Project Management Software Exam 1

Lakukan tugas rumah & ujian kamu dengan baik sekarang menggunakan Quizwiz!

Semi-flexible or inflexible constraint

A better approach to scheduling tasks is to use a deadline date rather than a(n) ______.

does not constrain a task

A deadline date:

Phase (Ch 1)

A group of closely related tasks that encompass a major section of your project is a(n) ____________.

Task Priority

A numeric ranking of a task's importance and appropriateness for leveling is called _______.

material resources

A resource calendar does not apply to

Predecessor (Ch 1)

A task whose start or end date determines the start or finish of another task or tasks is a(n) ____________.

Deadline

A(n) _______ is a value you enter for a task that indicates the latest date by which you want the task to be completed.

Assignment

A(n) ________ is the matching of a specific resource to a particular task to do work.

Link (Ch 1)

A(n) ____________ is a logical connection between tasks that controls sequence and dependency.

Project Schedule (Ch 1)

A(n) ____________ is a model of a real project-what you want to happen or what you think will happen.

Template (Ch 1)

A(n) ____________ is a pre-defined file that can be used as a starting point to create a project schedule.

Calendar (Ch 1)

A(n) ____________ is a scheduling tool that determines the standard working time and nonworking time for the project, resources, and tasks.

Exception (Ch 1)

A(n) ____________ is added to the project calendar to denote something different from the standard working times.

Note (Ch 1)

A(n) ____________ is supplemental text that you can attach to a task, resource, or assignment.

Milestone (Ch 1)

A(n) ____________ represents a significant event reached within the project or imposed upon the project.

Tasks (Ch 1)

A(n) ____________ represents the actual individual work activities that must be done to accomplish the final goal.

40

According to the work formula in Microsoft Project, 20 hours task duration x 200% assignment units = _______ hours work.

Cost or Material

Assigning a(n) ______ or ________ resource to a task will not affect the duration of the task.

constraint dates over relationships

By default, Microsoft Project honors:

Delay the start of a specific resource's assignment Delay the start date of an entire task Split up the work on a task

Depending on options you choose, resource leveling might:

Work Resources

Effort-driven scheduling adjusts a task's duration only if you add or remove ________ from a task.

slack

Entering a deadline date has no effect on the scheduling of a summary or subtask, except when the task involves:

material

For which resource is the standard rate listed per tracking unit of consumption?

Overallocated

If a resource is assigned to do more work than can be done within the normal work capacity of the resource, it is ________.

over-allocated

If you assign a resource to more tasks than it can accomplish at its maximum units, the resource is

200%

If you have four electricians who can each work part-time (4 hours rather than 8), what value should you assign to Max. Units for the resource "electrician"?

Work Formula

In Microsoft Project, Duration x Units = Work is known as the ______.

Work

In Microsoft Project, when you assign a human or equipment resource to a task, the result is _______.

work night shift.

It is helpful to assign a base calendar to a group of resources when they all

the information is often confidential.

It is often difficult to get cost information for people resources because

Negative Slack

Microsoft Project honors constraint dates over task relationships, even if this causes ______.

task priorites

Microsoft Project uses_______ to determine which tasks can be delayed in order to resolve periods of resource over allocation.

0

Tasks with a priority of _______ are leveled first.

1000

Tasks with a priority of ________ are never delayed by leveling.

Total Slack

The amount of time a task can be delayed without delaying the project completion date

Units

The capacity of a resource to work is measured in ______.

500

The default task priority value for all tasks is _______.

0 to 1000

The numeric ranking range for task priority is:

Change Working Time

To add vacation days to the calendar for an individual work resource, which dialog box would you use?

Clear the deadline field on the advanced tab of the task information dialog box

What must be done to remove a deadline from a task?

Material Resources

When you assign ________ to tasks, you can track their consumption and cost.

Completion

When you enter a deadline date, Microsoft Project alerts you if the task's _______ moves beyond the deadline.

Relationship

When you link the tasks in a project schedule, you establish a(n) ______ between the tasks.

deadline date

Which of the following allows the most flexibility in scheduling a task?

Must start on

Which of the following is NOT a semi-flexible constraint?

Start-No-Earlier-Than-Finish

Which of the following is NOT a type of task relationship?

DVD Disc

Which of the following is NOT an example of a work resource?

adding a resource note

You can provide additional information about how a resource is scheduled by

Resource Sheet view

You can view information for the individual people who will perform the tasks on the project in the

Duration

_______ is the amount of work periods you expect the task to take to complete.

Resource Leveling

_______ is the process of delaying a resource's work on a task to resolve an overallocation.

Cost Resource

a resource that doesn't depend on the amount of work on a task or the duration of a task

Work Resource

a resource that doesn't depend on the amount of work on a task or the duration of a task

Constraint

a restriction that controls the start or finish date of a task

Inflexible Constraint

a restriction that forces a task to begin or end on a certain date, preventing the rescheduling of a task

Recurring Task

a task that is repeated at specific intervals

Fixed Units

a task type in which the units value does not automatically change

Note

a way of documenting information about resources, tasks, and assignments

Split

an interruption in a task

Material Resource

consumable items used up as the tasks in a project are accomplished

Resource Calendar

defines the working and nonworking time for an individual resource

Base Calendar

specifies default working and nonworking times for a resource, a project, or a task

Free Slack

the amount of time a task can be delayed before it will delay another task

Project Calendar

the base calendar that provides default working times for an entire project

Fully Allocated

the condition of a resource when the total work of its task assignments is exactly equal to that resource's work capacity

Under Allocated

the condition of a resource when the work assigned to a resource is less than the resource's maximum capacity

Max. Units

the maximum capacity of a resource to accomplish tasks

Resources

the people, equipment, money, and materials used to complete the tasks in a project

Critical Path

the series of tasks whose scheduling directly affects the project's finish date

Availability

when and how much of a resource's time can be assigned to work on tasks


Set pelajaran terkait

Chapter 33 - Patients w/ Breast and Female Reproductive Disorders

View Set

Chapter 25: The Baroque in Northern Europe

View Set

Bio 122 Study Guide Chapter 15: The Chromosomal Basis of Inheritance

View Set

Mod C Fluids & Electrolytes/Nutrition HCD and Patho NCLEX style questions

View Set

HESI-Med Surg I final study guide

View Set