System Analysis & Design: Project Management - CH 7: Project Cost Management
What type of estimate is a cost estimation tool that involves estimating individual work items or activities and summing them to get a project total? Answers: a. budgetary b. bottom-up c. analogous d. parametric
bottom-up
What type of estimate is a cost estimation tool used to allocate money into an organization's budget? Answers: a. definitive b. rough order of magnitude c. budgetary d. ballpark
budgetary
Which is true of earned value? Answers: a. It is also known as the planned value. b. It is based solely on the total cost estimate to be spent on an activity. c. It is an estimate of the value of the physical work actually completed. d. It is the actual cost plus the planned cost.
It is an estimate of the value of the physical work actually completed.
It is important for project managers to understand that every cost estimate is unique. Answers: True False
True
The main goal of which process is to produce a cost baseline for measuring project performance and project funding requirements? Answers: a. cost estimating b. cost planning c. cost controlling d. cost budgeting
cost budgeting
What type of estimate is used for making many purchasing decisions for which accurate estimates are required and for estimating final project costs? Answers: a. budgetary b. final c. definitive d. rough order of magnitude
definitive
Which type of estimate should be used if the cost estimate for a project is used a basis for contract awards and performance reporting? Answers: a. definitive b. budgetary c. analogous d. rough order of magnitude
definitive
Which statement best defines cost variance? Answers: a. planned value minus the rate of performance b. rate of performance minus earned value c. earned value minus the actual cost d. planned value plus actual costs
earned value minus the actual cost
What is the purpose of a cost performance index (CPI)? Answers: a. indicate that the planned and actual costs are equal if CPI is more than one b. indicate that a project is under budget if CPI is less than one c. estimate the ratio of earned value to planned value d. estimate the projected cost of completing the project
estimate the projected cost of completing the project
Which process involves developing an approximation of the costs of resources needed to complete a project? Answers: a. estimating costs b. controlling costs c. determining the budget d. finalising the cost baseline
estimating costs
Which process helps develop an accurate projection of a project's financial expenses and benefits? Answers: a. life cycle costing b. fast tracking c. crashing d. critical path analysis
life cycle costing
What does the process of controlling costs primarily involve? Answers: a. finalising the procedures for project costs b. determining a basis for estimates c. managing changes to the project budget d. determining the policies for project costs
managing changes to the project budget
What is the first step in project cost management? Answers :a. allocate project cost estimates to individual material resources b. control project costs and monitor cost performance c. plan how costs will be managed d. develop several estimates of costs for different types of resources
plan how costs will be managed
Soles is a footwear company which has recently set up its store in Ambrosia. To manufacture its products, Soles incurs a range of different costs. Which would be an example of an indirect cost? Answers: a. Salary paid to factory workers b. Electricity used to run its factories c. Cost of machines to produce shoes d. Cost of leather used to manufacture shoes
Electricity used to run its factories
A budgetary estimate is the most accurate of the three types of estimates. Answers: True False
False
A negative schedule variance means that it took less time than planned to perform the work. Answers: True False
False
Analogous estimates are called activity-based costing. Answers: True False
False
In an earned value chart, when the actual cost line is right on or above the earned value line, it indicates that costs are less than planned. Answers: True False
False
Which statement is true of bottom-up estimates? Answers: a. They are time-intensive and expensive to develop. b. They are also known as parametric estimating. c. They are based on the actual cost of a previous, similar project. d. They are most accurate when they involve large, extensive work items.
They are time-intensive and expensive to develop.
Which statement is true of tangible costs? Answers: a. They are difficult to quantify. b. They cannot be calculated in monetary terms. c. They can be easily measured. d. Their examples include goodwill and prestige.
They can be easily measured.
A cost management plan can include organizational procedures links, control thresholds, and process descriptions. Answers: True False
True
Definitive estimates are made one year or less prior to project completion. Answers: True False
True
IT project managers must be able to present and discuss project information both in financial and technical terms. Answers: True False
True
In a bottom-up estimate, the size of the individual work items is one of the factors that drives the accuracy of the estimates. Answers: True False
True
One of the reasons why project cost estimates are inaccurate is because human beings are biased toward underestimation. Answers: True False
True
Parametric models are reliable when the models are flexible in terms of the project's size. Answers: True False
True
Which type of estimate uses the actual cost of a previous, similar project as the basis for estimating the cost of the current project? Answers: a. definitive estimates b. bottom-up estimates c. analogous estimates d. parametric estimates
analogous estimates
Intangible costs can be easily measured in monetary terms. Answers: True False
False
Overrun is the additional percentage amount by which estimates exceed actual costs. Answers: True False
False
Which is true of the schedule performance index (SPI)? Answers: a. It is the ratio of planned value to actual costs. b. It can be used to estimate the projected time to complete the project. c. It means that a project is behind schedule if an SPI is greater than one. d. It means that a project is ahead of schedule if SPI is lesser than one or hundred percent.
It can be used to estimate the projected time to complete the project
What is another term used for budget? Answers: a. earned value b. actual cost c. indirect cost d. planned value
planned value
How are profits best defined? Answers: a. revenues plus expenses b. expenses plus net income c. costs plus revenues d. revenues minus expenditures
revenues minus expenditures
Which method is used for determining the estimated annual costs and benefits for a project? Selected Answers: a. Cash flow analysis b. Requirements analysis c. Critical path analysis d. Present value analysis
Cash flow analysis
The primary output of the planning cost management process is a change request. Answers: True False
False
Spreadsheets are a common tool for cost estimating, cost budgeting, and cost control. Answers: True False
Selected Answer:True
The formulas for variances and indexes start with EV, the earned value. Answers: True False
True
Which process results in a cost baseline as a main output?
cost budgeting
Work performance information and cost forecasts are main outputs of which process? Answers: a. cost estimating b. cost budgeting c. cost pricing d. cost control
cost control
Which is an output of the process of controlling costs? Answers: a. project funding requirements b. cost forecasts c. basis of estimates d. scope baselines
cost forecasts
Which statement best defines schedule variance? Selected Answers: a. earned value minus the actual cost b. planned value plus the rate of performance c. planned value plus the earned value d. earned value minus the planned value
earned value minus the planned value
Estimates should become more accurate as time progresses. Answers: True False
True
Newtech Inc. hires John for the position of a software programmer to work on their new project. Salary paid to John by Newtech Inc. would be an example of which type of costs? Answers: a. indirect b. direct c. intangible d. sunk
direct
It is important for project managers to focus on indirect costs because they can be easily controlled. Answers: True False
False
Which reserves allow for future situations that are unpredictable? Answers: a. Known unknowns b. Management reserves c. Contingency reserves d. Cost baseline reserves
Management reserves
Determining the budget involves allocating the project cost estimate to individual work items over time. Answers: True False
True
What is a rough order of magnitude estimate also referred to as? Answers: a. definitive b. budgetary c. ballpark d. final
ballpark
Which statement is true regarding indirect costs? Answers: a. those that can be easily controlled by managers. b. those that cannot be allocated to projects. c. not directly related to the products or services of a project. d. directly related to performing the project.
not directly related to the products or services of a project.
Analogous estimates are the most accurate technique to estimate costs. Answers: True False
False
Contingency reserves are also known as unknown unknowns. Answers: True False
False
If cost variance is a positive number, it means that performing the work costs more than planned. Answers: True False
False
If the cost performance index (CPI) is less than 100 percent, the project is under budget. Answers: True False
False
When deciding what projects to invest in or continue, one should include sunk costs. Answers: True False
False
Which costs are difficult to measure in monetary terms? Answers: a. Fixed costs b. Direct costs c. Tangible costs d. Intangible costs
Intangible costs
Which statement is true of a order of magnitude estimate? Answers:a. Its timeframe is always less than a year prior to project completion. b. It is used to allocate money into an organization's budget. c. It is a type of estimate that is done in the final stages of a project. d. It provides an estimate of what a project will cost.
It provides an estimate of what a project will cost.
Which is most likely to be a reason for inaccuracies in information technology cost estimates? Answers: a. Estimates take a long time to be worked out. b. Only software development provides the scope for estimates to be accurate. c. People lack estimating experience. d. Human beings are biased toward overestimation.
People lack estimating experience.
Which statement is true of contingency reserves? Answers: a. They are also known as unknown unknowns. b. They allow for future situations that can be partially planned for. c. They allow for dollar amounts to be used to cover existing, fixed costs. d. They are not included in a cost baseline.
They allow for future situations that can be partially planned for.
Which statement is true of analogous estimates? Answers: a. They are most reliable when previous projects are similar in fact with current projects. b. Their main disadvantage is that they cost more than other techniques. c. They use project characteristics in a mathematical model to estimate project costs. d. They are the only technique which do not require expert judgement.
They are most reliable when previous projects are similar in fact with current projects.
A schedule performance index of one means that the project is on schedule. Answers: True False
True
Budgetary estimates are made even before a project is officially started. Answers: True False
True
If an important supplier goes out of business, management reserves can be set aside to cover the resulting costs. Answers: True False
True
Project managers must conduct cash flow analysis to determine net present value. Answers: True False
True
Supporting details for an estimate include the ground rules and assumptions used in creating the estimate. Answers: True False
True
The project management plan and project funding requirements are inputs of the process of controlling costs. Answers: True False
True
Which process involves allocating the overall cost estimate to individual work items to establish a baseline for measuring performance? Answers: a. determining the budget b. controlling costs c. finalizing policies for project costs d. estimating costs
determining the budget
Variances are calculated by subtracting the actual cost from which value? Answers: a. schedule variance b. rate of performance c. planned value d. earned value
earned value
Which type of estimating uses project characteristics in a mathematical model to estimate project costs?
parametric
What type of management includes the processes required to ensure that a project team completes a project within an approved budget? Answers: a. project quality management b. project cost management c. project scope management d. project time management
project cost management
Good Earth, a company manufacturing packaged food products, sets up its stores in Baltonia. However, a year later, the company closes the store down due to high operating costs. In such a scenario, the money spent in paying for the rent of the store in Baltonia would be an example of which costs? Answers: a. sunk b. intangible c. recurring d. direct
sunk
What term is used for analogous estimates? Answers: a. top-down b. bottom-up c. parametric d. budgetary
top-down
Which is an input of the process of controlling costs? Answers: a. change requests b. scope baseline c. work performance data d. cost forecasts
work performance data