quiz number two
using the assembly line balancing procedure which of the following is the theoretical minimum number of workstation if the test times for the six tasks that make up the job are 4, 6, 7, 2, 6, and 5 minutes, and the cycle time is 10 minutes
(4 + 6 + 7 + 2 + 6 + 5)/10=3
which of the following is not considered a major work flow structure
fabrication
according to Littles law which of the following can be used to estimate work-in-process inventory
throughput rate x flow time
You just determined the actual number of workstations that will be used on an assembly line to be 6 using the assembly line balancing procedure. The cycle time of the line is 5 minutes and the sum of all tasks required on the line is 25 minutes. which of the following is the correct value for the resulting lines efficiency
25/6×5=0.833
using the assembly line balancing procedure, which of the following is required cycle time in minutes per unit if the daily production time is 480 minutes and the required daily output is 50 units
480/50 equals 9.6
which of the following is a basic type of process structure
Workcenter
using the assembly line balancing procedure, which of the following is the required cycle time if the production time in minutes per day is 1440 and the required output per day in units is 2000
minutes per day/required output per day 1440/2000=.72
the placement of which of the following is not determined by production process organization decisions
emergency exits
when balancing an assembly line, which of the following is not a way to reduce the longest task time below the required workstations cycle time
speed up the assembly line transfer mechanism