MIS 4310 Chapter 5

Lakukan tugas rumah & ujian kamu dengan baik sekarang menggunakan Quizwiz!

43. Which is recommended for the creation of a good WBS? a. Any WBS item should be the responsibility of all the people working on it. b. A unit of work should appear at only one place in the WBS. c. Each WBS item should be created assuming that the requirements are inflexible. d. The work content of a WBS item is independent of the WBS items below it.

ANSWER: b

46. Which term refers to the difference between planned and actual performance? a. Decomposition b. Variance c. Scope validation d. Scope creep

ANSWER: b

49. Which process uses highly organized and intensive workshops to bring together project stakeholders—the sponsor, users, business analysts, programmers, and so on—to jointly define and design information systems? a. Prototyping b. JAD c. RAD d. Use case modeling

ANSWER: b

24. Which term describes a product produced as part of a project? a. variance b. scope c. deliverable d. work package

ANSWER: c

9. Many information technology projects also require detailed functional and design specifications for developing software, which also should be referenced in the detailed scope statement.

ANSWER: True

26. Which action involves defining and documenting the features and functions of the products produced during the project as well as the processes used for creating them? a. Collecting requirements b. Defining scope c. Controlling scope d. Validating scope

ANSWER: a

36. Which document should list and describe all of the deliverables required for the project? a. project charter b. scope statement c. WBS d. Gantt chart

ANSWER: b

41. During which approach do team members first identify as many specific tasks related to the project as possible and then aggregate the specific tasks and organize them into summary activities, or higher levels in the WBS? a. analogy b. bottom-up c. top-down d. mind mapping

ANSWER: b

34. What is the main technique used in creating a WBS, which involves subdividing project deliverables into smaller pieces? a. conglomeration b. accumulation c. decomposition d. catalyzation

ANSWER: c

38. Which approach for constructing a WBS involves refining the work into greater and greater levels of detail? a. analogy b. bottom-up c. top-down d. mind mapping

ANSWER: c

39. Which approach for constructing a WBS starts with the largest items of the project and breaks them into subordinate items? a. analogy b. bottom-up c. top-down d. mind mapping

ANSWER: c

42. Mind mapping can be used for developing WBSs using which approach? a. analogy approach only b. bottom-up or analogy approach c. top-down or bottom-up approach d. any approach

ANSWER: c

25. Which statement best describes scope? a. each level of work that is outlined in a work breakdown structure b. end product created as part of a project that is delivered to the client c. tasks that are decomposed into smaller tasks in a work breakdown structure d. work involved in creating the products and the processes used to create them

ANSWER: d

23. Scope creep if not managed well can lead to the failure of information technology projects.

ANSWER: True

1. Scope refers to all the work involved in creating the products of the project and the processes used to create them.

ANSWER: True

12. The scope baseline in a WBS consists of the requirements documentation and enterprise environmental factors.

ANSWER: False

14. A work package represents one component of the product that the project aims to deliver.

ANSWER: False

15. A work package must always represent less than 80 hours of work.

ANSWER: False

16. Given the project management software that is available, it is relatively easy to create a good WBS.

ANSWER: False

17. The tasks in a WBS must be developed as a sequential list of steps.

ANSWER: False

18. The executing tasks of the WBS remain constant from project to project.

ANSWER: False

2. Deliverables are only product-related, such as a piece of hardware or software.

ANSWER: False

21. The format of the WBS dictionary is essentially the same for all projects.

ANSWER: False

44. What is scope creep? a. the tendency for project scope to keep getting bigger and bigger b. subdividing project deliverables into smaller pieces c. the approved project scope statement and its associated WBS. d. a task at the lowest level of the WBS

ANSWER: a

45. What process involves formal acceptance of the completed project scope by the stakeholders? a. Scope validation b. Scope planning c. Scope control d. Scope baseline

ANSWER: a

47. Which process involves developing a working replica of the system or some aspect of the system? a. Prototyping b. Variance c. Decomposition d. Use case modeling

ANSWER: a

27. Which action involves reviewing the project charter, requirements documents, and organizational process assets to create a scope statement, adding more information as requirements are developed and change requests are approved? a. Creating scope b. Defining scope c. Controlling scope d. Validating scope

ANSWER: b

30. Which output documents how project needs will be analyzed, documented, and managed? a. requirements traceability matrix b. requirements management plan c. WBS d. project scope statement

ANSWER: b

31. Which process involves generating ideas by comparing specific project practices or product characteristics to those of other projects or products inside or outside the performing organization? a. variance b. benchmarking c. prototyping d. decomposition

ANSWER: b

35. Which task is at the lowest level of the WBS? a. variance b. objective c. deliverable d. work package

ANSWER: d

5. The project's size, complexity, importance, and other factors do not affect how much effort is spent on collecting requirements for scope planning.

ANSWER: False

7. Project scope statements must include the project boundaries, constraints, and assumptions.

ANSWER: False

8. The scope of a project is clear and specific from the start.

ANSWER: False

10. The project scope statement should reference supporting documents, such as product specifications that will affect what products are produced or purchased, or corporate policies, which might affect how products or services are produced.

ANSWER: True

11. The project management plan, project documents, enterprise environmental factors, and organizational process assets are the primary inputs for creating a WBS.

ANSWER: True

13. The main purpose of the WBS is to define all of the work required to complete a project.

ANSWER: True

19. Many organizations provide different guidelines and templates for developing WBSs.

ANSWER: True

20. Mind mapping allows people to write and even draw pictures of ideas in a nonlinear format.

ANSWER: True

22. A unit of work should appear at only one place in the WBS.

ANSWER: True

3. Project scope management includes the processes involved in defining and controlling what is or is not included in a project.

ANSWER: True

4. The scope management plan can be informal and broad or formal and detailed, based on the needs of the project.

ANSWER: True

6. Information from the project charter provides a basis for further defining the project scope.

ANSWER: True

29. Creating the WBS is a subprocess associated with which process in project scope management? a. planning b. monitoring and controlling c. closing d. executing

ANSWER: a

32. What is a table that lists requirements, their various attributes, and the status of the requirements to ensure that all are addressed referred to as? a. requirements traceability matrix b. Gantt chart c. state transition table d. entity-attribute-value model

ANSWER: a

28. Which action involves normalizing acceptance of the project deliverables and during this phase the key project stakeholders, such as the customer and sponsor for the project, inspect and then formally accept the deliverables? a. Creating scope b. Defining scope c. Controlling scope d. Validating scope

ANSWER: d

33. Which document contains a deliverable-oriented grouping of the work involved in a project that defines the total scope of the project? a. project charter b. business case c. project scope statement d. work breakdown structure

ANSWER: d

37. Which approach for constructing a WBS uses a similar project's WBS as a starting point? a. top-down b. bottom-up c. mind-mapping d. analogy

ANSWER: d

40. Which technique is used for creating a WBS uses branches radiating from a core idea to structure thoughts and ideas instead of writing down tasks in a list or immediately trying to create a structure for tasks? a. analogy b. bottom-up c. top-down d. mind mapping

ANSWER: d

48. Which process involves identifying and modeling business events, who initiated them, and how the system should respond to them? a. Prototyping b. JAD c. RAD d. Use case modeling

ANSWER: d


Set pelajaran terkait

older adult exam 2 practice questions

View Set

Chapter 12: Skin, Hair, and Nails

View Set

Unit 3- Clinical decision making

View Set

U12Ch46 어(魚/漁): fish, to fish (KBC)

View Set

Latin American Relations Midterm

View Set