ISDS 361
Task Notes
..... are used to write and review notes about the selected task.
Burn down
A _______ report shows thenumber of hours of work completed on the project
Critical Path
A _______________ for a project is the series of activites that determine the earliest time by which the project can be completed
False
A light blue pushpin in the task mode column indicates the auto-scheduling of the task
False
A recurring task is indicated on the Gantt chart with a circular symbol.
Planning
Creating the WBS is a subprocess associated with the ______ process in project sope management.
Task Sheet
In M.S. Project .... provides a list of scheduled tasks in the project.
Resource Sheet
In M.S. Project ..... is a place to enter employee hours available and their payrate for that project.
Change Working times
In M.S. Project ..... is an option to take in order to record your available working hours.
Project information
In M.S. Project ...... refers to the option you use to enter the project finish date if the project is required to finish by a deadline.
Resource Form
In M.S. Project ______ provides the task information of members assigned to a project.
Time Line
In M.S. Project placing the schedule of tasks on the ________ shows the start and finish time of a project in a calender format.
Task Information Dialog Box
In M.S. Project the ________ appears when you right click on a task.
Blank
In M.S. Project, a _______ is displayed when a subtask is 25% completed.
Linked
In MS project tasks need to be ________ in order to determine the start date of a project
Horizontal Boxed brackets
In the Gantt chart the ______ displays the grouping of subtasks.
timescale
In the view tav of the gant charty the ________ option helps you to update a gantt chart for a specific period
Direct
Newtech Inc hires jophn for the position of a software programmer to work on their new project, Salery paid to john by Newtech Inc would be an example of _______ costs
True
The project summary entryu displayes the name of the project file, total duration of the project, its startdate, and finish date
True
The red men symbol in the Gantt CHart indicates that a labor resource has been under-allocated
Milestone
To emphisize the importance of certain events or accomplishments on a project a _________ can be created on the Gantt chart
Gantt Charts
____ provide(s) a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a calendar format.
filter
in MS project it is possible to identify the incomplete tasks by using the ___ option
dependencies
the arrows connecting the horizontal blue bars on the Gantt chart reresent the ________ between the tasks
a line
when a task is comleted at a 100% a ________ is place on the bar for the task