the project such as government officials or concerned citizens.
True
Kick-off meeting agendas are usually recorded in a Word document.
False
Many projects fail because of unclear requirements and expectations, so starting with a payback analysis makes a lot of sense.
Project environment knowledge
Martha works as a project manager at a bank. Due to certain changes in external factors, Martha needs to make a few alterations in the tactical goals of her project. In such a scenario, which of the following will best help Martha cope with the change?
True
Monitoring and controlling processes overlap all of the other project management process groups.
True
Most colleges and universities have very strong functional organizations.
True
One of the main reasons why project management is challenging is because of the factor of uncertainty.
False
Opponents of a project do not belong to the category of stakeholders.
True
Organizational process asset updates are an important output of the closing process of a project.
False
Project integration management must occur just within the context of a particular project.
True
Project managers and their teams must recognize the effects of any project on the interests and needs of the entire system or organization instead of focusing on the immediate concerns of the project.
buying goods and services for a project from outside the performing organization.
Project procurement management mainly involves:
True
Projects should be developed in increments.
True
Projects that arise as a result of problems and directives must be resolved quickly to avoid hurting an organization's business.
Competitors
Select an example of external stakeholders for an organization.
True
Some organizations initiate projects using a contract in place of a project charter.
True
Standards and guidelines to follow when performing project management must be devised by top management.
the Robinson family
Steve, an engineer in a construction company, is at present working on a home construction project. The home is being built for the Robinson family, the owners of the home. Steve is working with his project team and support staff to ensure the project is completed on time. In such a scenario, the project sponsor is _____.
False
Systems analysis addresses the business, technological, and organizational issues associated with creating, maintaining, and modifying a system.
True
The WBS provides a basis for creating the project schedule and performing earned value management for measuring and forecasting project performance.
Human resources
The _____ frame of an organization focuses on providing harmony between the needs of the organization and the needs of people.
False
The best way to sustain a project is to withhold the required money, human resources, and visibility for the project.
False
The burndown chart is a Scrum created artifact that provides a list of features prioritized by business value.
False
The kick-off meeting is always held before the business case and project charter are completed.
True
The level of activity and length of each process group varies for every project.
False
The nature of hardware development projects is more diverse than software-oriented projects.
Monitoring and controlling
The outputs of which process include change request status updates, project management plan updates, and project document updates?
False
The pre-initiation phase of a project using the Scrum method does not involve project charters, stakeholder management strategy, and kick-off meetings.
True
The same organization can have different subcultures.
False
The team members of a virtual team are all of the same nationality.
False
The two main items for monitoring and controlling in the Scrum framework are the daily Scrum and the sprint retrospectives.
True
To be a successful manager, the only skills an IT project manager needs to possess are excellent technical skills.
Project management plan
What document used to coordinate all project planning documents and help guide a project's execution and control?
Project Management Plan
What is developed in the Project Integration Management knowledge area?
Planning
What is often the most difficult and unappreciated process in project management?
Determine the estimated costs and benefits for the life of the project and its produces
What is the first step in determining the NPV?
Guide project execution
What is the main purpose of project plans?
They provide leadership and direction for project managers heading the projects within a program
What is true about program managers?
Initiating
What process group does the project integration management knowledge area map to through the activities of developing project charters?
Planning
What processes include devising and maintaining a workable scheme to ensure that the project addresses the organization's needs?
Work breakdown structure
What tool provides a basis for creating the project schedule and performing earned value management for measuring and forecasting project performance?
Net present value
What type of analysis involves calculating the expected net monetary gain or loss from a project by discounting all expected future cash inflows and outflows to the present point in time?
When the net cumulative benefits equal the net cumulative costs
When does payback occur?
Hybrid
Which approach to product development is currently used by many organizations so a predictive set of steps is used as an overall means to coordinate more detailed steps that are adaptively managed?
The inspire people to reach goals
Which attribute best defines the role of leaders?
They are designed for especially large projects with multiple users
Which attribute is true of low-end tools of project management software?
Projects are temporary endeavors where as an organization's operations are ongoing in nature.
Which characteristic highlights a difference between projects and operations?
People focus
Which characteristic of organizational culture describes the degree to which management's decisions take into account the effect of outcomes on people within the organization?
Unit Integration
Which characteristic of organizational culture refers to the degree to which departments within an organization are encouraged to coordinate with each other?
Member Identity
Which characteristic of organizational culture refers to the degree to which employees identify with the organization as a whole, rather than with their types of job or profession?
Project management addresses specific, short-term goals whereas portfolio management focuses on long-term goals.
Which goal distinguishes project management and portfolio management?
It uses several iterations or deliveries of software instead of waiting until the end of the project to provide a product.
Which is true about the agile method?
In a strong matrix organizational structure, the project manager controls the project budget and has moderate to high authority.
Which of the following is true of a matrix organizational structure?
Are we investing in the right areas?
Which of the following questions reflects the strategic goals of project portfolio management?
Political Frame
Which perspective on organizations assumes that organizations are coalitions composed of varied individuals and interest groups?
Project Planning
Which process includes defining project scope, benefits, and constraints?
Closing
Which process involves gaining stakeholder and customer acceptance of the final products and services and bringing the project, or project phase, to an orderly end?
Developing the project charter
Which process involves working with stakeholders to create the document that formally authorizes a project?
Deliverable
Which term refers to a product or service, such as a technical report, a training session, a piece of hardware, or a segment of software code, produced or provided as part of a project?
kick-off meetings
Which tool can best help in efficient communication management?
Gantt charts
Which tool is most likely to be used in project schedule management?
Low-end
Which type of tool is usually recommended for small projects and single users?