Firms that service customers from finished goods inventory are known as which of the following
make-to-stock.
The ____ relationship identifies the restrictions imposed by product design and process technologies.
precedence
The calculated theoretical number of workstations should be _____.
rounded up to the next highest integer.
In a project layout, a high degree of _____ ____ is common.
task ordering
Which the following describes the layout for items produced through a fixed sequence of workstations?
Assembly line
A computer manufacturer offers 3 types of hard disk drives, 2 types of monitors, 4 types of batteries, and 5 choices of operating systems. How many total combinations are possible using these choices?
120 (3 x 2 x 4 x 5 = 120)
The efficiency of an assembly-line balance must always be less than or equal to
100%
Which of the following products would use a project layout?
Bridge
______ is used to avoid expensive shut downs by operating 24 hours a day.
Continuous process
Inventory turn
Cost of goods sold/Average inventory
Which of the following is not one of the five basic work flow structures?
Flow line
Which layout format groups machines to work on products that have similar processing requirements?
Manufacturing cell
Which of the following is one of the dimensions depicted on a product-process matrix?
Volume
In an organizational context, break-even analysis is also known as
cost-volume-profit analysis
A manufacturing cell is generally made up of ____ machines.
dissimilar
Inventory turn is calculated by
dividing cost of goods sold by average inventory value.
When parts are moved on a conveyor that passes a series of workstations in a uniform time interval, this is called the ___.
workstation cycle time
The time between successive units coming off the end of an assembly line is referred to as
workstation cycle time.
Standardization on the product-process matrix refers to
variations in the product.
Which are characteristics of a continuous process line?
- Highly automated machinery is used. - May operate 24 hours a day. - Shutdowns can be expensive.
Which of the following statements about inventory measures is TRUE?
- Inventory turn compares cost of goods sold to average inventory. - Days-of-supply measures how long (on average) a firm's inventory can support sales.
Identify the true statements about assembly-line and continuous process layouts.
- Often, the item being produced in a continuous process is a liquid or chemical that actually flows through the system. - In a continuous process, a product moves continuously through the process. - In an assembly line, a product goes through a progressive set of steps.
Customer order decoupling points
- can impact inventory investment. - determine lead times.
Lead time can vary based on
- location of the manufacturing facility - customization of the product being produced.
Rank the production process layouts from lowest- to highest-volume (top to bottom).
1. Project 2. Workcenter 3. Manufacturing cell 4.. Assembly line
Production process
1. Sourcing 2. Making 3. Delivering
Last year a firm had an average inventory of $1,500,000 and the cost of goods sold was $3,750,000. What was the days-of-supply last year?
146 (avg inventory / cogs) x 365 = 146
There are _____ dimensions depicted on a product-process matrix.
2
Last year a firm had an average inventory of $1,500,000 and the cost of goods sold was $3,750,000. What was the inventory turn last year?
2.6 (cost of goods sold / avg inventory)
An assembly line must produce 1,000 units in an 8 hour day. Assuming the line operates continuously, what is the required workstation cycle time?
28.8 seconds
If the sum of all task times is 100 seconds and the required cycle time is 21 seconds, what is the theoretical minimum number of workstations?
5 (sum of task times / required cycle time)
For an assembly-line system with 6 workstations, the cycle time is 27 seconds and the sum of task times is 120 seconds. What is the efficiency of this balance?
74.1% (sum of task time / (actual # of stations x cycle time))
Which of the following is NOT true about a workcenter layout?
A workcenter layout is commonly used for systems with high production volumes.
Which common layout format refers to the progressive build of a product?
Assembly line
Which layout moves product from workstation to workstation at a controlled rate?
Assembly line
Days-of-Supply
Average Inventory/Cost of goods sold x 365
Which process layout is best used for manufacturing liquids?
Continuous
Which of the following is NOT a step in the process of developing a manufacturing cell?
Determine which machines perform the same process.
True or false: The total work at a workstation is equal to the sum of all tasks to complete a product.
False
Little's law relates inventory, throughput rate, and flow time as
Inventory = Throughput rate x Flow time
The issue of balancing the level of finished inventory against the level of service to the customer occurs in which type of firm?
Make-to-stock
Which type of firm invests in lean manufacturing programs in order to improve customer service levels for a given inventory investment?
Make-to-stock
In which production system does the product remain in one place while resources (such as workers or equipment) travel to the product when needed?
Project layout
______ techniques are typically used to manage production processes that follow a project layout structure.
Project management
Which of the following is not a step in the process to balance an assembly line?
Randomly assign tasks to workstations.
Which of the following describes the step where parts are procured from one or more suppliers?
Sourcing
Total average value of inventory
Sum of raw material, work-in-process, and finished goods inventory
True or false: The longest required task time often defines the shortest possible workstation cycle time for production.
True
True or false: Typically, there is a trade-off where quicker response to customer demand comes at the expense of greater inventory investment.
True
A _____ line layout can increase operator access and improve workstation time.
U-shaped
Which of the following is not a way to reduce the required time for a task?
Use a less skilled worker
Firms invest in lean manufacturing programs in order to
achieve high customer service with minimum levels of inventory investment.
Workcenters with large amounts of interdepartmental traffic are often placed
adjacent to each other.
A flexible line layout may improve assembly-line balance by
allowing work sharing among employees.
In an organizational context, the main purpose of break-even analysis is to
ascertain the quantity at which the initial investment starts to make a profit
An _____ arranges processes according to the sequence of steps by which the product is manufactured.
assembly line
The point in the supply chain where inventory is positioned to allow the preceding processes to operate independently is the
customer order decoupling point.
The required workstation cycle time is determined by
dividing the production time per day by the required output per day.
The time required to respond to a customer order is known as
lead time.
The practice of achieving high levels of customer service with a minimal inventory investment is known as ____ manufacturing.
lean
The long-term relationship between inventory, throughput, and flow time is mathematically related using ______'s law.
little
A map showing the flow of materials through a manufacturing system is known as a ____-to-____ process map.
make stock
When attempting to balance an assembly-line, the amount of idle time across workstations should be
minimized
If inventory turn is known, days-of-supply is calculated by
multiplying the inverse of inventory turn by 365 days.
In an assemble-to-order system, the total number of unique combinations possible is calculated by
multiplying the number of options for each choice together.
Workcenters are often structured to___________ the movement of material.
optimize
On an assembly-line, the order in which tasks must be performed is called the
precedence relationship
The ____-____ matrix shows when different production process types are used in relation to product volume and standardization.
product process
To determine the required workstation cycle time, an analyst needs to know the ____ _____ per day and the required ____ per day (in units).
production time, output
A production process map is built by
tracking the flow of material through the system.
In a _____ layout, machines are grouped according to type or function and parts travel to the appropriate location for processing.
workcenter