Task Notes

..... are used to write and review notes about the selected task.

Burn down

A _______ report shows thenumber of hours of work completed on the project

Critical Path

A _______________ for a project is the series of activites that determine the earliest time by which the project can be completed

False

A light blue pushpin in the task mode column indicates the auto-scheduling of the task

False

A recurring task is indicated on the Gantt chart with a circular symbol.

Planning

Creating the WBS is a subprocess associated with the ______ process in project sope management.

Task Sheet

In M.S. Project .... provides a list of scheduled tasks in the project.

Resource Sheet

In M.S. Project ..... is a place to enter employee hours available and their payrate for that project.

Change Working times

In M.S. Project ..... is an option to take in order to record your available working hours.

Project information

In M.S. Project ...... refers to the option you use to enter the project finish date if the project is required to finish by a deadline.

Resource Form

In M.S. Project ______ provides the task information of members assigned to a project.

Time Line

In M.S. Project placing the schedule of tasks on the ________ shows the start and finish time of a project in a calender format.

Task Information Dialog Box

In M.S. Project the ________ appears when you right click on a task.

Blank

In M.S. Project, a _______ is displayed when a subtask is 25% completed.

Linked

In MS project tasks need to be ________ in order to determine the start date of a project

Horizontal Boxed brackets

In the Gantt chart the ______ displays the grouping of subtasks.

timescale

In the view tav of the gant charty the ________ option helps you to update a gantt chart for a specific period

Direct

Newtech Inc hires jophn for the position of a software programmer to work on their new project, Salery paid to john by Newtech Inc would be an example of _______ costs

True

The project summary entryu displayes the name of the project file, total duration of the project, its startdate, and finish date

True

The red men symbol in the Gantt CHart indicates that a labor resource has been under-allocated

Milestone

To emphisize the importance of certain events or accomplishments on a project a _________ can be created on the Gantt chart

Gantt Charts

____ provide(s) a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a calendar format.

filter

in MS project it is possible to identify the incomplete tasks by using the ___ option

dependencies

the arrows connecting the horizontal blue bars on the Gantt chart reresent the ________ between the tasks

a line

when a task is comleted at a 100% a ________ is place on the bar for the task


Related study sets

Chapter One: Introduction to the Human Body

View Set

Adolescent Development Chapter 1,2,3,4,7,12

View Set

Chapter One: Understanding Computer Programming Exam Prep

View Set

Health Assessment: Chapter 20: Peripheral Vascular and Lymphatic System

View Set