Test - TST 102 Module 8 Exam: Operational Test and Evaluation
One of the key purposes of Operational Test & Evaluation (OT&E) is to determine a system's operational effectiveness and operational suitability.
True
One of the key differences between OT&E and DT&E is _____. Select the correct answer.
DT&E is concerned with maturing the engineering design and manufacturing processes.
Advantages of a concurrent DT/OT strategy include all of the following EXCEPT _____. Select the correct answer.
Increasing the competition for access to limited test articles
The purpose of ______ is to assess the effectiveness and suitability of a system early in development so as to provide user feedback to the design and development process. Select the correct answer.
Operational Assessment (OA)
OT&E of the Short-Range Anti-Tank Weapon (SRAW) showed that it could not hit its target when operated by typical users in an operational environment. This would be considered a deficiency in the area of _____. Select the correct answer.
Operational Effectiveness
Early OT&E activities may require support from system contractors, program office personnel, DT&E elements, and operational forces.
True